Environmental Matters.  The Company is subject to various federal, state and local laws and regulations relating to the protection of the environment.  The Company has established procedures for the ongoing evaluation of its operations to identify potential environmental exposures and to comply with regulatory requirements.  It is the Company’s policy to accrue estimated environmental clean-up costs (investigation and remediation) when such amounts can reasonably be estimated and it is probable that the Company will be required to incur such costs. 
    
At June 30, 2019, the Company has estimated its remaining clean-up costs related to former manufactured gas plant sites will be approximately $7.1 million, which includes a $3.9 million estimated minimum liability to remediate a former manufactured gas plant site located in New York.  In March 2018, the NYDEC issued a Record of Decision for this New York site and the minimum liability reflects the remedy selected in the Record of Decision. The Company's liability for such clean-up costs has been recorded in Other Deferred Credits on the Consolidated Balance Sheet at June 30, 2019. The Company expects to recover its environmental clean-up costs through rate recovery over a period of approximately 3 years and is currently not aware of any material additional exposure to environmental liabilities.  However, changes in environmental laws and regulations, new information or other factors could have an adverse financial impact on the Company.
    
Northern Access Project. On February 3, 2017, Supply Corporation and Empire received FERC approval of the Northern Access project described herein. On April 7, 2017, the NYDEC issued a Notice of Denial of the federal Clean Water Act Section 401 Water Quality Certification and other state stream and wetland permits for the New York portion of the project (the Water Quality Certification for the Pennsylvania portion of the project was received on January 27, 2017). On April 21, 2017, Supply Corporation and Empire filed a Petition for Review in the United States Court of Appeals for the Second Circuit of the NYDEC's Notice of Denial with respect to National Fuel's application for the Water Quality Certification, and on May 11, 2017, the Company commenced legal action in New York State Supreme Court challenging the NYDEC's actions with regard to various state permits. On August 6, 2018, the FERC issued an Order finding that the NYDEC exceeded the statutory time frame to take action under the Clean Water Act and, therefore, waived its opportunity to approve or deny the Water Quality Certification. FERC denied rehearing requests associated with its Order. In light of these legal actions and the need to complete necessary project development activities in advance of construction, the in-service date for the project is expected to be no earlier than fiscal 2022.
 
Other.  The Company is involved in other litigation and regulatory matters arising in the normal course of business.  These other matters may include, for example, negligence claims and tax, regulatory or other governmental audits, inspections, investigations and other proceedings.  These matters may involve state and federal taxes, safety, compliance with regulations, rate base, cost of service and purchased gas cost issues, among other things.  While these other matters arising in the normal course of business could have a material effect on earnings and cash flows in the period in which they are resolved, an estimate of the possible loss or range of loss, if any, cannot be made at this time.