XML 79 R10.htm IDEA: XBRL DOCUMENT v3.24.0.1
Rate Matters
12 Months Ended
Dec. 31, 2023
Rate Matters RATE MATTERS
The disclosures in this note apply to all Registrants unless indicated otherwise.

The Registrants are involved in rate and regulatory proceedings at the FERC and their state commissions.  Rate matters can have a material impact on net income, cash flows and possibly financial condition.  The Registrants’ recent significant rate orders and pending rate filings are addressed in this note.

AEP Texas Rate Matters (Applies to AEP and AEP Texas)

AEP Texas Interim Transmission and Distribution Rates

Through December 31, 2023, AEP Texas’ cumulative revenues from interim base rate increases that are subject to a prudency review is approximately $987 million. A base rate review could result in a refund to customers if AEP Texas incurs a disallowance of the transmission or distribution investment on which an interim increase was based. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. A revenue decrease, including a refund of interim transmission and distribution rates, could reduce future net income and cash flows and impact financial condition. AEP Texas is required to file for a comprehensive rate review no later than April 5, 2024.

APCo and WPCo Rate Matters (Applies to AEP and APCo)

2020-2022 Virginia Triennial Review

In March 2023, APCo submitted its 2020-2022 Virginia triennial review filing and base rate case with the Virginia SCC as required by state law. APCo requested a $213 million annual increase in Virginia base rates based upon a proposed 10.6% return on common equity. The requested annual increase includes $47 million related to vegetation management and a $35 million increase in depreciation expense. The requested increase in depreciation expense reflects, among other things, the impacts of incremental investments made since APCo’s last depreciation study using property balances as of December 31, 2022. Effective January 1, 2023 and in accordance with past Virginia SCC directives, APCo implemented updated Virginia depreciation rates. APCo’s proposed revenue requirement also includes the recovery of certain costs incurred that partially contributed to APCo’s calculated earnings shortfall for the 2020-2022 triennial period. For triennial review periods in which a Virginia utility earns below its authorized ROE band, the utility may file to recover expenses incurred, up to the bottom of the authorized ROE band, related to certain categories of costs, including system restoration costs for severe weather events.

In August 2023, APCo, Virginia Staff and intervening parties reached a settlement agreement that included the following: (a) a $127 million annual increase in Virginia base rates, (b) a 9.5% ROE, (c) updated depreciation rates that reflect a 2040 Amos Plant retirement date, (d) approval of a regulatory asset, including tax gross-up, to be recovered over three years starting in 2024 related to major storm expenses incurred during the 2020-2022 triennial period when APCo under-earned in Virginia, (e) approval of the revenue requirement impact of net operating loss carryforward related to income taxes and approval of deferral authority for corporate alternative minimum taxes incurred and (f) approval of the revenue requirement impact of an increase in vegetation management costs with certain costs subject to over-/under-recovery accounting. In November 2023, the Virginia SCC issued a final order approving the settlement agreement as described above with new rates taking effect in January 2024.

ENEC (Expanded Net Energy Cost) Filings

In April 2023, APCo and WPCo (the Companies) submitted their 2023 annual ENEC filing with the WVPSC, proposing two alternatives to increase ENEC rates effective September 1, 2023 and to resolve the Companies’ open 2021 and 2022 ENEC filings. The first alternative was a $293 million annual increase in ENEC rates comprised of an $89 million increase for current year ENEC expense and a $200 million annual increase for the recovery of the Companies’ February 28, 2023 ENEC under-recovery balances over three years, including debt and equity carrying costs. The second alternative was an $89 million annual increase in ENEC rates with the Companies securitizing approximately $1.9 billion of assets, including: (a) $553 million relating to ENEC under-recoveries as of February 28, 2023, (b) $88 million relating to major storm expense deferrals and (c) $1.2 billion relating to APCo’s West Virginia jurisdictional book values of the Amos and Mountaineer Plants and forecasted CCR and ELG investments at these generating facilities.

In September 2023, the WVPSC issued an order on the 2023 ENEC filing approving an $89 million annual increase in ENEC surcharge rates for the Companies’ forecasted costs for the period September 2023 through August 2024.

In January 2024, the WVPSC issued an order resolving the Companies’ 2021-2023 ENEC cases. In the order, the WVPSC: (a) disallowed $232 million in ENEC under-recovered costs as of February 28, 2023 ($136 million related to APCo) and (b) approved the recovery of $321 million of ENEC under-recovered costs as of February 28, 2023 ($174 million related to APCo) plus a 4% carrying charge rate over a ten-year recovery period starting September 1, 2024. As of December 31, 2023, the Companies’ financial statements reflect the impact of the disallowance. In February 2024, the Companies filed briefs with the
West Virginia Supreme Court to initiate an appeal of this order. The Companies will submit their annual ENEC update filing with the WVPSC in the second quarter of 2024 proposing that updated ENEC rates become effective September 1, 2024.

