XML 28 R14.htm IDEA: XBRL DOCUMENT v3.10.0.1
Regulatory Matters
6 Months Ended
Jun. 30, 2018
Regulated Operations [Abstract]  
Regulatory Matters [Text Block]
REGULATORY MATTERS

Regulatory matters are summarized in Note 4. Regulatory Matters to our Consolidated Financial Statements in our 2017 Form 10‑K, with additional disclosure provided in the following paragraphs.

Electric Rates. Entities within our Regulated Operations segment file for periodic rate revisions with the MPUC, PSCW or FERC. As authorized by the MPUC, Minnesota Power also recognizes revenue under cost recovery riders for transmission, renewable, and environmental investments and expenditures. (See Transmission Cost Recovery Rider, Renewable Cost Recovery Rider and Environmental Improvement Rider.) Revenue from cost recovery riders was $28.0 million and $52.1 million for the quarter and six months ended June 30, 2018, respectively ($24.4 million and $48.6 million for the quarter and six months ended June 30, 2017, respectively).

2016 Minnesota General Rate Case. In November 2016, Minnesota Power filed a retail rate increase request with the MPUC which sought an average increase of approximately 9 percent for retail customers. The rate filing sought a return on equity of 10.25 percent and a 53.81 percent equity ratio. On an annualized basis, the requested final rate increase would have generated approximately $55 million in additional revenue. In December 2016, Minnesota Power filed a request to modify its original interim rate proposal, reducing its requested interim rate increase to $34.7 million from the original request of approximately $49 million due to a change in its electric sales forecast. In December 2016 orders, the MPUC accepted the November 2016 filing as complete and authorized an annual interim rate increase of $34.7 million beginning in January 2017.

In February 2017, Minnesota Power filed an additional request to further reduce its requested interim rate increase. In an April 2017 order, the MPUC approved Minnesota Power’s updated retail rate request resulting in a reduction in the annual interim rate increase to $32.2 million beginning in May 2017. As a result of working with intervenors and further developments as the rate review progressed, Minnesota Power’s final rate request was adjusted to approximately $49 million on an annualized basis. In an order dated March 12, 2018, the MPUC affirmed determinations made at a hearing on January 18, 2018, regarding Minnesota Power’s general rate case including allowing a return on common equity of 9.25 percent and a 53.81 percent equity ratio. Upon commencement of final rates, we expect additional revenue of approximately $13 million on an annualized basis. Final rates are expected to commence in the fourth quarter of 2018; interim rates will be collected through this period which are fully offset by the recognition of a corresponding reserve. Minnesota Power has recorded a reserve for an interim rate refund of $49.2 million as of June 30, 2018 ($32.3 million as of December 31, 2017). The MPUC also disallowed Minnesota Power’s regulatory asset for deferred fuel adjustment clause costs due to the anticipated adoption of a forward-looking fuel adjustment clause methodology resulting in a $19.5 million pre-tax charge to Fuel, Purchased Power and Gas – Utility in the fourth quarter of 2017.

As part of its decision in Minnesota Power’s 2016 general rate case, the MPUC extended the depreciable lives of Boswell Unit 3, Unit 4 and common facilities to 2050 primarily to mitigate rate increases for our customers, and shortened the depreciable lives of Boswell Unit 1 and Unit 2 to 2022, resulting in a net decrease to depreciation expense of approximately $25 million in the fourth quarter of 2017.

On April 2, 2018, Minnesota Power filed a petition with the MPUC requesting reconsideration of certain decisions in the MPUC’s order dated March 12, 2018, collectively representing approximately $20 million to $25 million in additional revenue on an annualized basis. Minnesota Power’s petition included requesting reconsideration of the allowed return on common equity, recovery of the prepaid pension asset in rate base, certain disallowed expenses, and certain transmission revenue adjustments. In an order dated May 29, 2018, the MPUC denied Minnesota Power’s petition for reconsideration and accepted a Minnesota Department of Commerce request for reconsideration reducing the depreciable lives of Boswell Unit 3, Unit 4 and common facilities to 2035 while utilizing the benefits of the lower federal income tax rate enacted as part of the TCJA to mitigate the impact on customer rates.

