XML 92 R63.htm IDEA: XBRL DOCUMENT v3.22.1
Regulatory Matters (Tables)
3 Months Ended
Mar. 31, 2022
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at March 31, 2022 and December 31, 2021 were as follows:
Regulatory ClauseBalance Sheet Line ItemMarch 31,
2022
December 31, 2021
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory assets, deferred$12 $16 
Rate CNP PPAOther regulatory assets, deferred84 84 
Retail Energy Cost Recovery(*)
Other regulatory assets, deferred46 126 
Georgia Power
Fuel Cost RecoveryDeferred under recovered fuel clause revenues$494 $410 
Mississippi Power
Fuel Cost RecoveryOther customer accounts receivable$16 $
Ad Valorem Tax
Other regulatory assets, current
12 12 
Other regulatory assets, deferred
33 37 
Southern Company Gas
Natural Gas Cost RecoveryNatural gas cost under recovery$306 $266 
Other regulatory assets, deferred44 207 
Other regulatory liabilities, current13 — 
(*)In accordance with an Alabama PSC order issued on February 1, 2022, Alabama Power applied $126 million of its 2021 Rate RSE refund to reduce the Rate ECR under recovered balance.
Nuclear Construction Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4, including contingency, through the end of the first quarter 2023 and the fourth quarter 2023, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$10,294 
Construction contingency estimate107 
Total project capital cost forecast(a)(b)
10,401 
Net investment at March 31, 2022(b)
(8,715)
Remaining estimate to complete$1,686 
(a)Includes approximately $590 million of costs that are not shared with the other Vogtle Owners and approximately $440 million of incremental costs under the cost-sharing and tender provisions of the joint ownership agreements described below. Excludes financing costs expected to be capitalized through AFUDC of approximately $377 million, of which $221 million had been accrued through March 31, 2022.
(b)Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Infrastructure Replacement Programs and Capital Projects
Capital expenditures incurred under specific infrastructure replacement programs and capital projects during the first three months of 2022 were as follows:
UtilityProgramThree Months Ended March 31, 2022
(in millions)
Nicor GasInvesting in Illinois$51 
Virginia Natural GasSteps to Advance Virginia's Energy14 
Atlanta Gas LightSystem Reinforcement Rider14 
Chattanooga GasPipeline Replacement Program
Total$80