ETT Rate Matters (Applies to AEP)

ETT Interim Transmission Rates

AEP has a 50% equity ownership interest in ETT. Predominantly all of ETT’s revenues are based on interim rate changes that can be filed twice annually and are subject to review and possible true-up in the next base rate proceeding. Through December 31, 2023, AEP’s share of ETT’s cumulative revenues that are subject to a prudency review is approximately $1.7 billion. A base rate review could produce a refund to customers if ETT incurs a disallowance of the transmission investment on which an interim increase was based. A revenue decrease, including a refund of interim transmission rates, could reduce future net income and cash flows and impact financial condition. Management is unable to determine a range of potential losses, if any, that are reasonably possible of occurring. ETT is required to file for a comprehensive rate review no later than February 1, 2025, during which the $1.7 billion of cumulative revenues above will be subject to review.

I&M Rate Matters (Applies to AEP and I&M)

Michigan Power Supply Cost Recovery (PSCR)

In April 2023, I&M received intervenor testimony in I&M’s 2021 PSCR Reconciliation for the 12-month period ending December 31, 2021, recommending disallowances of purchased power costs of $18 million associated with the OVEC Inter-Company Power Agreement (ICPA) and the UPA with AEGCo that were alleged to be above market in applying the MPSC’s Code of Conduct rules. Michigan staff submitted testimony in I&M’s 2021 PSCR Reconciliation with no recommended disallowances for PSCR costs incurred, including those associated with the OVEC ICPA and the AEGCo UPA. Michigan staff also recommended several options to address I&M’s shortfall in achieving Michigan’s annual one percent energy waste reduction savings level, resulting in potential future disallowed costs of up to approximately $14 million. In June 2023, Michigan staff submitted rebuttal testimony to update their calculation of the 2021 market proxy price resulting in a recommended disallowance of approximately $1 million related to the OVEC ICPA.

In January 2024, I&M received staff testimony in I&M’s 2022 PSCR Reconciliation for the 12-month period ending December 31, 2022 recommending disallowances of purchased power costs of $2 million associated with the OVEC ICPA that were alleged to be above market in applying the MPSC’s Code of Conduct rules. Similar to the 2021 PSCR Reconciliation, Michigan staff also recommended several options to address I&M’s shortfall in achieving Michigan’s annual one percent energy waste reduction savings level, resulting in potential future disallowed costs of up to approximately $6 million.

MPSC orders on I&M’s 2021 and 2022 PSCR Reconciliations are expected in the first half of 2024. If any PSCR costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

2023 Indiana Base Rate Case

In August 2023, I&M filed a request with the IURC for a $116 million annual increase in Indiana base rates based upon a 2024 forecasted test year, a proposed 10.5% ROE and a proposed capital structure of 48.8% debt and 51.2% common equity. I&M proposed that the annual increase in base rates be implemented in two steps, with the first increase effective in mid-2024, following an IURC order, and the second increase effective in January 2025. The proposed annual increase includes a $41 million increase related to depreciation expense, driven by increased depreciation rates and increased capital investments, and a $15 million increase related to storm expenses. I&M’s Indiana base case filing requests recovery of certain historical period regulatory asset balances and proposes deferral accounting for certain future investments and tax related issues, including corporate alternative minimum tax expense and PTCs related to the Cook Plant.
In December 2023, I&M and intervenors reached a settlement agreement that was submitted to the IURC recommending a two-step increase in Indiana rates with a $28 million annual increase effective upon an IURC order and the remaining $34 million annual increase effective in January 2025. The recommended revenue increase includes: (a) a 9.85% ROE, (b) a two-step update of I&M’s capital structure with a capital structure of 50% for both debt and common equity effective upon an IURC order and I&M will submit an updated capital structure in January 2025 with the common equity component adjusted to no more than 51.2%, (c) a $25 million increase related to depreciation expense and (d) an $11 million increase related to storm expenses.
A hearing was held in January 2024 and an order is expected in the second quarter of 2024. If any costs included in this filing are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

2023 Michigan Base Rate Case

In September 2023, I&M filed a request with the MPSC for a $34 million annual increase in Michigan base rates based upon a 2024 forecasted test year, a proposed 10.5% ROE and a capital structure of 49.4% debt and 50.6% common equity. The proposed annual increase includes an $11 million annual increase in depreciation expense driven by increased capital investment. I&M’s Michigan base case filing requests recovery of certain historical period regulatory asset balances and proposes deferral accounting for certain future investments and tax related issues, including corporate alternative minimum tax expense and PTCs related to the Cook Plant.

In January 2024, Michigan Staff and various intervenors submitted testimony recommending changes in base rates ranging from a $6 million annual decrease to a $19 million annual increase. These changes are based on ROEs ranging from 9.7% to 9.9% and capital structures ranging from 49.4% debt and 50.6% equity to 52% debt and 48% equity. Intervenors also proposed in testimony certain disallowances related to existing regulatory assets totaling approximately $5 million, the exclusion of CAMT from any future deferrals and the prospective inclusion of PTCs related to the Cook Plant in I&M’s PSCR.

A hearing was held in February 2024. If any costs included in this filing are not approved for recovery, it could reduce future net income and cash flows and impact financial condition.

