Property Plant And Equipment [Line Items]    
Project Cost $ 121 $ 36
Acquisition of Solar Project Madison in Virginia    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2020-07  
Date Agreement Closed 2020-07  
Project Cost [1] $ 130  
Date of Commercial Operations Expected 2023  
MW Capacity | MW 62  
Acquisition of Solar Project Atlanta Farms in Ohio    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2022-03  
Date Agreement Closed May 2022  
Project Cost [1] $ 390  
Date of Commercial Operations [2] Expected split  
MW Capacity | MW 200  
Acquisition of Solar Project Hardin II in Ohio    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2020-08  
Date Agreement Closed Expected 2022  
Project Cost [1] $ 295  
Date of Commercial Operations Expected 2023  
MW Capacity | MW 150  
Virginia Electric and Power Company    
Property Plant And Equipment [Line Items]    
Project Cost $ 38 $ 19
Virginia Electric and Power Company | Acquisition of Solar Project Pumpkinseed in Virginia    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2020-05  
Date Agreement Closed 2020-05  
Project Cost [3] $ 140  
Date of Commercial Operations Expected 2022  
MW Capacity | MW 60  
Virginia Electric and Power Company | Acquisition of Solar Project Bookers Mill in Virginia    
Property Plant And Equipment [Line Items]    
Date Agreement Entered 2021-02  
Date Agreement Closed 2021-06  
Project Cost [3] $ 230  
Date of Commercial Operations Expected 2023  
MW Capacity | MW 127  
[1]

Includes acquisition cost.

[2] Expected to be split between 2023 and 2024
[3] Includes acquisition cost