NOTE 4—USE OF ESTIMATES

The following is a discussion of our most significant changes in cost estimates that impacted segment operating income for the three months ended March 31, 2018 and 2017.

Three months ended March 31, 2018

Segment operating income was positively impacted by favorable changes in estimates totaling approximately $37 million in our Middle East (“MEA”) and Asia (“ASA”) segments, which were partially offset by $2 million of net unfavorable changes in estimates in our Americas, Europe and Africa (“AEA”) segment.

MEAThis segment was positively impacted by favorable changes in estimates aggregating approximately $30 million, primarily due to:

 

cost savings associated with fabrication, procurement and marine campaigns on two Saudi Aramco lump-sum EPCI projects under the second Saudi Aramco Long Term Agreement (“LTA II”);

 

savings associated with marine campaigns, reimbursement for costs incurred and reduction in estimated costs to complete on multiple projects in the Middle East, none of which were individually material.

Those favorable changes in estimates were partially offset by higher estimated costs associated with:

 

hook-up and marine campaigns on two Saudi Aramco projects; and

 

standby equipment and mechanical equipment downtime on Middle East projects.

ASA—This segment was positively impacted by favorable changes in estimates aggregating approximately $9 million, primarily due to reduction in estimates of costs to complete several active projects. Those favorable changes in estimates were partially offset by additional costs associated with weather downtime on two active projects.

Three months ended March 31, 2017

Segment operating income for the three months ended March 31, 2017 was positively impacted by net favorable changes in estimates totaling approximately $47 million across all segments.

AEAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $5 million on multiple projects, none of which individually were material. 

MEAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $16 million, primarily due to productivity improvements and associated cost savings on Saudi Aramco projects.

ASAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $26 million, primarily as a result of improved cost estimates associated with efficient project execution, including productivity improvements on our marine vessels and associated cost savings achieved, on our active projects.

At December 31, 2016, on the Ichthys project in Australia, we reported a $34 million increase in our estimated costs at completion due to a failure identified in a supplier-provided subsea-pipe connector component that we had previously installed, and we identified possible additional increases of up to $10 million, due to potential need for alternative installation methods. We investigated the cause of the failure and developed a remediation plan in conjunction with the customer. We commenced offshore replacement in June 2017 through a diving intervention method and completed the replacement in 2017. The costs to replace the supplier-provided subsea-pipe connector component were less than our December 31, 2016 estimate. The project remains in an overall profitable position.