Rate Matters - East Companies (Details)
$ in Millions
1 Months Ended 12 Months Ended
Feb. 23, 2016
USD ($)
Jan. 31, 2016
USD ($)
Dec. 31, 2015
USD ($)
$ / MWD
$ / MWh
MW
Dec. 31, 2014
USD ($)
Public Utilities, General Disclosures [Line Items]        
Noncurrent Regulatory Assets     $ 5,140.3 $ 4,263.7
Appalachian Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Noncurrent Regulatory Assets     1,154.2 857.9
Indiana Michigan Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Noncurrent Regulatory Assets     804.3 536.2
Ohio Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Noncurrent Regulatory Assets     1,113.0 $ 1,318.9
Kentucky 2014 Base Rate Case [Member]        
Public Utilities, General Disclosures [Line Items]        
Requested Net Increase in Rates     70.0  
Recommended Net Increase in Rates as Proposed in Stipulation Agreement     45.0  
Recommended Increase in Rider Rates as Proposed in Stipulation Agreement     68.0  
Recommended Decrease in Annual Base Rates as Proposed in Stipulation Agreement     23.0  
Amount of Storm Costs Recommended for Recovery as Proposed in Stipulation Agreement     12.0  
Amount of Off-System Sales Margins Included in the Annual Base Rates as Proposed in Stipulation Agreement     $ 15.0  
Percentage of Off-System Sales Margins Above the Amount in Base Rates to be Shared with Customers as Proposed in Stipulation Agreement     75.00%  
Percentage of Off-System Sales Margins Above the Amount in Base Rates to be Retained by KPCo as Proposed in Stipulation Agreement     25.00%  
Approved Net Revenue Increase     $ 45.0  
Amount of IGCC and Carbon Capture Costs Approved for Recovery     $ 2.0  
Recovery Period of Approved IGCC and Carbon Capture Costs     25 years  
Kentucky Fuel Adjustment Clause Review [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount of Regulatory Disallowance Resulting from a Commission Order     $ 36.0  
Ohio Electric Security Plan Filing [Member]        
Public Utilities, General Disclosures [Line Items]        
Approved Return On Equity     10.20%  
PUCO-ordered Fixed Price per MW Day for Customers Who Switch During ESP Period | $ / MWD     188.88  
Reliability Pricing Model Rate per MW Day in Effect through May 2014 | $ / MWD     34  
Reliability Pricing Model Rate per MW Day in Effect from June 2014 through May 2015 | $ / MWD     150  
Retail Stability Rider through May 2014 ($ Per MWh) | $ / MWh     3.50  
Retail Stability Rider for the Period June 2014 through May 2015 ($ per MWh) | $ / MWh     4.00  
Amount of Retail Stability Rider Applied to the Deferred Capacity Costs ($ per MWh) | $ / MWh     1.00  
Retail Stability Rider Rate to be Continued Until Capacity Deferral Balance is Collected as Ordered by the PUCO ($ per MWh) | $ / MWh     4.00  
Deferred Capacity Costs Recovery Period as Ordered by PUCO (in months)     32 months  
Annual Retail Share of Fixed Fuel Costs     $ 90.0  
Return on Equity Proposed in PPA Stipulation Agreement     10.38%  
Solar Energy Projects to be Developed and Implemented by 2021 as Proposed in Stipulation Agreement (in MWs) | MW     400  
Wind Energy Projects to be Developed and Implemented by 2021 as Proposed in Stipulation Agreement (in MWs) | MW     500  
Percentage of Output to be Received from Solar and Wind Projects as Proposed in Stipulation Agreement     100.00%  
Maximum Ownership Percentage of Solar and Wind Projects as Proposed in Stipulation Agreement     50.00%  
Future Commitment to Support the Development of a Large Solar Farm     $ 20.0  
Ohio Electric Security Plan Filing [Member] | Ohio Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Approved Return On Equity     10.20%  
PUCO-ordered Fixed Price per MW Day for Customers Who Switch During ESP Period | $ / MWD     188.88  
Reliability Pricing Model Rate per MW Day in Effect through May 2014 | $ / MWD     34  
Reliability Pricing Model Rate per MW Day in Effect from June 2014 through May 2015 | $ / MWD     150  
Retail Stability Rider through May 2014 ($ Per MWh) | $ / MWh     3.50  
Retail Stability Rider for the Period June 2014 through May 2015 ($ per MWh) | $ / MWh     4.00  
Amount of Retail Stability Rider Applied to the Deferred Capacity Costs ($ per MWh) | $ / MWh     1.00  
Retail Stability Rider Rate to be Continued Until Capacity Deferral Balance is Collected as Ordered by the PUCO ($ per MWh) | $ / MWh     4.00  
Deferred Capacity Costs Recovery Period as Ordered by PUCO (in months)     32 months  
Annual Retail Share of Fixed Fuel Costs     $ 90.0  
Return on Equity Proposed in PPA Stipulation Agreement     10.38%  
Solar Energy Projects to be Developed and Implemented by 2021 as Proposed in Stipulation Agreement (in MWs) | MW     400  
Wind Energy Projects to be Developed and Implemented by 2021 as Proposed in Stipulation Agreement (in MWs) | MW     500  
Percentage of Output to be Received from Solar and Wind Projects as Proposed in Stipulation Agreement     100.00%  
Maximum Ownership Percentage of Solar and Wind Projects as Proposed in Stipulation Agreement     50.00%  
Future Commitment to Support the Development of a Large Solar Farm     $ 20.0  
Ohio Fuel Adjustment Clause Audit - 2009 [Member]        
Public Utilities, General Disclosures [Line Items]        
2008 Coal Contract Settlement Proceeds to be Applied to Deferred Fuel Balance as Originally Ordered by the PUCO     65.0  
Net Favorable Fuel Adjustment Recorded in 2012 Based on Fuel Adjustment Clause Audit Rehearing     30.0  
Ohio Fuel Adjustment Clause Audit - 2009 [Member] | Ohio Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