Energy-Intensive Trade-Exposed Customer Rates. An EITE customer ratemaking law was enacted in 2015, which established a Minnesota energy policy to have competitive rates for certain industries such as mining and forest products. In 2015, Minnesota Power filed a rate schedule petition with the MPUC for EITE customers and a corresponding rider for EITE cost recovery. In a March 2016 order, the MPUC dismissed the petition without prejudice. In June 2016, Minnesota Power filed a revised EITE petition with the MPUC which included additional information on the net benefits analysis, limits on eligible customers and term lengths for the EITE discount. The rate adjustments were intended to be revenue and cash flow neutral to Minnesota Power. The MPUC approved a reduction in rates for EITE customers in a December 2016 order and subsequently approved cost recovery in an April 2017 order; collection of the discount was subject to the MPUC’s review of Minnesota Power’s compliance filing implementing approval of a recovery mechanism, with the subsequent order issued in October 2017 that modified the April 2017 order. During 2017, Minnesota Power provided discounts of $8.6 million that were recorded as a regulatory asset.
NOTE 6. REGULATORY MATTERS (Continued)
Electric Rates (Continued)

In September 2017, Minnesota Power informed its EITE customers that it had suspended the EITE discount due to a concern that it was not revenue and cash flow neutral to Minnesota Power based on an MPUC decision at a hearing in September 2017, as well as the interim rate reduction and decisions in its 2016 general rate case. Based on the MPUC’s decisions at a hearing on January 18, 2018, as part of Minnesota Power’s 2016 general rate case, Minnesota Power reinstated the EITE discount effective January 1, 2018. Minnesota Power expects the discount to EITE customers to be approximately $15 million annually based on EITE customer current operating levels. While interim rates are in effect for Minnesota Power’s 2016 general rate case, discounts provided to EITE customers will offset interim rate refund reserves for non-EITE customers. Minnesota Power provided $3.8 million and $8.1 million of discounts to EITE customers during the quarter and six months ended June 30, 2018, respectively ($3.6 million and $5.9 million for the quarter and six months ended June 30, 2017, respectively).

FERC-Approved Wholesale Rates. Minnesota Power has 16 non-affiliated municipal customers in Minnesota. SWL&P is a Wisconsin utility and a wholesale customer of Minnesota Power. All wholesale contracts include a termination clause requiring a three-year notice to terminate.

Minnesota Power’s wholesale electric contract with the Nashwauk Public Utilities Commission is effective through at least December 31, 2032. No termination notice may be given for this contract prior to July 1, 2029. The wholesale electric service contracts with SWL&P and another municipal customer are effective through at least August 31, 2021, and through June 30, 2019, respectively. Under the agreement with SWL&P, no termination notice has been given. The other municipal customer provided termination notice for its contract in 2016. Minnesota Power currently provides approximately 29 MW of average monthly demand to this customer. The rates included in these three contracts are set each July 1 based on a cost-based formula methodology, using estimated costs and a rate of return that is equal to Minnesota Power’s authorized rate of return for Minnesota retail customers. The formula-based rate methodology also provides for a yearly true-up calculation for actual costs incurred.

Minnesota Power’s wholesale electric contracts with 14 municipal customers are effective through varying dates ranging from 2024 through 2029 with a majority effective through at least December 31, 2024. No termination notices may be given prior to three years before maturity. These contracts include fixed capacity charges through 2018; beginning in 2019, the capacity charge will be determined using a cost-based formula methodology with limits on the annual change from the previous year’s capacity charge. The base energy charge for each year of the contract term will be set each January 1, subject to monthly adjustment, and will also be determined using a cost-based formula methodology.

Transmission Cost Recovery Rider. Minnesota Power has an approved cost recovery rider for certain transmission investments and expenditures. In a 2016 order, the MPUC approved Minnesota Power’s updated customer billing rates allowing Minnesota Power to charge retail customers on a current basis for the costs of constructing certain transmission facilities plus a return on the capital invested. As a result of the MPUC approval of the certificate of need for the GNTL in 2015, the project is eligible for cost recovery under the existing transmission cost recovery rider. Minnesota Power is funding the construction of the GNTL with a subsidiary of Manitoba Hydro (see Great Northern Transmission Line), and anticipates including its portion of the investments and expenditures for the GNTL in future transmission bill factor filings.

Renewable Cost Recovery Rider. Minnesota Power has an approved cost recovery rider for investments and expenditures related to Bison. The cost recovery rider allows Minnesota Power to charge retail customers on a current basis for the costs of certain renewable investments plus a return on the capital invested. Updated customer billing rates for the renewable cost recovery rider were approved by the MPUC in a November 2017 order. On June 5, 2018, Minnesota Power made a renewable resources factor filing. Upon approval of the filing, Minnesota Power will be authorized to include updated billing rates on customer bills.

Minnesota Power also has approval for current cost recovery of investments and expenditures related to compliance with the Minnesota Solar Energy Standard. (See Minnesota Solar Energy Standard.) Currently, there is no approved customer billing rate for solar costs.

