REVENUE RECOGNITION
3 Months Ended
Mar. 31, 2015
Revenue Recognition [Abstract]  
REVENUE RECOGNITION

NOTE 2—REVENUE RECOGNITION

Unapproved Change Orders

As of March 31, 2015, total unapproved change orders included in our estimates at completion aggregated approximately $240.3 million, of which approximately $73.0 million was included in backlog. As of March 31, 2014, total unapproved change orders included in our estimates at completion aggregated approximately $223.5 million, of which approximately $38.1 million was included in backlog.

Claims Revenue

The amount of revenues and costs included in our estimates at completion (i.e., contract values) associated with claims was $6.5 million as of March 31, 2015 and 2014. All of these claim amounts at March 31, 2015 and 2014 were related to our MEA segment. For the quarters ended March 31, 2015 and 2014, no revenues or costs pertaining to claims were included in the accompanying Consolidated Financial Statements. None of the pending claims as of March 31, 2015 were the subject of any litigation proceedings.

Our unconsolidated joint ventures did not include any claims revenue or associated cost in their financial results for the quarters ended March 31, 2015 and 2014.  

Deferred Profit Recognition

As of March 31, 2015 and 2014, we were not accounting for any projects under our deferred profit recognition policy.

Completed Contract Method

As of March 31, 2015 and 2014, we were not accounting for any contracts under the completed contract method.

Loss Recognition

As of March 31, 2015, we have provided for our estimated costs to complete on all of our ongoing contracts. However, it is possible that current estimates could change due to unforeseen events, which could result in adjustments to overall contract costs. Variations from estimated contract performance could result in material adjustments to operating results for any fiscal quarter or year. For all contracts, if a current estimate of total contract cost indicates a loss, the projected loss is recognized in full when determined.

Of the March 31, 2015 backlog, approximately $406.7 million related primarily to four active projects that were in loss positions, whereby future revenues are expected to equal costs when recognized. Included in this amount was $130.4 million of backlog associated with an EPCI project, PB Litoral, in Mexico, which is expected to be completed in the fourth quarter of 2015, $87.5 million of backlog pertaining to a five-year charter of the Agile in Brazil, which is expected to be completed in the first quarter of 2017, and $20.8 million of backlog relating to NO102 vessel charter project in Brazil, scheduled for completion in the second quarter of 2015, all of which are being conducted in our AEA segment. The March 31, 2015 backlog amount also included $166.5 million relating to an EPCI project in our MEA segment, which is also in a loss position and is expected to be completed by the fourth quarter of 2017.  It is possible that our estimates of gross profit could increase or decrease based on changes in productivity, actual downtime and the resolution of change orders and claims with the customers.