XML 64 R50.htm IDEA: XBRL DOCUMENT v3.19.2
Commitments, Guarantees and Contingencies - Transmission (Details)
$ in Millions
Jun. 30, 2019
USD ($)
kV
Miles
MW
Great Northern Transmission Line [Member]  
Transmission [Line Items]  
Total Project Cost in the U.S. $ 750.0
Total Project Costs Incurred to Date 510.8
Manitoba Hydro [Member] | Great Northern Transmission Line [Member]  
Transmission [Line Items]  
Project Costs Recovered from Counterparty $ 272.7
Minnesota Power [Member] | Great Northern Transmission Line [Member]  
Transmission [Line Items]  
Transmission Line Length (Miles) | Miles 220
Transmission Line Capacity (kV) | kV 500
Total Project Cost in the U.S. $ 345.0
Manitoba Hydro PPA [Member] | Manitoba Hydro [Member]  
Transmission [Line Items]  
Output Being Purchased (MW) | MW 250