A.    Environmental Matters
Eversource, CL&P, NSTAR Electric and PSNH are subject to environmental laws and regulations intended to mitigate or remove the effect of past operations and improve or maintain the quality of the environment. These laws and regulations require the removal or the remedy of the effect on the environment of the disposal or release of certain specified hazardous substances at current and former operating sites. Eversource, CL&P, NSTAR Electric and PSNH have an active environmental auditing and training program and each believes it is substantially in compliance with all enacted laws and regulations.

The number of environmental sites and related reserves for which remediation or long-term monitoring, preliminary site work or site assessment is being performed are as follows:
 
As of March 31, 2019
 
As of December 31, 2018
 
Number of Sites
 
Reserve
(in millions)
 
Number of Sites
 
Reserve
(in millions)
Eversource
59

 
$
64.8

 
60

 
$
64.7

CL&P
15

 
5.6

 
15

 
5.4

NSTAR Electric
15

 
10.5

 
16

 
10.9

PSNH
9

 
5.3

 
9

 
5.4



Included in the Eversource number of sites and reserve amounts above are former MGP sites that were operated several decades ago and manufactured gas from coal and other processes, which resulted in certain by-products remaining in the environment that may pose a potential risk to human health and the environment, for which Eversource may have potential liability.  The reserve balances related to these former MGP sites were $50.6 million and $50.1 million as of March 31, 2019 and December 31, 2018, respectively, and related primarily to the natural gas business segment.

These reserve estimates are subjective in nature as they take into consideration several different remediation options at each specific site.  The reliability and precision of these estimates can be affected by several factors, including new information concerning either the level of contamination at the site, the extent of Eversource's, CL&P's, NSTAR Electric's and PSNH's responsibility for remediation or the extent of remediation required, recently enacted laws and regulations or changes in cost estimates due to certain economic factors.  It is possible that new information or future developments could require a reassessment of the potential exposure to required environmental remediation.  As this information becomes available, management will continue to assess the potential exposure and adjust the reserves accordingly.

B.     Long-Term Contractual Arrangements
On December 28, 2018, under Public Act 17-3, "An Act Concerning Zero Carbon Procurement," DEEP selected the Millstone Nuclear Power Station generation facility, along with smaller generation facilities, in DEEP’s zero-carbon request for proposal. CL&P and UI were directed by DEEP to enter into ten-year contracts to purchase a combined total of approximately 9 million MWh annually from the Millstone generation facility. On March 15, 2019, CL&P and UI each signed a ten-year contract with the owner of Millstone Nuclear Power Station in order to purchase a combined amount of approximately 50 percent of the facility's output (approximately 40 percent by CL&P). The Millstone Nuclear Power Station has a 2,112 MW nameplate capacity. The parties filed the contract with PURA on March 29, 2019 for review and approval. A decision from PURA is expected in the third quarter of 2019.

The significant output of the generation facility, the contract period, and the pricing will result in a significant multi-billion dollar commitment. We plan to sell the energy purchased under this contract into the market and use the proceeds from these energy sales to offset the contract costs.  As the net costs under this contract will be recovered from customers in future rates, the contract will not have an impact on the net income of CL&P.

C.    Guarantees and Indemnifications
In the normal course of business, Eversource parent provides credit assurances on behalf of its subsidiaries, including CL&P, NSTAR Electric and PSNH, in the form of guarantees.

Eversource parent issued a guaranty on behalf of its subsidiary, NPT, under which, beginning at the time the Northern Pass Transmission line goes into commercial operation, Eversource parent will guarantee the financial obligations of NPT under the TSA with HQ in an amount not to exceed $25 million.  Eversource parent's obligations under the guaranty expire upon the full, final and indefeasible payment of the guaranteed obligations. Eversource parent has also entered into a guaranty on behalf of NPT under which Eversource parent will guarantee NPT's obligations under a facility with a financial institution pursuant to which NPT may request letters of credit in an aggregate amount of up to approximately $14 million.

Management does not anticipate a material impact to net income or cash flows as a result of these various guarantees and indemnifications.  The following table summarizes Eversource parent's exposure to guarantees and indemnifications of its subsidiaries to external parties, as of March 31, 2019:  
Company
 
Description
 
Maximum Exposure
(in millions)
 
Expiration Dates
On behalf of subsidiaries:
 
 
 
 
 
 
Eversource Investment LLC
 
Revolution Wind and South Fork Wind (1)
 
$
113.9

 
-
Various
 
Surety Bonds (2)
 
32.0

 
2019 - 2021
Rocky River Realty Company and Eversource Service
 
Lease Payments for Real Estate
 
7.3

 
2024
Bay State Wind LLC
 
Real Estate Purchase
 
2.5

 
2019

(1) 
Eversource parent issued a declining balance guaranty on behalf of its subsidiary, Eversource Investment LLC. Eversource parent will guarantee, as a primary obligor, the financial obligations, primarily all post-closing payment obligations of Eversource Investment LLC, under the Sale and Purchase Agreement and an Irrevocable Equity Commitment Letter with Ørsted. Eversource parent's obligations under the guaranty expire upon the full, final and indefeasible payment of the guaranteed obligations.