KPCo Rate Matters (Applies to AEP)

Investigation of the Service, Rates and Facilities of KPCo

In June 2023, the KPSC issued an order directing KPCo to show cause why it should not be subject to Kentucky statutory remedies, including fines and penalties, for failure to provide adequate service in its service territory. The KPSC’s show cause order did not make any determination regarding the adequacy of KPCo’s service. In July 2023, KPCo filed a response to the show cause order demonstrating that it has provided adequate service. In December 2023 and February 2024, KPCo and certain intervenors filed testimony with the KPSC. In February 2024, KPCo filed a motion to strike and exclude intervenor testimony in its entirety on the grounds that issues raised are outside the scope of the proceeding and because the testimony is largely unreasoned, unsupported, and provides no evidentiary value. A hearing is expected in 2024. If any fines or penalties are levied against KPCo relating to the show cause order, it could reduce net income and cash flows and impact financial condition.

2023 Kentucky Base Rate and Securitization Case

In June 2023, KPCo filed a request with the KPSC for a $94 million net annual increase in base rates based upon a proposed 9.9% ROE with the increase to be implemented no earlier than January 2024. The filing proposes no changes in depreciation rates and an annual level of storm restoration expense in base rates of approximately $1 million. KPCo also proposed to discontinue tracking of PJM transmission costs through a rider, and to instead collect an annual level of costs through base rates. In addition, KPCo has proposed a rider to recover certain distribution reliability investments and related incremental operation and maintenance expenses. KPCo also requested a prudency determination and recovery mechanism for approximately $16 million of purchased power costs not recoverable through its FAC since its last base case. KPCo’s proposal did not address the disposition of its 50% interest in Mitchell Plant, which will be addressed in the future. As of December 31, 2023, the net book value of KPCo’s share of the Mitchell Plant, before cost of removal including CWIP and inventory, was $553 million. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

In conjunction with its June 2023 filing, KPCo further requested to finance, through the issuance of securitization bonds, approximately $471 million of regulatory assets recorded as of June 2023 including: (a) $289 million of plant retirement costs, (b) $79 million of deferred storm costs related to 2020, 2021, 2022 and 2023 major storms, (c) $52 million of deferred purchased power expenses and (d) $51 million of under-recovered purchased power rider costs. Plant retirement costs and deferred purchased power expenses have been deemed prudent in prior KPSC decisions. KPCo has requested a prudency determination in this proceeding for the deferred storm costs and under-recovered purchase power rider costs since the last base case.

In November 2023, KPCo filed an uncontested settlement agreement with the KPSC, that included an annual base rate increase of $75 million, based upon a 9.75% ROE. Settlement parties agreed that the KPSC should approve KPCo’s securitization request, and that the approximately $471 million regulatory assets requested for securitization are comprised of prudently incurred costs. The settlement does not modify KPCo’s proposal to discontinue tracking of PJM transmission costs through a
rider, and to instead collect an annual level of costs through base rates. The settlement approved KPCo’s request to implement a rider to recover certain distribution reliability investments. Under the terms of the settlement, KPCo agreed to forgo recovery of approximately $16 million of purchased power costs not recoverable through the FAC since KPCo’s last base case and excluded a return on its stand-alone NOLC deferred tax asset from the base rate revenue requirement while it seeks a private letter ruling from the IRS. Other differences between KPCo’s requested annual base rate increase and the uncontested settlement agreement are primarily due to exclusion of certain employee-related expenses from the revenue requirement.

In January 2024, consistent with the November 2023 uncontested settlement agreement, the KPSC issued a financing order approving KPCo’s securitization request and concluding that costs requested for recovery were prudently incurred. The KPSC’s financing order includes certain additional requirements related to securitization bond structuring, marketing, placement, and issuance that were not reflected in KPCo’s proposal. As a result, in January 2024, KPCo filed a request for rehearing with the KPSC to clarify certain aspects of these additional requirements. In February 2024, the KPSC denied KPCo’s rehearing requests. In accordance with Kentucky statutory requirements and the financing order, the issuance of the securitized bonds is subject to final review by the KPSC after bond pricing. KPCo expects to proceed with the securitized bond issuance process and to complete the securitization process in the second half of 2024, subject to market conditions. If any of these costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.

In January 2024, the KPSC issued an order modifying the November 2023 uncontested settlement agreement and approving an annual base rate increase of $60 million based upon a 9.75% ROE effective with billing cycles mid-January 2024. The order reduced KPCo’s base rate revenue requirement by $14 million to allow recovery of actual test year PJM transmission costs instead of KPCo’s requested annual level of costs based on PJM 2023 projected transmission revenue requirements. The KPSC denied implementation of a rider to recover certain distribution reliability investments. In February 2024, KPCo filed an appeal with the Commonwealth of Kentucky Franklin Circuit Court, challenging among other aspects of the order the $14 million base rate revenue requirement reduction.

Fuel Adjustment Clause (FAC) Review

In December 2023, KPCo received intervenor testimony in its FAC review for the two-year period ending October 31, 2022, recommending a disallowance ranging from $44 million to $60 million of its total $432 million purchased power cost recoveries as a result of proposed modifications to the ratemaking methodology that limits purchased power costs recoverable through the FAC. A hearing was held in February 2024. If any fuel costs are not recoverable or refunds are ordered, it could reduce future net income and cash flows and impact financial condition.

