XML 135 R45.htm IDEA: XBRL DOCUMENT v2.3.0.15
Rate and Regulatory Matters
9 Months Ended
Sep. 30, 2011
Rate and Regulatory Matters [Abstract] 
RATE AND REGULATORY MATTERS
NOTE 2. RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
Regulatory Assets
     See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries. Following are updates to that information.
Fuel and Purchased Power Cost Recovery
Entergy Gulf States Louisiana
     In January 2003 the LPSC authorized its staff to initiate a proceeding to audit the fuel adjustment clause filings of Entergy Gulf States Louisiana and its affiliates. The audit includes a review of the reasonableness of charges flowed by Entergy Gulf States Louisiana through its fuel adjustment clause for the period 1995 through 2004. The LPSC Staff issued its audit report in December 2010. The report recommended the disallowance of $23 million of costs which, with interest, would total $43 million. $2 million of this total relates to a realignment to and recovery through base rates of certain SO2 costs. Entergy Gulf States Louisiana filed comments disputing the findings in the report. Entergy Gulf States Louisiana and the LPSC Staff reached a settlement to resolve the audit that requires Entergy Gulf States Louisiana to refund $18 million to customers, including the realignment to base rates of the $2 million of SO2 costs. Entergy Gulf States Louisiana and the LPSC Staff filed the uncontested settlement, the ALJ held a stipulation hearing in September 2011, and the LPSC approved the settlement in October 2011. The refund will be made in the November 2011 billing cycle. Entergy Gulf States Louisiana had previously recorded provisions for the estimated outcome of this proceeding.
     In April 2010 the LPSC authorized its staff to initiate an audit of Entergy Gulf States Louisiana’s purchased gas adjustment clause filings for its gas distribution operations. The audit includes a review of the reasonableness of charges flowed through by Entergy Gulf States Louisiana for the period from 2003 through 2008. Discovery was completed and, in June 2011, the LPSC Staff filed an audit report generally supporting the appropriateness of charges flowed through the purchased gas adjustment clause filings. The LPSC approved the staff audit report in October 2011.
Entergy Texas
     In December 2010, Entergy Texas filed with the PUCT a request to refund fuel cost recovery over-collections through October 2010. Pursuant to a stipulation among the parties that was approved by the PUCT in March 2011, Entergy Texas refunded over-collections through November 2010 of approximately $73 million, including interest through the refund period. The refund was made for most customers over a three-month period that began with the February 2011 billing cycle.
Little Gypsy Repowering Project (Entergy and Entergy Louisiana)
     See the Form 10-K for a discussion of the Little Gypsy repowering project. As discussed in the Form 10-K, in January 2011 all parties conducted a mediation on the disputed issues, and thereafter, reached agreement on a settlement of all disputed issues, including cost recovery and cost allocation. The settlement provides for Entergy Louisiana to recover $200 million as of March 31, 2011, and carrying costs on that amount on specified terms thereafter. The settlement also provides for Entergy Louisiana to recover the approved project costs by securitization. In April 2011, Entergy Louisiana filed an application with the LPSC to authorize the securitization of the investment recovery costs associated with the project and to issue a financing order by which Entergy Louisiana may accomplish such securitization. In August 2011 the LPSC issued an order approving the settlement and also issued a financing order for the securitization. See Note 4 to the financial statements for a discussion of the September 2011 issuance of the securitization bonds.
Retail Rate Proceedings
      See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies. The following are updates to the Form 10-K.
Filings with the LPSC
(Entergy Gulf States Louisiana)
     In January 2011, Entergy Gulf States Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2010. The filing showed an earned return on common equity of 8.84% and a revenue deficiency of $0.3 million. In March 2011, the LPSC Staff filed its findings, suggesting an adjustment that will produce an 11.76% earned return on common equity for the test year and a $0.2 million rate reduction. Entergy Gulf States Louisiana implemented the $0.2 million rate reduction effective with the May 2011 billing cycle. The LPSC docket is now closed.
