Project Changes in Estimates - Additional Information (Detail) - USD ($)
3 Months Ended
Mar. 31, 2020
Mar. 31, 2019
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results $ 150,000,000  
Estimated additional project costs, recovery recognized from customers 0  
COVID-19 Pandemic [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 79,000,000  
NCSA [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 115,000,000 $ 24,000,000
NCSA [Member] | Cameron LNG and Freeport LNG Project [Member] | LNG Project [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 11,000,000  
NCSA [Member] | Total Ethane Cracker Project [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 47,000,000  
NCSA [Member] | Total Ethane Cracker Project [Member] | Downstream Petrochemical Projects [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 54,000,000  
NCSA [Member] | Rota 3 Pipeline and Other Projects [Member] | Offshore and Subsea Projects [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 68,000,000  
NCSA [Member] | COVID-19 Pandemic [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 39,000,000  
EARC [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results   4,000,000
EARC [Member] | Total Tyra Redevelopment Project    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 11,000,000  
EARC [Member] | COVID-19 Pandemic [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 11,000,000  
EARC [Member] | COVID-19 Pandemic [Member] | Total Tyra Redevelopment Project    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 9,000,000  
MENA [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 13,000,000 33,000,000
MENA [Member] | COVID-19 Pandemic [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 17,000,000  
APAC [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results   6,000,000
APAC [Member] | Reliance subsea field development project [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 7,000,000  
APAC [Member] | COVID-19 Pandemic [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results 12,000,000  
APAC [Member] | COVID-19 Pandemic [Member] | Reliance subsea field development project [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results $ 13,000,000  
NCSA, EARC, MENA and APAC [Member]    
Organization Consolidation And Presentation Of Financial Statements Disclosure [Line Items]    
Effect of changes in estimated project cost on operating results   $ 19,000,000