Rockport Offset Recovery

In January 2024, KPCo filed an application with the KPSC seeking to recover an allowed cost (Rockport Offset) of $41 million in accordance with the terms of the settlement agreement in the 2017 Kentucky Base Rate Case permitting KPCo to use the level of non-fuel, non-environmental Rockport Plant UPA expense included in base rates to earn its authorized ROE in 2023 since the Rockport UPA ended in December 2022. An estimated Rockport Offset of $23 million was recovered through a rider, subject to true-up, during the 12-months ended December 2023. KPCo is requesting to recover the remaining $18 million Rockport Offset true-up over a 12-month period beginning March 2024, also through a rider. The Rockport Offset true-up is not yet reflected in revenue, as KPCo has not met the requirements of alternative revenue recognition in accordance with the accounting guidance for “Regulated Operations”. In February 2024, the KPSC issued an order allowing KPCo to collect the remaining $18 million through interim rates, subject to refund, over twelve months starting in March 2024. Intervenor testimony is expected in April 2024 and an order is expected in the second quarter of 2024. If the Rockport Offset is not recoverable or refunds are ordered, it could reduce future net income and cash flows and impact financial condition.

OPCo Rate Matters (Applies to AEP and OPCo)

OVEC Cost Recovery Audits

In December 2021, as part of OVEC cost recovery audits pending before the PUCO, intervenors filed positions claiming that costs incurred by OPCo during the 2018-2019 audit period were imprudent and should be disallowed. In May 2022, intervenors filed for rehearing on the 2016-2017 OVEC cost recovery audit period claiming the PUCO’s April 2022 order to adopt the findings of the audit report were unjust, unlawful and unreasonable for multiple reasons, including the position that OPCo recovered imprudently incurred costs. In June 2022, the PUCO granted rehearing on the 2016-2017 audit period for purposes of further consideration.

In May 2023, as part of the OVEC cost recovery audits pending before the PUCO, intervenors filed positions claiming that costs incurred by OPCo during the 2020 audit period were imprudent and should be disallowed. A hearing was held in November 2023.
Management disagrees with these claims and is unable to predict the impact of these disputes. If any costs are disallowed or refunds are ordered, it could reduce future net income and cash flows and impact financial condition.

Ohio ESP Filings

In January 2023, OPCo filed an application with the PUCO to approve an ESP that included proposed rate adjustments, proposed new riders and the continuation and modification of certain existing riders, including the DIR, effective June 2024 through May 2030. The proposal includes a return on common equity of 10.65% on capital costs for certain riders. In June 2023, intervenors filed testimony opposing OPCo’s plan for various new riders and modifications to existing riders, including the DIR. In September 2023, OPCo and certain intervenors filed a settlement agreement with the PUCO addressing the ESP application. The settlement included a four year term from June 2024 through May 2028, an ROE of 9.7% and continuation of a number of riders including the DIR subject to revenue caps. An order from the PUCO is expected in the first quarter of 2024. If OPCo is ultimately not permitted to fully collect its ESP rates it could reduce future net income and cash flows and impact financial condition.

PSO Rate Matters (Applies to AEP and PSO)

2022 Oklahoma Base Rate Case

In November 2022, PSO filed a request with the OCC for an annual base rate increase of $294 million based upon a 10.4% ROE with a capital structure of 45.4% debt and 54.6% common equity. The requested $294 million annual base rate increase, net of existing rider revenues and certain incremental renewable facility benefits expected to be provided to customers through riders, represented a requested annual increase in rates of $173 million and included a $47 million annual depreciation expense increase related to the accelerated depreciation recovery of the Northeastern Plant, Unit 3 through 2026, and a $16 million annual amortization expense increase to recover intangible plant over a 5-year useful life instead of a 10-year useful life. PSO’s request also included recovery of the 155 MW Rock Falls Wind Facility through base rates to aid PSO’s near-term capacity needs and support compliance with SPP’s 2023 increased capacity planning reserve margin requirements.

In November 2023, the OCC issued a final order approving an annual base rate increase of $131 million based upon a 9.3% ROE. As a result of the final order, PSO is required to exclude Rock Falls Wind Facility from recovery through base rates until a future base case since the facility was placed into service for PSO customers after the conclusion of the customary six-month post-test year period for ratemaking adjustments. In addition, PSO must provide Rock Falls Wind Facility benefits in excess of $21 million on an annual basis to customers through a rider. The order also stipulates PSO’s proposals related to inclusion of a stand-alone NOLC deferred tax asset in rate base will be addressed in a future proceeding, upon receipt of a private letter ruling from the IRS. Effective January 2024, interim rates implemented in May 2023 concluded and updated rates and tariffs were implemented in accordance with the final order. In January 2024, refund of the $18 million interim rate over collection began and will be competed no later than April 2024, in compliance with the final order. In December 2023, PSO appealed certain elements of the OCC’s final order to the Supreme Court of the State of Oklahoma.

2024 Oklahoma Base Rate Case

In January 2024, PSO filed a request with the OCC for a $218 million annual base rate increase based upon a 10.8% ROE with a capital structure of 48.9% debt and 51.1% common equity. PSO requested an expanded transmission cost recovery rider and a mechanism to recover generation costs necessary to comply with SPP’s 2023 increased capacity planning reserve margin requirements. PSO’s request reflects recovery of Northeastern Plant, Unit 3 through 2040.

