Revenue Recognition - Additional Information (Detail) - USD ($)
3 Months Ended 6 Months Ended
Jun. 30, 2019
Mar. 31, 2019
Jun. 30, 2018
Jun. 30, 2019
Jun. 30, 2018
Dec. 31, 2018
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Revenues recognized due to changes in transaction price [1] $ 2,137,000,000   $ 1,735,000,000 $ 4,348,000,000 $ 2,343,000,000  
Revenue included from settlement of claims 72,000,000     72,000,000    
Advance billings on contracts 579,000,000     1,300,000,000    
Unapproved change orders and claims 388,000,000     388,000,000   $ 428,000,000
Unapproved change orders and claims in our RPO balance 101,000,000     101,000,000   130,000,000
Incentives amount included in transaction prices 126,000,000     126,000,000   0
Incentives amount included in our RPO balance $ 25,000,000     $ 25,000,000    
Estimated percentage of in progress as of combination date 0.00%     0.00%    
Effect of changes in estimated project cost on operating results     84,000,000   121,000,000  
Uncompleted Contracts [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Provisions for estimated losses $ 132,000,000     $ 132,000,000   $ 266,000,000
Freeport LNG Train 3 Project [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Effect of changes in estimated project cost on operating results       38,000,000    
NCSA [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Revenues recognized due to changes in transaction price 74,000,000     96,000,000    
Effect of changes in estimated project cost on operating results 131,000,000     155,000,000    
NCSA [Member] | Cameron Liquefied Natural Gas Project [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Provisions for estimated losses $ 58,000,000     $ 58,000,000    
Percentage of complete acquired on post combination basis 78.00%     78.00%    
Percentage of complete acquired on pre combination basis 93.00%     93.00%    
Revenue recognized achievement of progress milestones $ 110,000,000          
NCSA [Member] | Line 1 and Line 10 project for Pemex [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Provisions for estimated losses $ 6,000,000     $ 6,000,000    
Percentage of completion 85.00%     85.00%    
Effect of changes in estimated project cost on operating results $ 10,000,000     $ 28,000,000    
NCSA [Member] | Freeport LNG Trains 1 and 2 Project [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Provisions for estimated losses $ 19,000,000     $ 19,000,000    
Percentage of complete acquired on post combination basis 87.00%     87.00%    
Percentage of complete acquired on pre combination basis 96.00%     96.00%    
Effect of changes in estimated project cost on operating results $ 27,000,000     $ 54,000,000    
Partial offset on estimated costs on project   $ 11,000,000        
NCSA [Member] | Freeport LNG Train 3 Project [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Effect of changes in estimated project cost on operating results $ 11,000,000     $ 5,000,000    
NCSA [Member] | Calpine Power Project [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Percentage of complete acquired on post combination basis 99.00%     99.00%    
Percentage of complete acquired on pre combination basis 99.70%     99.70%    
Effect of changes in estimated project cost on operating results $ 11,000,000     $ 11,000,000    
APAC [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Revenues recognized due to changes in transaction price     $ 13,000,000   $ 79,000,000  
Pemex [Member] | Abkatun-A2 Project [Member]            
Revenue Recognition Multiple Deliverable Arrangements [Line Items]            
Percentage of project acquired complete 99.00%     99.00%    
[1] Intercompany amounts have been eliminated in consolidation.