Commitments, Guarantees and Contingencies - Transmission (Details)
$ in Millions
Dec. 31, 2019
USD ($)
Miles
kV
MW
Great Northern Transmission Line [Member]  
Transmission [Line Items]  
Total Project Costs Incurred to Date $ 633.3
Manitoba Hydro [Member] | Great Northern Transmission Line [Member]  
Transmission [Line Items]  
Project Costs Recovered from Counterparty $ 339.6
Minnesota Power [Member] | Great Northern Transmission Line [Member]  
Transmission [Line Items]  
Transmission Line Length (Miles) | Miles 220
Transmission Line Capacity (kV) | kV 500
Total Project Cost in the U.S. $ 325.0
Minnesota Power [Member] | Great Northern Transmission Line [Member] | Maximum [Member]  
Transmission [Line Items]  
Total Project Cost in the U.S. $ 700.0
Manitoba Hydro PPA [Member] | Manitoba Hydro [Member]  
Transmission [Line Items]  
Output Being Purchased (MW) | MW 250