SWEPCo Rate Matters (Applies to AEP and SWEPCo)

2012 Texas Base Rate Case

In 2012, SWEPCo filed a request with the PUCT to increase annual base rates primarily due to the completion of the Turk Plant. In 2013, the PUCT issued an order affirming the prudence of the Turk Plant but determined that the Turk Plant’s Texas jurisdictional capital cost cap established in a previous Certificate of Convenience and Necessity case also limited SWEPCo’s recovery of AFUDC in addition to limits on its recovery of cash construction costs.

Upon rehearing in 2014, the PUCT reversed its initial ruling and determined that AFUDC was excluded from the Turk Plant’s Texas jurisdictional capital cost cap. As a result, SWEPCo reversed $114 million of a previously recorded regulatory disallowance in 2013. In 2017, the Texas District Court upheld the PUCT’s 2014 order and intervenors filed appeals with the Texas Third Court of Appeals.

In August 2021, the Texas Third Court of Appeals reversed the Texas District Court judgment affirming the PUCT’s order on AFUDC, concluding that the language of the PUCT’s original 2008 order intended to include AFUDC in the Texas
jurisdictional capital cost cap, and remanded the case to the PUCT for future proceedings. In November 2021, SWEPCo and the PUCT submitted Petitions for Review with the Texas Supreme Court. In October 2022, the Texas Supreme Court denied the Petitions for Review submitted by SWEPCo and the PUCT. In December 2022, SWEPCo and the PUCT filed requests for rehearing with the Texas Supreme Court. In June 2023, the Texas Supreme Court denied SWEPCo’s request for rehearing and the case was remanded to the PUCT for future proceedings. In October 2023, SWEPCo filed testimony with the PUCT in the remanded proceeding recommending no refund or disallowance.

On December 14, 2023, the PUCT approved a preliminary order stating the PUCT will not address SWEPCo’s request that would allow the PUCT to find cause to allow SWEPCo to exceed the Texas jurisdictional capital cost cap in the current remand proceeding. As a result of the PUCT’s approval of the preliminary order, SWEPCo believes it is probable the PUCT will disallow capitalized AFUDC in excess of the Texas jurisdictional capital cost cap and recorded a pretax, non-cash disallowance of $86 million in the fourth quarter of 2023. Such determination may reduce SWEPCo’s future revenues by approximately $15 million on an annual basis. On December 21, 2023, SWEPCo filed a motion with the PUCT for reconsideration of the preliminary order. In January 2024, the PUCT denied the motion for reconsideration of the preliminary order.

The PUCT’s December 2023 approval of the preliminary order determined that it will address, in the ongoing PUCT remand proceeding, any potential revenue refunds to customers that may be required by future PUCT orders. In January 2024, the PUCT established a procedural schedule for the remand proceeding. Supplemental testimony from SWEPCo is due in March 2024, intervenor and staff testimony is due in April 2024 and a hearing is scheduled for May 2024. Although SWEPCo does not currently believe any refunds are probable of occurring, SWEPCo estimates it could be required to make customer refunds, including interest, ranging from $0 to $200 million related to revenues collected from February 2013 through December 2023.

2016 Texas Base Rate Case

In 2016, SWEPCo filed a request with the PUCT for a net increase in Texas annual revenues of $69 million based upon a 10% ROE. In January 2018, the PUCT issued a final order approving a net increase in Texas annual revenues of $50 million based upon a ROE of 9.6%, effective May 2017. The final order also included: (a) approval to recover the Texas jurisdictional share of environmental investments placed in-service, as of June 30, 2016, at various plants, including Welsh Plant, Units 1 and 3, (b) approval of recovery of, but no return on, the Texas jurisdictional share of the net book value of Welsh Plant, Unit 2, (c) approval of $2 million in additional vegetation management expenses and (d) the rejection of SWEPCo’s proposed transmission cost recovery mechanism.

As a result of the final order, in 2017 SWEPCo: (a) recorded an impairment charge of $19 million, which included $7 million associated with the lack of return on Welsh Plant, Unit 2 and $12 million related to other disallowed plant investments, (b) recognized $32 million of additional revenues, for the period of May 2017 through December 2017, that was surcharged to customers in 2018 and (c) recognized an additional $7 million of expenses consisting primarily of depreciation expense and vegetation management expense, offset by the deferral of rate case expense. SWEPCo implemented new rates in February 2018 billings. The $32 million of additional 2017 revenues was collected during 2018. In March 2018, the PUCT clarified and corrected portions of the final order, without changing the overall decision or amounts of the rate change. The order has been appealed by various intervenors related to limiting SWEPCo’s recovery of AFUDC on Turk Plant and recovery of Welsh Plant, Unit 2. If certain parts of the PUCT order are overturned, it could reduce future net income and cash flows and impact financial condition.

2020 Texas Base Rate Case

In October 2020, SWEPCo filed a request with the PUCT for a $105 million annual increase in Texas base rates based upon a proposed 10.35% ROE. The request would move transmission and distribution interim revenues recovered through riders into base rates. Eliminating these riders would result in a net annual requested base rate increase of $90 million primarily due to increased investments. SWEPCo subsequently filed a request with the PUCT lowering the requested annual increase in Texas base rates to $100 million which would result in an $85 million net annual base rate increase after moving the proposed riders to rate base.