2008 Coal Contract Settlement Proceeds to be Applied to Deferred Fuel Balance as Originally Ordered by the PUCO     65.0  
Net Favorable Fuel Adjustment Recorded in 2012 Based on Fuel Adjustment Clause Audit Rehearing     30.0  
Special Rate Mechanism For Ormet [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount of Foregone Revenues to be Collected Through the Economic Development Rider as Approved in the Economic Development Rider Filing     39.0  
Remaining Ormet Deferral Allowed to be Requested Upon PUCO Adoption of Ormet Stipulation Agreement     10.0  
Remaining Ormet Deferral Approved for Recovery     10.0  
Deferred Fuel Adjustment Clause Related to Ormet Interim Arrangement as of September 2009     64.0  
Unrecognized Equity Carrying Costs Related to Ormet Interim Arrangement as of September 2009     2.0  
Special Rate Mechanism For Ormet [Member] | Ohio Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount of Foregone Revenues to be Collected Through the Economic Development Rider as Approved in the Economic Development Rider Filing     39.0  
Remaining Ormet Deferral Allowed to be Requested Upon PUCO Adoption of Ormet Stipulation Agreement     10.0  
Remaining Ormet Deferral Approved for Recovery     10.0  
Deferred Fuel Adjustment Clause Related to Ormet Interim Arrangement as of September 2009     64.0  
Unrecognized Equity Carrying Costs Related to Ormet Interim Arrangement as of September 2009     2.0  
Transmission Distribution and Storage System Improvement Charge (TDSIC) [Member]        
Public Utilities, General Disclosures [Line Items]        
Estimated Cost of Capital Improvements and Associated Operation and Maintenance Expenses     787.0  
Transmission Distribution and Storage System Improvement Charge (TDSIC) [Member] | Indiana Michigan Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Estimated Cost of Capital Improvements and Associated Operation and Maintenance Expenses     787.0  
West Virginia Base Rate Case - 2014 [Member]        
Public Utilities, General Disclosures [Line Items]        
Approved Base Rate Increase     $ 99.0  
Approved Return On Equity     9.75%  
Amount of Annual Delayed Customer Billing to Residential Customers     $ 25.0  
Approved Annual Vegetation Management Rider     45.0  
Approved Recovery of Previously Recorded Regulatory Assets     89.0  
West Virginia Base Rate Case - 2014 [Member] | Appalachian Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Approved Base Rate Increase     $ 85.0  
Approved Return On Equity     9.75%  
Amount of Annual Delayed Customer Billing to Residential Customers     $ 22.0  
Approved Annual Vegetation Management Rider     38.0  
Approved Recovery of Previously Recorded Regulatory Assets     77.0  
Virginia Regulatory Asset Proceeding - 2015 [Member]        
Public Utilities, General Disclosures [Line Items]        
Amounts of Regulatory Assets Under Review in Separate Proceeding     10.0  
Virginia Regulatory Asset Proceeding - 2015 [Member] | Appalachian Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Amounts of Regulatory Assets Under Review in Separate Proceeding     10.0  
Deferred Capacity Costs [Member] | Ohio Electric Security Plan Filing [Member]        
Public Utilities, General Disclosures [Line Items]        
Capacity Deferral Balance as of May 2015 Subject to Audit by the PUCO     444.0  
Noncurrent Regulatory Assets     359.0  
Amount of Deferred Capacity Costs Collected from Customers     222.0  
Deferred Capacity Costs [Member] | Ohio Electric Security Plan Filing [Member] | Ohio Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Capacity Deferral Balance as of May 2015 Subject to Audit by the PUCO     444.0  
Noncurrent Regulatory Assets     359.0  
Amount of Deferred Capacity Costs Collected from Customers     222.0  
Subsequent Event [Member] | Kingsport Base Rate Case [Member]        
Public Utilities, General Disclosures [Line Items]        
Requested Base Rate Increase   $ 12.0    
Requested Return on Equity   10.66%    
Subsequent Event [Member] | West Virginia Base Rate Case - 2014 [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount Of Recovery Requested Related To Delayed Billing Including Carrying Charges $ 29.0      
Subsequent Event [Member] | West Virginia Base Rate Case - 2014 [Member] | Appalachian Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount Of Recovery Requested Related To Delayed Billing Including Carrying Charges $ 26.0      
Big Sandy Plant, Unit 2 [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount Reclassified as Regulatory Assets Upon Retirement of the Plant     $ 194.0  
Amortization Period of Approved Regulatory Assets Related to Plant Retirement     25 years  
Tanners Creek Plant, Units 1-4 [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount Reclassified as Regulatory Assets Upon Retirement of the Plant     $ 265.0  
Amortization Period of Approved Regulatory Assets Related to Plant Retirement     29 years  
Amount Reclassified as Regulatory Assets Upon Plant Retirement Currently Not Being Amortized     $ 38.0  
Tanners Creek Plant, Units 1-4 [Member] | Indiana Michigan Power Co [Member]        
Public Utilities, General Disclosures [Line Items]        
Amount Reclassified as Regulatory Assets Upon Retirement of the Plant     $ 265.0  
Amortization Period of Approved Regulatory Assets Related to Plant Retirement     29 years  
Amount Reclassified as Regulatory Assets Upon Plant Retirement Currently Not Being Amortized     $ 38.0