(2) 
Surety bond expiration dates reflect termination dates, the majority of which will be renewed or extended.  Certain surety bonds contain credit ratings triggers that would require Eversource parent to post collateral in the event that the unsecured debt credit ratings of Eversource parent are downgraded.  

Eversource parent issued a declining balance guaranty on behalf of its subsidiary, Eversource Gas Transmission LLC, to guarantee the payment of the subsidiary's authorized capital contributions for its investment in the Access Northeast project. As of March 31, 2019, the amount of the Access Northeast project capital contribution guaranty was $184.8 million. On April 1, 2019, pursuant to a provision in the partnership agreement jointly entered into by Eversource, Enbridge, Inc. and National Grid plc, through Algonquin Gas Transmission, LLC, the Access Northeast project was terminated. The rights under the guaranty were released, which terminated the obligation of Eversource parent.

D.     Spent Nuclear Fuel Obligations - Yankee Companies
CL&P, NSTAR Electric and PSNH have plant closure and fuel storage cost obligations to the Yankee Companies, which have each completed the physical decommissioning of their respective nuclear facilities and are now engaged in the long-term storage of their spent fuel. The Yankee Companies fund these costs through litigation proceeds received from the DOE and, to the extent necessary, through wholesale, FERC-approved rates charged under power purchase agreements with several New England utilities, including CL&P, NSTAR Electric and PSNH. CL&P, NSTAR Electric and PSNH, in turn recover these costs from their customers through state regulatory commission-approved retail rates. The Yankee Companies collect amounts that management believes are adequate to recover the remaining plant closure and fuel storage cost estimates for the respective plants. Management believes CL&P and NSTAR Electric will recover their shares of these obligations from their customers. PSNH has recovered its total share of these costs from its customers.

Spent Nuclear Fuel Litigation:
The Yankee Companies have filed complaints against the DOE in the Court of Federal Claims seeking monetary damages resulting from the DOE's failure to provide for a permanent facility to store spent nuclear fuel pursuant to the terms of the 1983 spent fuel and high level waste disposal contracts between the Yankee Companies and the DOE. The court had previously awarded the Yankee Companies damages for Phase I, II and III of litigation resulting from the DOE's failure to meet its contractual obligations. These Phases covered damages incurred in the years 1998 through 2012, and the awarded damages have been received by the Yankee Companies with certain amounts of the damages refunded to their customers.

DOE Phase IV Damages - On May 22, 2017, each of the Yankee Companies filed subsequent lawsuits against the DOE in the Court of Federal
Claims. The Yankee Companies sought monetary damages totaling $104.4 million for CYAPC, YAEC and MYAPC, resulting from the DOE's failure to begin accepting spent nuclear fuel for disposal covering the years from 2013 to 2016 (“DOE Phase IV”). On February 21, 2019, the Yankee Companies received a partial summary judgment and partial final judgment in their favor for the undisputed amount of monetary damages of $103.2 million. The court awarded CYAPC, YAEC and MYAPC damages of $40.7 million, $28.1 million and $34.4 million, respectively. The DOE did not appeal the court's judgment and the decision became final on April 23, 2019. The DOE Phase IV trial for the $1.2 million of remaining damages is expected to begin in June 2019.

E.    FERC ROE Complaints
Four separate complaints have been filed at the FERC by combinations of New England state attorneys general, state regulatory commissions, consumer advocates, consumer groups, municipal parties and other parties (collectively the "Complainants"). In each of the first three complaints, filed on October 1, 2011, December 27, 2012, and July 31, 2014, respectively, the Complainants challenged the NETOs' base ROE of 11.14 percent that had been utilized since 2005 and sought an order to reduce it prospectively from the date of the final FERC order and for the separate 15-month complaint periods. In the fourth complaint, filed April 29, 2016, the Complainants challenged the NETOs' base ROE billed of 10.57 percent and the maximum ROE for transmission incentive ("incentive cap") of 11.74 percent, asserting that these ROEs were unjust and unreasonable.

The ROE originally billed during the period October 1, 2011 (beginning of the first complaint period) through October 15, 2014 consisted of a base ROE of 11.14 percent and incentives up to 13.1 percent. On October 16, 2014, the FERC set the base ROE at 10.57 percent and the incentive cap at 11.74 percent for the first complaint period. This was also effective for all prospective billings to customers beginning October 16, 2014. This FERC order was vacated on April 14, 2017 by the U.S. Court of Appeals for the D.C. Circuit (the "Court").

