XML 77 R10.htm IDEA: XBRL DOCUMENT v2.4.0.6
Restructuring and Other Items
3 Months Ended
Apr. 01, 2012
Restructuring and Other Items [Abstract]  
Restructuring and Other Items

Note 4 — Restructuring and Other Items

The following table summarizes items included in restructuring of operations and other items, net:

 

     Three Months Ended  
     April 1, 2012     April 3, 2011  
     (In thousands)  

Lease terminations

   $ 1,634 (a)    $  1,688 (a) 

Employee severance and benefits

     431        1,643 (b) 
  

 

 

   

 

 

 

Total restructuring expense

     2,065        3,331   

Other items, net

     13,397 (c)      (525
  

 

 

   

 

 

 

Total restructuring of operations and other items, net

   $ 15,462      $ 2,806   
  

 

 

   

 

 

 

 

(a) Includes changes in time value, on-going operating expense and changes in estimates incurred from previously vacated facilities.

 

(b) Relates to restructuring actions taken during the first quarter of 2011 as the Company continued to streamline operations.

 

(c) Primarily consists of $8.3 million of SandForce acquisition-related costs and $4.6 million of costs associated with the transition service agreements entered into in connection with the sale of the external storage systems business.

The following table summarizes the significant activity within, and components of, the Company's restructuring obligations:

 

     Lease
Terminations
    Employee
Severance
and
Benefits
    Total  

Balance at December 31, 2011

   $ 11,752      $ 10,444      $ 22,196   

Expense

     1,634        431        2,065   

Utilized

     (2,564 )(a)      (8,168 )(a)      (10,732
  

 

 

   

 

 

   

 

 

 

Balance at April 1, 2012

   $ 10,822 (b)    $ 2,707 (b)    $ 13,529   
  

 

 

   

 

 

   

 

 

 

(a) Represents cash payments.

 

(b) The balance remaining for lease terminations is expected to be paid during the remaining terms of the leases, which extend through 2013. The balance remaining for employee severance and benefits is expected to be paid by the end of the second quarter of 2012.