XML 93 R70.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments And Contingencies (Narrative) (Details)
$ in Millions
12 Months Ended
Sep. 30, 2017
USD ($)
Site Contingency [Line Items]  
Estimate minimum liability for environmental remediation $ 3.1
Project Costs 75.8
Future purchase obligation first year 262.4
Future purchase obligation second year 84.6
Future purchase obligation third year 77.9
Future purchase obligation fourth year 70.9
Future purchase obligation fifth year 61.7
Future purchase obligation thereafter 504.9
Operating lease commitment first year 10.8
Operating lease commitment second year 4.6
Operating lease commitment third year 3.7
Operating lease commitment fourth year 2.2
Operating lease commitment fifth year 1.5
Operating lease commitment thereafter $ 1.9
Environmental Site Remediation Costs [Member]  
Site Contingency [Line Items]  
Rate recovery period 4 years
Pipeline And Storage, Gathering And Utility Segments [Member]  
Site Contingency [Line Items]  
Contract commitments first year $ 61.7
Contract commitments second year 0.7
Contract commitments third year 0.2
Contractual commitments fourth year 0.3
Contractual commitments fifth year 0.3
Contractual commitments thereafter 1.1
Exploration And Production [Member]  
Site Contingency [Line Items]  
Contract commitments first year 79.5
Contract commitments second year 98.0
Contract commitments third year $ 17.1