XML 148 R126.htm IDEA: XBRL DOCUMENT v3.24.0.1
Property, Plant and Equipment (Schedule of Nonregulated Solar Projects) (Detail)
$ in Millions
12 Months Ended
Dec. 31, 2023
USD ($)
MW
Dec. 31, 2022
USD ($)
Dec. 31, 2021
USD ($)
Property Plant And Equipment [Line Items]      
Project Cost $ 24 $ 167 $ 101
Acquisition of Solar Project Yemassee in South Carolina      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-05    
Date Agreement Closed 2020-08    
Project Cost [1] $ 17    
Date of Commercial Operations January 2021    
MW Capacity | MW 10    
Acquisition of Solar Project Trask in South Carolina      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-05    
Date Agreement Closed 2020-10    
Project Cost [1] $ 22    
Date of Commercial Operations March 2021    
MW Capacity | MW 12    
Acquisition of Solar Project Hardin I in Ohio      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-06    
Date Agreement Closed 2020-06    
Project Cost [1] $ 240    
Date of Commercial Operations [2] Split    
MW Capacity | MW 150    
Acquisition of Solar Project Madison in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-07    
Date Agreement Closed 2020-07    
Project Cost [1] $ 165    
Date of Commercial Operations [3],[4] Expected 2024    
MW Capacity | MW 62    
Acquisition of Solar Project Hardin II in Ohio      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2020-08    
Date Agreement Closed [5] Terminated    
Acquisition Of Solar Project Atlanta Farms In Ohio      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2022-03    
Date Agreement Closed 2022-05    
Project Cost [1] $ 390    
Date of Commercial Operations [3] Expected 2024    
MW Capacity | MW 200    
Acquisition of Solar Project Foxhound in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered 2023-03    
Date Agreement Closed 2024-02    
Project Cost [1] $ 205    
Date of Commercial Operations [3] Expected 2024(3    
MW Capacity | MW 83    
Virginia Electric and Power Company      
Property Plant And Equipment [Line Items]      
Project Cost $ 24 $ 77 $ 75
Virginia Electric and Power Company | Acquisition of Solar Project Ft. Powhatan in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [6] 2019-06    
Date Agreement Closed [6] 2019-06    
Project Cost [6],[7] $ 267    
Date of Commercial Operations [6] January 2022    
MW Capacity | MW [6] 150    
Virginia Electric and Power Company | Acquisition of Solar Project Belcher in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [6],[8] 2019-06    
Date Agreement Closed [6],[8] 2019-08    
Project Cost [6],[7],[8] $ 164    
Date of Commercial Operations [6],[8] June 2021    
MW Capacity | MW [6],[8] 88    
Virginia Electric and Power Company | Acquisition of Solar Project Bedford in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [6] 2019-08    
Date Agreement Closed [6] 2019-11    
Project Cost [6],[7] $ 106    
Date of Commercial Operations [6] November 2021    
MW Capacity | MW [6] 70    
Virginia Electric and Power Company | Acquisition of Solar Project Maplewood in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [6] 2019-10    
Date Agreement Closed [6] 2019-10    
Project Cost [6],[7] $ 210    
Date of Commercial Operations [6] December 2022    
MW Capacity | MW [6] 120    
Virginia Electric and Power Company | Acquisition of Solar Project Rochambeau in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [6] 2019-12    
Date Agreement Closed [6] 2020-01    
Project Cost [6],[7] $ 35    
Date of Commercial Operations [6] December 2021    
MW Capacity | MW [6] 20    
Virginia Electric and Power Company | Acquisition of Solar Project Pumpkinseed in Virginia      
Property Plant And Equipment [Line Items]      
Date Agreement Entered [6] 2020-05    
Date Agreement Closed [6] 2020-05    
Project Cost [6],[7] $ 138    
Date of Commercial Operations [6] September 2022    
MW Capacity | MW [6] 60    
[1] Includes acquisition costs.
[2] In December 2020 and January 2021, 97 MW and 53 MW of the project commenced commercial operations, respectively.
[3] Dominion Energy expects to claim production tax credits on the energy generated and sold by project.
[4] Madison is reflected in the Corporate and Other segment effective December 2023.
[5] In January 2023, Dominion Energy terminated its agreement, without penalty, to acquire Hardin II.
[6] During 2023, Virginia Power determined the Bookers Mill solar project under development will be utilized to support its utility customers and included the project in its most recent Rider CE application. See Note 13 for additional information.
[7] Includes acquisition costs.
[8] Referred to as Desper once placed in service.