Acquisitions and Dispositions
9 Months Ended
Sep. 30, 2020
Acquisitions and Dispositions ACQUISITIONS AND DISPOSITIONS
The disclosures in this note apply to AEP unless indicated otherwise.

ACQUISITIONS

Sempra Renewables LLC (Generation & Marketing Segment)

In April 2019, AEP acquired Sempra Renewables LLC and its ownership interests in 724 MWs of wind generation and battery assets valued at approximately $1.1 billion. This acquisition is part of AEP’s strategy to grow its renewable generation portfolio and to diversify generation resources. AEP paid $580 million in cash and acquired a 50% ownership interest in five non-consolidated joint ventures with net assets valued at $404 million as of the acquisition date (which includes $364 million of existing debt obligations). Additionally, the transaction included the acquisition of two tax equity partnerships and the associated recognition of noncontrolling tax equity interest of $135 million.

Upon closing of the purchase, Sempra Renewables LLC was legally renamed AEP Wind Holdings LLC. AEP Wind Holdings LLC develops, owns and operates, or holds interests in, wind generation facilities in the United States. The operating wind generation portfolio includes seven wind farms. Five wind farms are jointly-owned with BP Wind Energy, and two wind farms are consolidated by AEP and are tax equity partnerships with nonaffiliated noncontrolling interests. All seven wind farms have long-term PPAs for 100% of their energy production.

Parent has issued guarantees over the performance of the joint ventures. If a joint venture were to default on payments or performance, Parent would be required to make payments on behalf of the joint venture. As of September 30, 2020, the maximum potential amount of future payments associated with these guarantees was $166 million, with the last guarantee expiring in December 2037. The non-contingent liability recorded associated with these guarantees was $31 million, with an additional $1 million expected credit loss liability for the contingent portion of the guarantees. Management considered historical losses, economic conditions, and reasonable and supportable forecasts in the calculation of the expected credit loss. As the joint ventures generate cash flows through PPAs, the measurement of the contingent portion of the guarantee liability is based upon assessments of the credit quality and default probabilities of the respective PPA counterparties.

Santa Rita East (Generation & Marketing Segment)

In July 2019, AEP acquired a 75% interest, or 227 MWs, in Santa Rita East for approximately $356 million. In accordance with the accounting guidance for “Business Combinations,” management determined that the acquisition of Santa Rita East represents an asset acquisition. Additionally, and in accordance with the accounting guidance for “Consolidation,” management concluded that Santa Rita East is a VIE. As a result, to account for the initial consolidation of Santa Rita East, management applied the acquisition method by allocating the purchase price based on the relative fair value of the assets acquired and noncontrolling interest assumed.  The fair value of the primary assets acquired and the noncontrolling interest assumed was determined using the market approach.  The key input assumptions were the transaction price paid for AEP’s interest in Santa Rita East and recent third-party market transactions for similar wind farms.

Desert Sky Wind Farm and Trent Wind Farm (Generation & Marketing Segment)

In August 2020, AEP exercised its call right which required the nonaffiliated member of Desert Sky Wind Farm LLC and Trent Wind Farm LLC (collectively the LLCs) to sell its noncontrolling interest to AEP. The exercise price for the call right was determined using a discounted cash flow model with agreed input assumptions as well as updates to certain assumptions reasonably expected based on the actual results of the LLCs. As a result, the LLCs are wholly-owned by AEP and management has concluded that the LLCs are no longer VIEs. AEP paid $57 million in cash, derecognized $63 million of Redeemable Noncontrolling Interest within Mezzanine Equity and recorded an increase of $6 million of Paid-In Capital on the balance sheets.
DISPOSITIONS

Conesville Plant (Generation & Marketing Segment)

In June 2020, AEP and a non-affiliated joint-owner executed an Environmental Liability and Property Transfer and Asset Purchase Agreement with a non-affiliated third-party related to the merchant Conesville Plant site. The purchaser took ownership of the assets and assumed responsibility for environmental liabilities, including ash pond closure, asbestos abatement and decommissioning and demolition of the Conesville Plant site. In consideration of the transfer of the acquired assets to the purchaser and the purchaser’s assumption of liabilities, AEP will pay approximately $98 million, derecognized $106 million in ARO and recorded an immaterial gain on the transaction which is recorded in Other Operation on the statements of income. AEP paid approximately $26 million in June 2020 and will make additional payments totaling $28 million in quarterly installments from October 2020 to April 2021 and payments totaling $44 million in quarterly installments from July 2021 to July 2022.

Oklaunion Power Station (Applies to AEP, AEP Texas and PSO)

In October 2020, AEP Texas, PSO and a non-affiliated joint-owner executed an Environmental Liability and Property Transfer and Asset Purchase Agreement with a non-affiliated third-party related to the Oklaunion Power Station site. The purchaser took ownership of the assets and assumed responsibility for environmental liabilities, including ash pond closure, asbestos abatement and decommissioning and demolition of the Oklaunion Power Station site. The sale is expected to have an immaterial impact on the financial statements in the fourth quarter of 2020.