Regulatory Matters [Line Items]                    
Regulatory asset     $ 2,371           $ 2,371 $ 2,216
Virginia Electric and Power Company                    
Regulatory Matters [Line Items]                    
ROE (percentage)             11.40%      
Facility operating capacity (kV) | kV           500   500    
Regulatory asset     1,159           1,159 993
Virginia Electric and Power Company | FERC Gas Regulation | Order Regarding Transmission Rate Design for Allocation of Costs among PJM Interconnect LLC Transmission Customers | Unfavorable Regulatory Action | Settled Litigation                    
Regulatory Matters [Line Items]                    
Amount required to pay under settlement agreement     $ 200              
Duration of payment under settlement agreement     10 years              
Virginia Electric and Power Company | FERC Gas Regulation | Order Regarding Transmission Rate Design for Allocation of Costs among PJM Interconnect LLC Transmission Customers | Unfavorable Regulatory Action | Settled Litigation | Regulatory asset recovered through retail rates                    
Regulatory Matters [Line Items]                    
Regulatory asset     $ 192           192  
Virginia Electric and Power Company | FERC Gas Regulation | Order Regarding Transmission Rate Design for Allocation of Costs among PJM Interconnect LLC Transmission Customers | Unfavorable Regulatory Action | Settled Litigation | Other operations and maintenance | Regulatory asset recovered through retail rates                    
Regulatory Matters [Line Items]                    
Remaining amount recorded in other operations and maintenance expense                   $ 8
Virginia Electric and Power Company | FERC Gas Regulation | Order Regarding Transmission Rate Design for Allocation of Costs among PJM Interconnect LLC Transmission Customers | Unfavorable Regulatory Action | Settled Litigation | Other deferred credits and other liabilities                    
Regulatory Matters [Line Items]                    
Amount of contingent liability     200           $ 200  
Virginia Electric and Power Company | Virginia Regulation                    
Regulatory Matters [Line Items]                    
Amount of fuel revenue decrease       $ 286            
Virginia Electric and Power Company | Virginia Regulation | Rider S                    
Regulatory Matters [Line Items]                    
Proposed revenue requirement     254              
Revenue requirement increase (decrease)     3              
Virginia Electric and Power Company | Virginia Regulation | Rider R                    
Regulatory Matters [Line Items]                    
Proposed revenue requirement     75              
Revenue requirement increase (decrease)     1              
Virginia Electric and Power Company | Virginia Regulation | Rider W                    
Regulatory Matters [Line Items]                    
Proposed revenue requirement     126              
Revenue requirement increase (decrease)     9              
Virginia Electric and Power Company | Virginia Regulation | Rider B                    
Regulatory Matters [Line Items]                    
Proposed revenue requirement     28              
Revenue requirement increase (decrease)     (1)              
Number of power stations converted to biomass | power_station                 3  
Virginia Electric and Power Company | Virginia Regulation | Rider GV                    
Regulatory Matters [Line Items]                    
Proposed revenue requirement     89              
Revenue requirement increase (decrease)     $ 49              
Virginia Electric and Power Company | Virginia Regulation | Rider BW                    
Regulatory Matters [Line Items]                    
ROE (percentage)     10.60%              
Approved revenue required     $ 119              
Virginia Electric and Power Company | Virginia Regulation | Rider T1                    
Regulatory Matters [Line Items]                    
Proposed revenue requirement       639            
Revenue requirement increase (decrease)       1            
Virginia Electric and Power Company | Virginia Regulation | Solar Development Project | Subsequent Event | Scenario, Forecast                    
Regulatory Matters [Line Items]                    
Capacity of solar facility (mw) | MW   18                
Total estimated cost   $ 40                
Virginia Electric and Power Company | Virginia Regulation | Solar Development Project | Rider US-2                    
Regulatory Matters [Line Items]                    
ROE (percentage)     9.60%              
Capacity of solar facility (mw) | MW         56          
Total estimated cost         $ 130          
Approved revenue required     $ 4              
East Ohio | Ohio Regulation | UEX Rider                    
Regulatory Matters [Line Items]                    
Refund of accumulated bad debt expense       8            
Net bad debt expense       19            
East Ohio | Ohio Regulation | Subsequent Event | PIPP Plus Program                    
Regulatory Matters [Line Items]                    
Projected deferred program costs $ 32                  
Refund of over-recovery of accumulated arrearages $ 28                  
Hope Gas Inc | West Virginia Regulation | PREP                    
Regulatory Matters [Line Items]                    
Projected capital investment       $ 27            
Period for capital investment       5 years            
Total projected capital investment       $ 152            
DCG | FERC Gas Regulation | Columbia to Eastover Project                    
Regulatory Matters [Line Items]                    
Amount of project     $ 45