     In May 2011, Entergy Gulf States Louisiana made a special formula rate plan rate implementation filing with the LPSC that implements effective with the May 2011 billing cycle a $5.1 million rate decrease to reflect adjustments in accordance with a previous LPSC order relating to the acquisition of Unit 2 of the Acadia Energy Center by Entergy Louisiana. As a result of the closing of the acquisition and termination of the pre-acquisition power purchase agreement with Acadia, Entergy Gulf States Louisiana’s allocation of capacity related to this unit ended, resulting in a reduction in the additional capacity revenue requirement.
     In May 2011, Entergy Gulf States Louisiana made its formula rate plan filing with the LPSC for the 2010 test year. The filing reflects an 11.11% earned return on common equity, which is within the allowed earnings bandwidth, indicating no cost of service rate change is necessary under the formula rate plan. The filing also reflects a $22.8 million rate decrease for incremental capacity costs. Entergy Gulf States Louisiana and the LPSC Staff subsequently filed a joint report that also stated that no cost of service rate change is necessary under the formula rate plan, and the LPSC approved it in October 2011. Unless otherwise ordered by the LPSC, the 2010 test year is the final evaluation period of Entergy Gulf States Louisiana’s formula rate plan. Entergy Gulf States Louisiana has filed a motion requesting that the LPSC extend the formula rate plan for an additional year. The LPSC has indicated that it will act on that request at its November 9, 2011 meeting.
(Entergy Louisiana)
     In May 2011, Entergy Louisiana made a special formula rate plan rate implementation filing with the LPSC that implements effective with the May 2011 billing cycle a $43.1 million net rate increase to reflect adjustments in accordance with a previous LPSC order relating to the acquisition of Unit 2 of the Acadia Energy Center. The net rate increase represents the decrease in the additional capacity revenue requirement resulting from the termination of the power purchase agreement with Acadia and the increase in the revenue requirement resulting from the ownership of the Acadia facility. In August 2011, Entergy Louisiana made a filing to correct the May 2011 filing and decrease the rate by $1.1 million.
     In May 2011, Entergy Louisiana made its formula rate plan filing with the LPSC for the 2010 test year. The filing reflects an 11.07% earned return on common equity, which is just outside of the allowed earnings bandwidth and results in no cost of service rate change under the formula rate plan. The filing also reflects a very slight ($9 thousand) rate increase for incremental capacity costs. Entergy Louisiana and the LPSC Staff subsequently filed a joint report that reflects an 11.07% earned return and results in no cost of service rate change under the formula rate plan, and the LPSC approved the joint report in October 2011. Unless otherwise ordered by the LPSC, the 2010 test year is the final evaluation period of Entergy Louisiana’s formula rate plan. Entergy Louisiana has filed a motion requesting that the LPSC extend the formula rate plan for an additional year. The LPSC has indicated that it will act on that request at its November 9, 2011 meeting.
Filings with the MPSC
     In March 2011, Entergy Mississippi submitted its formula rate plan 2010 test year filing. The filing shows an earned return on common equity of 10.65% for the test year, which is within the earnings bandwidth and results in no change in rates. The filing is currently subject to MPSC review.
Filings with the City Council
     In May 2011, Entergy New Orleans filed its electric and gas formula rate plan evaluation reports for the 2010 test year. The filings requested a $6.5 million electric rate decrease and a $1.1 million gas rate decrease. Entergy New Orleans and the City Council’s Advisors reached a settlement that results in an $8.5 million incremental electric rate decrease and a $1.6 million gas rate decrease. The settlement also provides for the deferral of $13.4 million of Michoud plant maintenance expenses incurred in 2010 and the establishment of a regulatory asset that will be amortized over the period October 2011 through September 2018. The City Council approved the settlement in September 2011. The new rates are effective with the first billing cycle of October 2011.
System Agreement Cost Equalization Proceedings
     See Note 2 to the financial statements in the Form 10-K for detailed information regarding the System Agreement Cost Equalization Proceedings. The following are updates to the Form 10-K.