All amounts associated with the first complaint period have been refunded, which totaled $38.9 million (pre-tax and excluding interest) at Eversource and reflected both the base ROE and incentive cap prescribed by the FERC order. The refund consisted of $22.4 million for CL&P, $13.7 million for NSTAR Electric and $2.8 million for PSNH.

Eversource has recorded a reserve of $39.1 million (pre-tax and excluding interest) for the second complaint period as of March 31, 2019. This reserve represents the difference between the billed rates during the second complaint period and a 10.57 percent base ROE and 11.74 percent incentive cap. The reserve consisted of $21.4 million for CL&P, $14.6 million for NSTAR Electric and $3.1 million for PSNH as of March 31, 2019.

On October 16, 2018, FERC issued an order on all four complaints describing how it intends to address the issues that were remanded by the Court. FERC proposed a new framework to determine (1) whether an existing ROE is unjust and unreasonable and, if so, (2) how to calculate a replacement ROE. The parties to these proceedings were directed to submit briefs on this new proposed framework and how they would apply the proposed framework in each of the four complaint proceedings. Initial briefs were filed by the NETOs, Complainants and FERC Trial Staff on January 11, 2019 and reply briefs were filed on March 8, 2019. The NETOs' brief was supportive of the overall ROE methodology determined in the October 16, 2018 order provided the FERC does not change the proposed methodology or alter its implementation in a manner that has a material impact on the results.

The FERC order included illustrative calculations for the first complaint using FERC's proposed frameworks with financial data from that complaint. Those preliminary calculations indicated that for the first complaint period, for the NETOs that FERC concludes are of average financial risk, (1) a preliminary range of presumptively just and reasonable base ROEs is 9.60 percent to 10.99 percent; (2) the pre-existing base ROE of 11.14 percent is therefore unjust and unreasonable; (3) the preliminary just and reasonable base ROE is 10.41 percent; and (4) the preliminary incentive cap on total ROE is 13.08 percent.

If the results of these illustrative calculations were included in a final FERC order for each of the complaint periods, then a 10.41 percent base ROE and a 13.08 percent incentive cap would not have a significant impact on our financial statements for all of the complaint periods.

Although the order provided illustrative calculations, FERC stated that these calculations are merely preliminary. The FERC’s preliminary calculations are not binding and do not represent what we believe to be the most likely outcome of a final FERC order, as changes to the methodology by FERC are possible as a result of the parties’ arguments and calculations in the briefing process. Until FERC issues a final decision on each of these four complaints, there is significant uncertainty, and at this time, the Company cannot reasonably estimate a range of gain or loss for any of the four complaint proceedings. The October 16, 2018 FERC order or the 2019 briefs did not provide a reasonable basis for a change to the reserve or recognized ROEs for any of the complaint periods.

Eversource, CL&P, NSTAR Electric and PSNH currently record revenues at the 10.57 percent base ROE and incentive cap at 11.74 percent established in the October 16, 2014 FERC order.

The average impact of a 10 basis point change to the base ROE for each of the 15-month complaint periods would affect Eversource's after-tax earnings by approximately $3 million.

F.    Eversource and NSTAR Electric Boston Harbor Civil Action
On July 15, 2016, the United States Attorney on behalf of the United States Army Corps of Engineers filed a civil action in the United States District Court for the District of Massachusetts under provisions of the Rivers and Harbors Act of 1899 and the Clean Water Act against NSTAR Electric, HEEC, and the Massachusetts Water Resources Authority (together with NSTAR Electric and HEEC, the "Defendants").  The action alleged that the Defendants failed to comply with certain permitting requirements related to the placement of the HEEC-owned electric distribution cable beneath Boston Harbor.  The action sought an order to compel HEEC to comply with cable depth requirements in the United States Army Corps of Engineers' permit or alternatively to remove the electric distribution cable and cease unauthorized work in U.S. waterways.  The action also sought civil penalties and other costs.

The parties reached a settlement pursuant to which HEEC agreed to install a new 115kV distribution cable across Boston Harbor to Deer Island, utilizing a different route, and remove portions of the existing cable. Upon the installation and completion of the new cable and the removal of the portions of the existing cable, all issues surrounding the current permit from the United States Army Corps of Engineers are expected to be resolved, and such litigation is expected to be dismissed with prejudice.

NSTAR Electric agreed to provide a rate base credit of $17.5 million to the Massachusetts Water Resources Authority for the new cable. This negotiated credit resulted in the initial $17.5 million of construction costs on the new cable being expensed as incurred, all of which was fully expensed in 2018. Construction of the new cable is underway and is expected to be completed in 2019.