XML 22 R42.htm IDEA: XBRL DOCUMENT v2.4.0.6
Business Combination - Additional Information (Detail) (USD $)
In Millions, unless otherwise specified
9 Months Ended
Sep. 30, 2012
Business Combinations [Line Items]  
Acquisition Date Jan. 03, 2012
Gain recognized from re-measurement of the pre-acquisition equity $ 5.8
Acquisition related costs 8.4
SandForce acquisition [Member]
 
Business Combinations [Line Items]  
Revenue recognized related to SandForce business since date of acquisition 124.1
Griffin project [Member]
 
Business Combinations [Line Items]  
Expected costs to complete $ 20.3
Anticipated completion date of Griffin project 2013
Revenues for Griffin project is expected through 2018
Minimum [Member]
 
Business Combinations [Line Items]  
Discount rate applied to projects 12.90%
Maximum [Member]
 
Business Combinations [Line Items]  
Discount rate applied to projects 17.90%