NOTE 3—USE OF ESTIMATES

We use estimates and assumptions to prepare our financial statements in conformity with U.S. GAAP. Those estimates and assumptions affect the amounts we report in our consolidated financial statements and accompanying notes. Our actual results could differ from those estimates, and variances could materially affect our financial condition and results of operations in future periods. Changes in project estimates generally exclude change orders and changes in scope, but may include, without limitation, changes in cost recovery estimates, unexpected changes in weather conditions, changes in productivity, unidentified required vessel repairs, customer and vendor delays and other costs. We generally expect to experience a reasonable amount of unanticipated events, and some of those events can result in significant cost increases above cost amounts we previously estimated. As of March 31, 2015, we have provided for our estimated costs to complete on all of our ongoing contracts. However, it is possible that current estimates could change due to unforeseen events, which could result in adjustments to overall contract costs. Variations from estimated contract performance could result in material adjustments to operating results. For all contracts, if a current estimate of total contract cost indicates a loss, the projected loss is recognized in full when determined.

The following is a discussion of our most significant changes in estimates that impacted operating income for the three months ended March 31, 2015 and 2014.

Three months ended March 31, 2015

Operating income for the three months ended March 31, 2015 was positively impacted by net favorable changes in cost estimates totaling approximately $21.6 million across all segments.

The AEA segment was positively impacted by net favorable changes in estimates aggregating approximately $6.6 million, primarily due to $4.4 million in reduced cost estimates attributable to a revised demobilization plan for one of our vessels, North Ocean 105 (the “NO 105”), which is working on a  subsea project in Brazil.

The MEA segment was positively impacted by net favorable changes in estimates aggregating approximately $9.1 million. Two EPCI projects in Saudi Arabia were positively impacted by $6.9 million of changes in revenue recovery and cost savings based on constructive discussions with a customer on design optimization and by $6.3  million for improvement in revenue recovery estimates and due to the favorable outcome of our discussions with a customer on compensation for vessel downtime due to weather and standby delays. These favorable changes were partially offset by the $4.5 million negative impact on a Saudi Arabia EPCI project, primarily due to change in cost estimates as a result of a change in marine execution plans.

The ASA segment was positively impacted by net favorable changes in estimates aggregating approximately $5.9 million, driven by multiple projects, none of the individual results of which were material.

Three months ended March 31, 2014

Operating income for the three months ended March 31, 2014 was impacted by net unfavorable changes in cost estimates relating to projects in our AEA and MEA segments, partially offset by net favorable changes in ASA segment.

The AEA segment was negatively impacted by changes in estimates of approximately $35.4 million on an EPCI project, PB Litoral, in Mexico, in the first quarter of 2014. The estimated cost at completion on this project increased primarily due to delays in final project delivery, resulting in a revised execution plan, increased fabrication labor costs and recognition of liquidated damages.

The MEA segment was negatively impacted by losses of approximately $31.9 million, mostly due to changes in estimates on three projects in Saudi Arabia during the three months ended March 31, 2014. On two EPCI projects in Saudi Arabia, we increased our estimated cost at completion by approximately $24.3 million, primarily as a result of vessel downtime due to weather and standby delays (which may be recoverable from the customer, but which were not recognizable at March 31, 2014), and reduced productivity on fabrication and engineering activities. Both projects remain in a profitable position at March 31, 2014. On another EPCI project in Saudi Arabia, we increased our estimated cost to complete by approximately $7.6 million, primarily due to increases in our cost estimates for the completion of onshore activities on the project.

The ASA segment experienced an improvement of approximately $20.6 million, mostly due to changes in estimates on a subsea project, Siakap Subsea Development, in Malaysia during the quarter ended March 31, 2014, primarily due to productivity improvements on our marine vessels as well as offshore support activities.