XML 94 R66.htm IDEA: XBRL DOCUMENT v3.7.0.1
COMMITMENTS AND CONTINGENCIES - FERC ROE Complaints (Details) - USD ($)
$ in Millions
6 Months Ended 15 Months Ended 30 Months Ended
Jun. 08, 2017
Apr. 14, 2017
Apr. 29, 2016
Jun. 30, 2017
Mar. 26, 2014
Apr. 14, 2017
FERC ROE First, Second and Third Complaints [Member]            
Loss Contingencies [Line Items]            
Base ROE percentage challenged by complainants 11.14%     11.14%    
Percentage of maximum ROE for any incentive project 13.50%          
Period of billing of reinstated ROE       60 days    
FERC ROE Complaints [Member]            
Loss Contingencies [Line Items]            
Period of complaint       15 months    
Basis point change       10.00%    
Estimate of possible loss for each 10 basis point change to base ROE       $ 3.0    
FERC ROE Fourth Complaint [Member]            
Loss Contingencies [Line Items]            
Base ROE percentage of complaint period     10.57%      
Maximum percentage cap of ROE for incentive projects     11.74%      
Loss contingency, estimate of possible earnings impact       $ 0.0    
FERC ROE First Complaint [Member]            
Loss Contingencies [Line Items]            
Base ROE percentage challenged by complainants   11.14%   10.57%    
Percentage of maximum ROE for any incentive project       11.74%   11.74%
Loss contingency, estimate of possible earnings impact       $ 0.0    
FERC ROE Second Complaint [Member]            
Loss Contingencies [Line Items]            
Base ROE percentage of complaint period         10.57%  
Percentage of maximum ROE for any incentive project         11.74%  
Loss contingency, estimate of possible earnings impact       39.1    
The Connecticut Light And Power Company [Member] | FERC ROE Second Complaint [Member]            
Loss Contingencies [Line Items]            
Loss contingency, estimate of possible earnings impact       21.4    
NSTAR Electric Company [Member] | FERC ROE Second Complaint [Member]            
Loss Contingencies [Line Items]            
Loss contingency, estimate of possible earnings impact       8.5    
Public Service Company Of New Hampshire [Member] | FERC ROE Second Complaint [Member]            
Loss Contingencies [Line Items]            
Loss contingency, estimate of possible earnings impact       3.1    
Western Massachusetts Electric Company [Member] | FERC ROE Second Complaint [Member]            
Loss Contingencies [Line Items]            
Loss contingency, estimate of possible earnings impact       $ 6.1