In January 2022, the PUCT issued a final order approving an annual revenue increase of $39 million based upon a 9.25% ROE. The order also includes: (a) rates implemented retroactively back to March 18, 2021, (b) $5 million of the proposed increase related to vegetation management, (c) $2 million annually to establish a storm catastrophe reserve and (d) the creation of a rider to recover the Dolet Hills Power Station as if it were in rate base until its retirement at the end of 2021 and starting in 2022 the remaining net book value to be recovered as a regulatory asset through 2046. As a result of the final order, SWEPCo recorded a disallowance of $12 million in 2021 associated with the lack of return on the Dolet Hills Power Station. In February 2022, SWEPCo filed a motion for rehearing with the PUCT challenging several errors in the order, which include challenges of the approved ROE, the denial of a reasonable return or carrying costs on the Dolet Hills Power Station and the calculation of the Texas jurisdictional share of the storm catastrophe reserve. In April 2022, the PUCT denied the motion for rehearing. In May
2022, SWEPCo filed a petition for review with the Texas District Court seeking a judicial review of the several errors challenged in the PUCT’s final order.

2020 Louisiana Base Rate Case

In December 2020, SWEPCo filed a request with the LPSC for a $134 million annual increase in Louisiana base rates based upon a proposed 10.35% ROE. SWEPCo’s requested annual increase includes accelerated depreciation related to the Dolet Hills Power Station, Pirkey Power Plant and Welsh Plant, all of which were or are expected to be retired early. SWEPCo also included recovery of Welsh Plant, Unit 2 over the blended useful life of Welsh Plant, Units 1 and 3. SWEPCo subsequently revised the requested annual increase to $95 million to reflect removing hurricane storm restoration costs from the base case filing, to modify the proposed recovery of the Dolet Hills Power Station and revisions to various proposed amortizations. The hurricane costs have been requested in a separate storm filing. See “2021 Louisiana Storm Cost Filing” below for more information.

In January 2023, the LPSC approved a settlement which provides for an annual revenue increase of $27 million based upon a 9.5% ROE and includes: (a) a $21 million increase in base rates effective February 2023, (b) a $14 million rider to recover costs of the Dolet Hills Power Station and Pirkey Plant including a return, (c) an $8 million reduction in fuel rates, (d) adoption of a 3-year formula rate term subject to an earnings band and (e) the recovery of certain incremental SPP charges net of associated revenue and the Louisiana jurisdictional share of the return on and of projected transmission capital investment outside of the earnings band. The settlement agreement did not rule on the prudency of the early retirement of the Dolet Hills Power Station, which is being addressed in a separate proceeding.

The primary differences between SWEPCo’s requested annual rate increase and the agreed upon settlement increase are primarily due to: (a) a reduction in the requested ROE, (b) recovery of the Dolet Hills Power Station and Pirkey Plant over ten years in a separate rider mechanism as opposed to base rates with accelerated depreciation rates, (c) maintaining existing depreciation rates for Welsh Plant, Units 1 and 3 and (d) the severing of SWEPCo’s proposed adjustment to include a stand-alone NOLC deferred tax asset in rate base.

In January 2023, a hearing was held related to the inclusion of a stand-alone NOLC deferred tax asset in rate base. In September 2023, an order was received from the LPSC directing SWEPCo to seek a private letter ruling from the IRS to address the matter.

2021 Louisiana Storm Cost Filing

In 2020, Hurricanes Laura and Delta caused power outages and extensive damage to the SWEPCo service territories, primarily impacting the Louisiana jurisdiction. Following both hurricanes, the LPSC issued orders allowing Louisiana utilities, including SWEPCo, to establish regulatory assets to track and defer expenses associated with these storms. In February 2021, severe winter weather impacted the Louisiana jurisdiction and in March 2021, the LPSC approved the deferral of incremental storm restoration expenses related to the winter storm. In March 2023, SWEPCo and the LPSC staff filed a joint stipulation and settlement agreement with the LPSC which confirmed the prudency of $150 million of deferred incremental storm restoration expenses. The agreement also authorized an interim carrying charge at a rate of 3.125% until the recovery mechanism is determined in phase two of this proceeding. In April 2023, the LPSC issued an order approving the stipulation and settlement agreement. In July 2023, SWEPCo submitted additional information in phase two of this proceeding to obtain a financing order and prudency review of capital investment. The procedural schedule for this case states that a hearing will take place in the second quarter of 2024.
February 2021 Severe Winter Weather Impacts in SPP

In February 2021, severe winter weather had a significant impact in SPP, resulting in significantly increased market prices for natural gas power plants to meet reliability needs for the SPP electric system. For the time period of February 9, 2021, to February 20, 2021, SWEPCo’s natural gas expenses and purchases of electricity still to be recovered from customers are shown in the table below:

December 31, ApprovedApproved
Jurisdiction20232022Recovery PeriodCarrying Charge
(in millions)
Arkansas$54.2 $74.9 6 years(a)
Louisiana97.2 121.7 (b)(b)
Texas101.9 132.4 5 years1.65%
Total$253.3 $329.0 

(a)SWEPCo is permitted to record carrying costs on the unrecovered balance of fuel costs at a weighted-cost of capital approved by the APSC. The APSC will conclude an audit of these costs in 2024. A hearing is scheduled for May 2024.
(b)In March 2021, the LPSC approved a special order granting a temporary modification to the FAC and shortly after SWEPCo began recovery of its Louisiana jurisdictional share of these fuel costs based on a five-year recovery period inclusive of an interim carrying charge equal to the prime rate. The special order states the fuel and purchased power costs incurred will be subject to a future LPSC audit.