Environmental Improvement Rider. Minnesota Power has an approved environmental improvement rider for investments and expenditures related to the implementation of the Boswell Unit 4 mercury emissions reduction plan completed in 2015. Updated customer billing rates for the environmental improvement rider were provisionally approved by the MPUC in an order dated June 20, 2018, subject to further review by the MPUC.
NOTE 6. REGULATORY MATTERS (Continued)
Electric Rates (Continued)

Fuel Adjustment Clause Reform. In a December 2017 order, the MPUC adopted a three-year program to implement certain procedural reforms to the Minnesota utilities’ automatic fuel adjustment clause (FAC) for fuel and purchased power. The order will change the method of accounting for all Minnesota electric utilities to a monthly budgeted, forward-looking FAC with an annual prudence review and true-up to actual allowed costs. The MPUC is seeking input from Minnesota electric utilities and other stakeholders on the implementation and transition accounting needed to adopt the change. The three-year program is expected to begin in 2019.

Tax Cuts and Jobs Act of 2017. In December 2017, the MPUC opened a docket to review the effects of the TCJA on electric and natural gas rates and services in Minnesota, including the legislation’s impact on tax rates and utilities’ deferred income tax assets and liabilities. On March 2, 2018, Minnesota Power submitted an initial filing to the MPUC regarding the impacts of the TCJA on Minnesota Power. As part of Minnesota Power’s rate case, in an order dated May 29, 2018, the MPUC directed Minnesota Power to utilize the benefits of lower federal income tax rates enacted as part of the TCJA to offset a reduction in the depreciable lives of Boswell Unit 3, Unit 4 and common facilities to 2035 that would have otherwise resulted in an increase in customer rates. The treatment of the impact of the TCJA on Minnesota Power’s deferred income tax assets and liabilities is still subject to this regulatory proceeding.

On January 10, 2018, the PSCW opened a docket to review the effects of the TCJA and directed Wisconsin utilities to defer its impacts until further direction was provided by the PSCW. On February 9, 2018, SWL&P filed comments with the PSCW regarding the impacts of the TCJA on SWL&P. In this filing, SWL&P proposed deferring the benefits of the TCJA and incorporating any deferred refunds or credits into its next general rate case. In an order dated May 24, 2018, the PSCW directed SWL&P to refund the benefits of the lower federal income tax rates enacted as part of the TCJA on customer bills beginning in July 2018. Any changes in deferred income taxes will be adjusted as part of SWL&P’s rate filing. (See 2018 Wisconsin General Rate Case.)

We have recorded the impact of the remeasurement of deferred income tax assets and liabilities in 2017 resulting from the TCJA for Minnesota Power and SWL&P as regulatory assets and liabilities as the benefits are deferred pending the outcome of regulatory proceedings. Most of the benefits for Minnesota Power and SWL&P are expected to be passed back to customers over time primarily based upon the normalization provisions of the U.S. Internal Revenue Code over the life of the related property, plant and equipment with the remainder expected to be passed back based upon the outcome of regulatory proceedings. We are unable to predict the outcome of these regulatory proceedings.

2016 Wisconsin General Rate Case. SWL&P’s current retail rates are based on a 2017 PSCW retail rate order effective since August 2017 that allows for a 10.5 percent return on common equity and a 55 percent equity ratio. SWL&P’s retail rates prior to August 2017 were based on a 2012 PSCW retail rate order that provided for a 10.9 percent return on equity. On an annualized basis, SWL&P expects to collect additional revenue of $2.5 million under the 2017 PSCW retail rate order.

2018 Wisconsin General Rate Case. On May 25, 2018, SWL&P filed a rate increase request with the PSCW requesting an average increase of 2.7 percent for retail customers (2.0 percent increase in electric rates; 2.3 percent increase in natural gas rates; and 8.3 percent increase in water rates). The filing seeks an overall return on equity of 10.5 percent and a 55.41 percent equity ratio. On an annualized basis, this filing is expected to result in additional revenue of approximately $2.4 million.

