Regulatory Matters (Notes)
6 Months Ended
Jun. 30, 2014
Regulatory Assets and Liabilities Disclosure [Abstract]  
Regulatory Matters
Regulatory Matters

Energy Efficiency Implementation Rates

The PUCN's final order approving the merger between BHE and NV Energy stipulated that the Company will not seek recovery of any lost revenue for calendar year 2014 in an amount that exceeds 50% of the lost revenue that the Company could otherwise request. In February 2014, the Company filed an application with the PUCN to reset the energy efficiency implementation rate. In June 2014, the PUCN accepted a stipulation to adjust the energy efficiency implementation rate, as of July 1, 2014, to collect 50% of the estimated lost revenue that the Company would otherwise be allowed to recover for the 2014 calendar year. The energy efficiency implementation rate will be effective from July through December 2014 and will reset on January 1, 2015 and remain in effect through September 2015. To the extent the Company's earned rate of return exceeds the rate of return used to set base general rates, the Company is required to refund to customers energy efficiency implementation rate revenue collected. As a result, the Company has deferred recognition of energy efficiency implementation rate revenue collected and has recorded a liability of $7 million on the Consolidated Balance Sheets as of June 30, 2014.

General Rate Case

In May 2014, the Company filed a general rate case with the PUCN. In July 2014, the Company made its certification filing, which requests incremental annual revenue relief in the amount of $38 million, or an average price increase of 2%. An order is expected by the end of 2014 and, if approved, the new rates would be effective January 1, 2015.

2013 FERC Transmission Rate Case

In May 2013, the Company, along with Sierra Pacific, filed an application with the FERC to establish single system transmission and ancillary service rates. The combined filing requested incremental rate relief of $17 million annually to be effective January 1, 2014. On August 5, 2013, the FERC granted the companies' request for a rate effective date of January 1, 2014 subject to refund, and set the case for hearing or settlement discussions. On January 1, 2014, the Company implemented the filed rates in this case subject to refund as set forth in FERC's order. As of June 30, 2014, the Company accrued $7 million for amounts subject to rate refund, which is included in customer deposits and other on the Consolidated Balance Sheets. At this time management is unable to determine the final revenue impact of the case.