XML 23 R10.htm IDEA: XBRL DOCUMENT v3.8.0.1
USE OF ESTIMATES
9 Months Ended
Sep. 30, 2017
Accounting Policies [Abstract]  
USE OF ESTIMATES

NOTE 3—USE OF ESTIMATES

The following is a discussion of our most significant changes in estimates that impacted segment operating income for the three and nine months ended September 30, 2017 and 2016.

Three months ended September 30, 2017

Segment operating income for the three months ended September 30, 2017 was positively impacted by net favorable changes in estimates totaling approximately $36 million.

Americas, Europe and Africa Segment (“AEA”)This segment was impacted by net unfavorable changes in estimates aggregating approximately $4 million on multiple projects, none of which individually were material.  

Middle East Segment (“MEA”)This segment was positively impacted by net favorable changes in estimates aggregating approximately $36 million, primarily due to:

 

cost savings associated with marine campaigns and changes in estimate at completion on multiple Saudi Aramco projects;

 

marine campaign cost savings and benefits from favorable weather conditions, which were partially offset by higher fabrication costs and marine equipment downtime on a lump-sum EPCI project under the second Saudi Aramco Long-Term Agreement (“LTA II”);

 

favorable changes in estimated costs at completion on various other projects, which individually were not material.

Those net favorable changes in estimates were partially offset by higher marine campaign costs for the Berri platform, a Saudi Aramco EPCI project, and increases in costs on a project in the Neutral Zone.

Asia Segment (“ASA”)This segment was positively impacted by net favorable changes in estimates aggregating approximately $4 million, primarily due to change in estimates associated with efficient project execution and productivity improvements on multiple active projects which were individually not material.

Those favorable changes in estimates were partially offset by higher marine campaign costs associated with the transportation and installation of pipelines under the multi-year Brunei Shell Petroleum (“BSP”) offshore installation contract.

As of September 30, 2017, the diving work to replace the failed supplier-provided subsea-pipe connector component on the Ichthys project in Australia was substantially complete. The costs to replace the supplier-provided subsea-pipe connector component, at the completion of the project, are expected to be less than our December 31, 2016 estimate of $34 million. The project remains in an overall profitable position.

Nine months ended September 30, 2017

Segment operating income for the nine months ended September 30, 2017 was positively impacted by net favorable changes in estimates totaling approximately $115 million, primarily in our MEA and ASA segments.

AEAThis segment was impacted by net unfavorable changes in estimates aggregating approximately $3 million on multiple projects, none of which individually were material. 

MEAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $72 million, primarily due to:

 

productivity improvements and associated cost savings during the marine hookup campaign and reduction in estimated costs to complete two projects in the Middle East, including a Saudi Aramco project;  

 

marine campaign cost savings associated with productivity improvements and favorable weather conditions, which were partially offset by higher fabrication costs on lump-sum EPCI projects under the LTA II;

 

productivity improvements and associated cost savings during the installation phase on the Saudi Aramco Marjan power system replacement project;

 

close-out improvements associated with the first phase of a large pipeline repair project in the Middle East, which was completed in 2016, and a change in estimate to complete the next phase of this project; and

 

cost savings associated with productivity improvements on multiple projects in the Middle East, none of which were individually material.

ASAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $46 million, primarily due to changes in estimates driven by productivity improvements and associated cost savings and changes in estimated costs at completion on active and completed projects.

Those net favorable changes in estimates were partially offset by vessel and marine equipment downtime on our Vashishta EPCI project in India.

In addition, as of December 31, 2016, on the Ichthys project in Australia, we reported a $34 million increase in our estimated costs at completion due to a failure identified in a supplier-provided subsea-pipe connector component that we had previously installed, and we identified possible additional increases of up to $10 million, due to potential need for alternative installation methods. We investigated the cause of the failure and developed a remediation plan in conjunction with the customer. We commenced offshore replacement in June 2017 through a diving intervention method.  As of September 30, 2017, the remediation work was substantially complete. The costs to replace the supplier-provided subsea-pipe connector component are expected to be less than our December 31, 2016 estimate of $34 million. The project remains in an overall profitable position.

Three months ended September 30, 2016

Segment operating income for the three months ended September 30, 2016 was positively impacted by net favorable changes in estimates totaling approximately $34 million across all segments.

AEAThis segment was positively impacted by net favorable changes in estimates, aggregating approximately $6 million, none of which individually were material.

MEAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $12 million, primarily due to:

 

productivity improvements and associated cost savings related to a Saudi Aramco project; and

 

other miscellaneous projects, which individually were not material.

ASAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $16 million, primarily due to:

 

cost savings associated with our vessel productivity improvements; and

 

favorable changes in estimates at completion on several active projects.

Those net favorable changes in estimates were partially offset by net unfavorable changes on an active project, which was not material. 

Nine months ended September 30, 2016

Segment operating income for the nine months ended September 30, 2016 was positively impacted by net favorable changes in estimates totaling approximately $101 million across all segments.

AEAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $29 million, primarily due to:

 

successful execution and close-out improvements on two significant projects, PB Litoral and Exxon Julia Subsea Tieback;

 

productivity improvements and associated cost savings related to our DB 50 and NO 102 vessels’ marine campaigns undertaken in the Gulf of Mexico; and

 

a reversal of a $7 million provision for liquidated damages, due to an agreed additional extension of the PB Litoral project completion date.

Those net favorable changes in estimates were partially offset by net unfavorable changes on multiple projects, none of which were individually material. 

MEAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $29 million, primarily due to productivity improvements and associated cost savings related to the DB 27 and the Intermac 406 vessels, both associated with Saudi Aramco projects, due to improved execution. Those favorable changes in estimates were partially offset by marine equipment downtime due to weather on a project in Qatar.  

ASAThis segment was positively impacted by net favorable changes in estimates aggregating approximately $43 million, primarily due to:

 

cost savings associated with productivity improvements on our LV 108 vessel activities; and

 

favorable agreement on outstanding change orders on active and completed projects during the 2016 period.

Those net favorable changes in estimates were partially offset by net unfavorable changes on multiple projects, none of which were individually material.