Integrated Resource Plan. In 2015, Minnesota Power filed its 2015 IRP with the MPUC, which included an analysis of a variety of existing and future energy resource alternatives and a projection of customer cost impact by class. The 2015 IRP also contained steps in Minnesota Power’s EnergyForward strategic plan including the economic idling of Taconite Harbor Units 1 and 2 which occurred in 2016, the ceasing of coal-fired operations at Taconite Harbor in 2020, and the addition of between 200 MW and 300 MW of natural gas-fired generation in the next decade. In a 2016 order, the MPUC approved Minnesota Power’s 2015 IRP with modifications. The order accepted Minnesota Power’s plans for Taconite Harbor, directed Minnesota Power to retire Boswell Units 1 and 2 no later than 2022, required an analysis of generation and demand response alternatives to be filed with a natural gas resource proposal, and required Minnesota Power to conduct request for proposals for additional wind, solar and demand response resource additions subject to further MPUC approvals. In 2016, Minnesota Power announced Boswell Units 1 and 2 will be retired, which is expected to occur in the fourth quarter of 2018.
NOTE 6. REGULATORY MATTERS (Continued)
Integrated Resource Plan (Continued)

In July 2017, Minnesota Power submitted a resource package to the MPUC requesting approval of PPAs for the output of a 250 MW wind energy facility and a 10 MW solar energy facility as well as approval of a 250 MW natural gas energy PPA. These agreements are subject to MPUC approval of the construction of NTEC, a 525 MW to 550 MW combined‑cycle natural gas‑fired generating facility which will be jointly owned by Dairyland Power Cooperative and a subsidiary of ALLETE. Minnesota Power would purchase approximately 50 percent of the facility's output starting in 2025. In a September 2017 order, the MPUC approved Minnesota Power’s request to extend the next IRP filing deadline until October 1, 2019, and Minnesota Power’s request that approval for the natural gas energy PPA be decided through a contested case process. On July 2, 2018, an administrative law judge issued a recommendation that the MPUC deny approval of the NTEC agreements; the recommendation is not binding on the MPUC. On July 23, 2018, Minnesota Power filed exceptions to the administrative law judge’s recommendation. The MPUC is expected to hold a hearing in the fourth quarter of 2018 on NTEC. On June 18, 2018, Minnesota Power filed a separate petition for approval of the PPA for the output of a 10 MW solar energy facility located in central Minnesota. The MPUC has not taken any action regarding the wind energy PPA which will be refiled separately from the natural gas energy PPA.

Great Northern Transmission Line. Minnesota Power is constructing the GNTL, an approximately 220-mile 500-kV transmission line between Manitoba and Minnesota’s Iron Range that was proposed by Minnesota Power and Manitoba Hydro. In 2015, a certificate of need was approved by the MPUC. Based on this approval, Minnesota Power’s portion of the investments and expenditures for the project are eligible for cost recovery under its existing transmission cost recovery rider and are anticipated to be included in future transmission cost recovery filings. (See Transmission Cost Recovery Rider.) Also in 2015, the FERC approved our request to recover on construction work in progress related to the GNTL from Minnesota Power’s wholesale customers. In a 2016 order, the MPUC approved the route permit for the GNTL which largely follows Minnesota Power’s preferred route, including the international border crossing, and in 2016, the U.S. Department of Energy issued a presidential permit to cross the U.S.-Canadian border, which was the final major regulatory approval needed before construction in the U.S. could begin. Site clearing and pre‑construction activities commenced in the first quarter of 2017 with construction expected to be completed in 2020. To date, most of the right-of-way has been cleared while foundation installation and transmission tower construction have commenced. The total project cost in the U.S., including substation work, is estimated to be between $560 million and $710 million, of which Minnesota Power’s portion is expected to be between $300 million and $350 million; the difference will be recovered from a subsidiary of Manitoba Hydro as non-shareholder contributions to capital. Total project costs of $248.8 million have been incurred through June 30, 2018, of which $129.2 million has been recovered from a subsidiary of Manitoba Hydro.

Manitoba Hydro must obtain regulatory and governmental approvals related to a new transmission line in Canada known as the Manitoba-Minnesota Transmission Project (MMTP) that will connect with the GNTL. In 2015, Manitoba Hydro submitted the final preferred route and EIS for the MMTP to the Manitoba Conservation and Water Stewardship for siting and environmental approval, which remains pending. In 2016, Manitoba Hydro filed an application with the Canadian National Energy Board (NEB) requesting authorization to construct and operate the MMTP. The NEB determined that Manitoba Hydro’s application was complete in December 2017, and held public hearings in June 2018. The NEB is required to make a decision on the MMTP by March 2019, but is not precluded from making a decision prior to that date. Approval of the Canadian federal cabinet is also required.

The MMTP is subject to legal and regulatory challenges which Minnesota Power is actively monitoring. Manitoba Hydro has informed Minnesota Power that it continues to work towards completing the MMTP on schedule. In order to meet the transmission in‑service requirements in PPAs with Minnesota Power, Manitoba Hydro has indicated that it would need to start construction of the MMTP in December 2018. We are unable to predict the outcome of the Canadian regulatory review process, including the timing thereof or whether any onerous conditions may be imposed, or the timing of the completion of the MMTP, including the impact of any delays that may result in construction schedule adjustments. Any significant delays in the MMTP construction schedule may result in Minnesota Power adjusting the GNTL construction schedule and impact the timing of capital expenditures and associated cost recovery under our transmission cost recovery rider.
 