     As discussed in the Form 10-K, in June 2005, and on rehearing in December 2005, the FERC issued orders finding that, among other things, the System Agreement no longer roughly equalizes total production costs among the Utility operating companies and that, in order to reach rough production cost equalization, a bandwidth remedy should be imposed by which each company’s total annual production costs will have to be within +/- 11% of Entergy System average total annual production costs. In April 2008, the DC Circuit concluded that the FERC’s orders had failed to adequately explain both its conclusion that it was prohibited from ordering refunds for the 20-month period from September 13, 2001 — May 2, 2003 and its determination to implement the bandwidth remedy commencing on January 1, 2006, rather than June 1, 2005. The DC Circuit remanded the case to FERC for further proceedings on these issues.
     On October 20, 2011, the FERC issued an order addressing the D.C. Circuit remand on these two issues. On the first issue, the FERC concluded that it did have the authority to order refunds, but decided that it would exercise its equitable discretion and not require refunds for the 20-month period from September 13, 2001 — May 2, 2003. Because the ruling on refunds relied on findings in the interruptible load proceeding that is discussed below, the FERC concluded that the refund ruling will be held in abeyance pending the outcome of the rehearing requests in that proceeding. On the second issue, the FERC reversed its prior decision and ordered that the prospective bandwidth remedy begins on June 1, 2005 (the date of its initial order in the proceeding) rather than January 1, 2006, as it had previously ordered. Pursuant to the October 20, 2011 order, Entergy is required to calculate the additional bandwidth payments for the period June - December 2005 utilizing the bandwidth formula tariff prescribed by the FERC that was filed in a December 2006 compliance filing and accepted by the FERC in an April 2007 order. Entergy is required to submit a compliance filing within 60 days of the date of the order that provides the payments and receipts among the Utility operating companies, and is required to make the payments/receipts among the Utility operating companies within 90 days of the date of the order. As is the case with bandwidth remedy payments, these payments and receipts will be paid by Utility operating company customers to other Utility operating company customers.
     The Utility operating companies have recorded liabilities and assets based on the preliminary estimates of the payments and receipts required to implement the FERC’s remedy for the period June - December 2005. This estimate does not include other payments/receipts among the Utility operating companies that may occur in 2012 based on calendar year 2011 production costs.
         
    Payments or
    (Receipts)
    (In Millions)
Entergy Arkansas
  $ 157  
Entergy Gulf States Louisiana
  $ (82 )
Entergy Louisiana
  $  
Entergy Mississippi
  $ (21 )
Entergy New Orleans
  $  
Entergy Texas
  $ (54 )
The actual payments/receipts related to implementing the bandwidth remedy for the period from June — December 2005 will not be finalized until the Utility operating companies’ compliance filing has been completed. The actual payments/receipts may vary from the above estimates, which are preliminary. The compliance filing is due to be filed at the FERC by December 19, 2011.
Rough Production Cost Equalization Rates
2011 Rate Filing Based on Calendar Year 2010 Production Costs
     In May 2011, Entergy filed with the FERC the 2011 rates in accordance with the FERC’s orders in the System Agreement proceeding. The filing shows the following payments/receipts among the Utility operating companies for 2011, based on calendar year 2010 production costs, commencing for service in June 2011, are necessary to achieve rough production cost equalization under the FERC’s orders:
         
    Payments or
    (Receipts)
    (In Millions)
Entergy Arkansas
  $ 77  
Entergy Gulf States Louisiana
  $ (12 )
Entergy Louisiana
  $  
Entergy Mississippi
  $ (40 )
Entergy New Orleans
  $ (25 )
Entergy Texas
  $  
Several parties intervened in the proceeding at the FERC, including the LPSC, which filed a protest as well. In July 2011, the FERC accepted Entergy’s proposed rates for filing, effective June 1, 2011, subject to refund, set the proceeding for hearing procedures, and then held those procedures in abeyance pending FERC decisions in the prior production cost proceedings currently before the FERC on review.