If SWEPCo is unable to recover any of the costs relating to the extraordinary fuel and purchases of electricity, or obtain authorization of a reasonable carrying charge on these costs, it could reduce future net income and cash flows and impact financial condition.

FERC Rate Matters

FERC 2019 SPP Transmission Formula Rate Challenge (Applies to AEP, AEPTCo, PSO and SWEPCo)

In May 2021, certain joint customers submitted a formal challenge at the FERC related to the 2020 Annual Update of the 2019 SPP Transmission Formula Rates of the AEP transmission owning subsidiaries within SPP. In March 2022, the FERC issued an order granting the formal challenge on several issues and denying the formal challenge on other issues. Management has determined that the result of the order had an immaterial impact to the financial statements of AEP, AEPTCo, PSO and SWEPCo. In November 2022, certain joint customers appealed the FERC denial of issues to the U.S. Court of Appeals for the District of Columbia Circuit. In January 2024, the court agreed with the FERC’s order and denied the certain joint customers petition for review.

Independence Energy Connection Project (Applies to AEP)

In 2016, PJM approved the Independence Energy Connection Project (IEC) and included it in its Regional Transmission Expansion Plan to alleviate congestion. Transource Energy has an ownership interest in the IEC, which is located in Maryland and Pennsylvania. In June 2020, the Maryland Public Service Commission approved a Certificate of Public Convenience and Necessity to construct the portion of the IEC in Maryland. In May 2021, the Pennsylvania Public Utility Commission (PAPUC) denied the IEC certificate for siting and construction of the portion in Pennsylvania. Transource Energy appealed the PAPUC ruling in Pennsylvania state court and challenged the ruling before the United States District Court for the Middle District of Pennsylvania. In May 2022, the Pennsylvania state court issued an order affirming the PAPUC decision as to state law claims. In December 2023, the United States District Court for the Middle District of Pennsylvania granted summary judgment in favor of Transource Energy, finding that the PAPUC decision violated federal law and the United States Constitution. In January 2024, the PAPUC filed an appeal with the United States Court of Appeals for the Third Circuit. Additional regulatory proceedings before the PAPUC are expected to resume in 2024.

In September 2021, PJM notified Transource Energy that the IEC was suspended to allow for the regulatory and related appeals process to proceed in an orderly manner without breaching milestone dates in the project agreement. At that time, PJM stated that the IEC has not been cancelled and remains necessary to alleviate congestion. PJM continues to evaluate reliability and market efficiency in the area. As of December 31, 2023, AEP’s share of IEC capital expenditures was approximately $93 million, located in Total Property, Plant and Equipment - Net on AEP’s balance sheets. The FERC has previously granted abandonment benefits for this project, allowing the full recovery of prudently incurred costs if the project is cancelled for reasons outside the control of Transource Energy. If any of the IEC costs are not recoverable, it could reduce future net income and cash flows and impact financial condition.
FERC RTO Incentive Complaint (Applies to AEP, AEPTCo and OPCo)

In February 2022, the OCC filed a complaint against AEPSC, American Transmission Systems, Inc. and Duke Energy Ohio, alleging the 50 basis point RTO incentive included in Ohio Transmission Owners’ respective transmission formula rates is not just and reasonable and therefore should be eliminated on the basis that RTO participation is not voluntary, but rather is required by Ohio law. In March 2022, AEPSC filed a motion to dismiss the OCC’s February 2022 complaint with the FERC on the basis of certain deficiencies, including that the complaint fails to request relief that can be granted under FERC regulations because AEPSC is not a public utility nor does it have a transmission rate on file with the FERC. In December 2022, the FERC issued an order removing the 50 basis point RTO incentive from OPCo and OHTCo transmission formula rates effective the date of the February 2022 complaint filing and directed OPCo and OHTCo to provide refunds, with interest, within sixty days of the date of its order. In January 2023, both AEPSC and the OCC filed requests for rehearing with the FERC. In February 2023, in compliance with the FERC’s December 2022 order, AEPSC submitted a filing to the FERC to update OPCo and OHTCo 2023 transmission formula rates to exclude the 50 basis point RTO incentive and provide refunds with interest. In April 2023, the FERC approved the updated transmission formula rates for OPCo and OHTCo and issued an Order on Rehearing affirming its December 2022 decision. During 2023, in compliance with FERC’s December 2022 order, OPCo and OHTCo provided refunds including interest of $5 million and $13 million, respectively. This decision has been appealed to the U.S. Court of Appeals for the Sixth Circuit.