2010 Rate Filing Based on Calendar Year 2009 Production Costs
     In May 2010, Entergy filed with the FERC the 2010 rates in accordance with the FERC’s orders in the System Agreement proceeding, and supplemented the filing in September 2010. Several parties intervened in the proceeding at the FERC, including the LPSC and the City Council, which have also filed protests. In July 2010 the FERC accepted Entergy’s proposed rates for filing, effective June 1, 2010, subject to refund, and set the proceeding for hearing and settlement procedures. Settlement procedures have been terminated, and the ALJ scheduled hearings to begin in March 2011. Subsequently, in January 2011 the ALJ issued an order directing the parties and FERC Staff to show cause why this proceeding should not be stayed pending the issuance of FERC decisions in the prior production cost proceedings currently before the FERC on review. In March 2011 the ALJ issued an order placing this proceeding in abeyance.
2008 Rate Filing Based on Calendar Year 2007 Production Costs
     As discussed in the Form 10-K a hearing on remaining issues in the proceeding was completed in June 2009, and in September 2009 the ALJ issued an initial decision. Entergy, the APSC, the LPSC, and the MPSC submitted briefs on exceptions in the proceeding. In October 2011 the FERC issued an order on the ALJ’s initial decision. The FERC’s order may result in a minor reallocation of payments/receipts among the Utility operating companies on one issue in the 2008 rate filing.
Interruptible Load Proceeding
     See the Form 10-K for a discussion of the interruptible load proceeding, including the FERC’s motion requesting the D.C. Circuit hold the appeal of the FERC’s decisions ordering refunds in the interruptible load proceeding in abeyance and remand the record to the FERC. The D.C. Circuit granted the FERC’s unopposed motion in June 2009. In December 2009 the FERC established a paper hearing to determine whether the FERC had the authority and, if so, whether it would be appropriate to order refunds resulting from changes in the treatment of interruptible load in the allocation of capacity costs by the Utility operating companies. In August 2010 the FERC issued an order stating that it has the authority and refunds are appropriate. The APSC, MPSC, and Entergy requested rehearing of the FERC’s decision. In June 2011 the FERC issued an order granting rehearing in part and denying rehearing in part, in which the FERC determined to invoke its discretion to deny refunds. The FERC held that in this case where “the Entergy system as a whole collected the proper level of revenue, but, as was later established, incorrectly allocated peak load responsibility among the various Entergy operating companies...the Commission will apply here our usual practice in such cases, invoking our equitable discretion to not order refunds, notwithstanding our authority to do so.” The LPSC has requested rehearing of the FERC’s June 2011 decision. On October 6, 2011 the FERC issued an “Order Establishing Paper Hearing” inviting parties that oppose refunds to file briefs within 30 days addressing the LPSC’s argument that FERC precedent supports refunds under the circumstances present in this proceeding. Parties that favor refunds are then invited to file reply briefs within 21 days of the date that the initial briefs are due.
     In September 2010 the FERC had issued an order setting the refund report filed in the proceeding in November 2007 for hearing and settlement judge procedures. In May 2011, Entergy filed a settlement agreement that resolved all issues relating to the refund report set for hearing. In June 2011 the settlement judge certified the settlement as uncontested and the settlement agreement is currently pending before the FERC. In July 2011, Entergy filed an amended/corrected refund report and a motion to defer action on the settlement agreement until after the FERC rules on the LPSC’s rehearing request regarding the June 2011 decision denying refunds.
     Prior to the FERC’s June 2011 order on rehearing, Entergy Arkansas filed an application in November 2010 with the APSC for recovery of the refund that it paid. The APSC denied Entergy Arkansas’s application, and also denied Entergy Arkansas’s petition for rehearing. If the FERC were to order Entergy Arkansas to pay refunds on rehearing in the interruptible load proceeding the APSC’s decision would trap FERC-approved costs at Entergy Arkansas with no regulatory-approved mechanism to recover them. In August 2011, Entergy Arkansas filed a complaint in the United States District Court for the Eastern District of Arkansas asking for a declaratory judgment. In the complaint Entergy Arkansas asks the court to declare that the rejection of Entergy Arkansas’s application by the APSC is preempted by the Federal Power Act. The APSC filed a motion to dismiss the complaint and a decision is pending.