Request to Update AEGCo Depreciation Rates (Applies to AEP and I&M)

In October 2022, AEP, on behalf of AEGCo, submitted proposed revisions to AEGCo’s depreciation rates for its 50% ownership interest in Rockport Plant, Unit 1 and Unit 2, reflected in the UPA between AEGCo and I&M. The proposed depreciation rates for these assets reflect an estimated 2028 retirement date for the Rockport Plant. AEGCo’s previous FERC-approved depreciation rates for Rockport Plant, Unit 1 were based upon a December 31, 2028 estimated retirement date while AEGCo’s previous FERC-approved depreciation rates for Rockport Plant, Unit 2 leasehold improvements were based upon a December 31, 2022 estimated retirement date in conjunction with the termination of the Rockport Plant, Unit 2 lease.

In December 2022, the FERC issued an order approving the proposed AEGCo Rockport depreciation rates effective January 1, 2023, subject to further review and a potential refund. The FERC established a separate proceeding to review: (a) AEGCo’s acquisition value for the Rockport Plant, Unit 2 base generating asset (original cost and accumulated depreciation), (b) the appropriateness of including future capital additions as stated components in proposed depreciation rates, in light of the UPA’s formula rate mechanism, (c) the appropriateness of applying two different depreciation rates to a single asset common to both units and (d) the accounting and regulatory treatment of Rockport Plant, Unit 2 costs of removal and related AROs. In August 2023, AEGCo reached a settlement agreement with the FERC Trial Staff that resolves all issues set for hearing. In September 2023, the settlement agreement was certified to the FERC as uncontested. An order from the FERC on this settlement agreement is expected in 2024. If the FERC finalizes the settlement agreement as proposed, management anticipates the results of the order will not have a material impact on financial condition, results of operations or cash flows.

FERC 2021 PJM and SPP Transmission Formula Rate Challenge (Applies to AEP, AEPTCo, APCo, I&M, PSO and SWEPCo)

The Registrants transitioned to stand-alone treatment of NOLCs in its PJM and SPP transmission formula rates beginning with the 2022 projected transmission revenue requirements and 2021 true-up to actual transmission revenue requirements and provided notice of this change in informational filings made with the FERC. Stand-alone treatment of the NOLCs for transmission formula rates increased the annual revenue requirements for years 2023, 2022 and 2021 by $60 million, $69 million and $78 million, respectively.

In March 2023 and May 2023, certain joint customers submitted a complaint and a formal challenge at the FERC related to the 2022 Annual Update of the 2021 Transmission Formula Rates of the AEP transmission owning subsidiaries within PJM and SPP, respectively. These challenges primarily relate to stand-alone treatment of NOLCs in the transmission formula rates of the AEP transmission owning subsidiaries. AEPSC, on behalf of the AEP transmission owning subsidiaries within PJM and SPP, filed answers to the joint formal challenge and complaint with the FERC in the second quarter of 2023.

In January 2024, the FERC issued two orders, granting the joint customers’ challenges related to stand-alone treatment of NOLCs in the 2021 Transmission Formula Rates of the AEP transmission owning subsidiaries within PJM and SPP. The FERC directed the AEP transmission owning subsidiaries within PJM and SPP to provide refunds with interest on all amounts collected for the 2021 rate year, and for such refunds to be reflected in the annual update for the next rate year. In February 2024, AEPSC on behalf of the AEP transmission owning subsidiaries within PJM and SPP filed requests with the FERC that it grant rehearing and reverse findings in its January 2024 orders or establish hearing procedures to address outstanding factual issues.
As a result of the January 2024 FERC orders, the Registrants’ 2022 and 2023 income statements cumulatively reflect a provision for refund for the probable refund of all NOLC revenues included in transmission formula rates for years 2023, 2022 and 2021. The probable refunds to affiliated and nonaffiliated customers are reflected as Deferred Credits and Other Noncurrent Liabilities on the balance sheets. Refunds probable to be received by affiliated companies, resulting in a reduction to affiliated transmission expense, were deferred as an increase to Regulatory Liabilities or a reduction to Regulatory Assets on the balance sheets where management expects that refunds would be returned to retail customers through authorized retail jurisdiction rider mechanisms. The FERC directed cash refunds with interest related to the 2021 rate year to occur through the annual update for the next rate year, which will be invoiced by PJM and SPP primarily in 2025. The Registrants have not yet been directed to make cash refunds related to the 2022 or 2023 rate years.

The FERC's January 2024 orders reduced AEP and AEPTCo's 2023 pretax net income by approximately $76 million and $74 million, respectively. The impact of the FERC's orders on the pretax net income of AEP's remaining Registrant Subsidiaries was not material.


Request to Update SWEPCo Generation Depreciation Rates (Applies to AEP and SWEPCo)
In October 2023, SWEPCo filed an application to revise its generation wholesale customer’s contracts to reflect an increase in the annual revenue requirement of approximately $5 million for updated depreciation rates and allow for the return on and of FERC customers jurisdictional share of regulatory assets associated with retired plants. In November 2023, certain intervenors filed a motion with the FERC protesting and recommending the rejection of SWEPCo’s filings. In December 2023, the FERC issued an order approving the proposed rates effective January 1, 2024, subject to further review and refund and established hearing and settlement proceedings. If SWEPCo is unable to recover the remaining regulatory assets associated with retired plants, it could reduce future net income and cash flows and impact financial condition.