Construction of Manitoba Hydro’s Keeyask hydroelectric generation facility, which will provide the power to be sold under PPAs with Minnesota Power and transmitted on the MMTP and the GNTL, commenced in 2014 and is anticipated to be in service by early 2021.
NOTE 6. REGULATORY MATTERS (Continued)

Conservation Improvement Program. Minnesota requires electric utilities to spend a minimum of 1.5 percent of gross operating revenues, excluding revenue received from exempt customers, from service provided in the state on energy CIPs each year. On April 2, 2018, Minnesota Power submitted its 2017 CIP consolidated filing, which detailed Minnesota Power’s CIP program results and requested a CIP financial incentive of $3.3 million based upon MPUC procedures. In 2017, the CIP financial incentive of $5.5 million was recognized in the second quarter upon approval by the MPUC of Minnesota Power’s 2016 CIP consolidated filing in a June 2017 order. Approval of Minnesota Power’s 2017 CIP consolidated filing and related financial incentive is expected in the third quarter of 2018. CIP financial incentives are recognized in the period in which the MPUC approves the filing.

MISO Return on Equity Complaints. MISO transmission owners, including ALLETE and ATC, have an authorized return on equity of 10.32 percent, or 10.82 percent including an incentive adder for participation in a regional transmission organization.

In 2016, a federal administrative law judge ruled on a complaint proposing a reduction in the base return on equity to 9.70 percent, or 10.20 percent including an incentive adder for participation in a regional transmission organization, subject to approval or adjustment by the FERC. A final decision from the FERC on the administrative law judge’s recommendation is pending, which is not expected to have a material impact on our Consolidated Financial Statements.

Minnesota Solar Energy Standard. Minnesota law requires at least 1.5 percent of total retail electric sales, excluding sales to certain customers, to be generated by solar energy by the end of 2020. At least 10 percent of the 1.5 percent mandate must be met by solar energy generated by or procured from solar photovoltaic devices with a nameplate capacity of 40 kW or less and community solar garden subscriptions. In a 2016 order, the MPUC approved Camp Ripley, a 10 MW utility scale solar project at the Camp Ripley Minnesota Army National Guard base and training facility near Little Falls, Minnesota, as eligible to meet the solar energy standard and for current cost recovery. Camp Ripley was completed in the fourth quarter of 2016. In a 2016 order, the MPUC approved a community solar garden project in northeastern Minnesota, which is comprised of a 1 MW solar array owned and operated by a third party with the output purchased by Minnesota Power and a 40 kW solar array that is owned and operated by Minnesota Power. Minnesota Power believes Camp Ripley and the community solar garden arrays will meet approximately one‑third of the overall mandate. Additionally, in a February 2017 order, the MPUC approved Minnesota Power’s proposal to increase the amount of solar rebates available for customer-sited solar installations and recover costs of the program through Minnesota Power’s renewable cost recovery rider. The proposal to incentivize customer‑sited solar installations and community solar garden subscriptions is expected to meet a portion of the required small scale solar mandate.

Regulatory Assets and Liabilities. Our regulated utility operations are subject to accounting guidance for the effect of certain types of regulation. Regulatory assets represent incurred costs that have been deferred as they are probable for recovery in customer rates. Regulatory liabilities represent obligations to make refunds to customers and amounts collected in rates for which the related costs have not yet been incurred. The Company assesses quarterly whether regulatory assets and liabilities meet the criteria for probability of future recovery or deferral. No regulatory assets or liabilities are currently earning a return. The recovery, refund or credit to rates for these regulatory assets and liabilities will occur over the periods either specified by the applicable regulatory authority or over the corresponding period related to the asset or liability.
NOTE 6. REGULATORY MATTERS (Continued)
Regulatory Assets and Liabilities
June 30,
2018

 
December 31,
2017

Millions
 
 
 
Non-Current Regulatory Assets
 
 
 
Defined Benefit Pension and Other Postretirement Benefit Plans

$216.7

 

$220.3

Income Taxes
109.3

 
112.8

Asset Retirement Obligations
31.0

 
29.6

Manufactured Gas Plant 
8.0

 
8.1

PPACA Income Tax Deferral
5.0

 
5.0

Conservation Improvement Program

 
3.3

Other
4.5

 
5.6

Total Non-Current Regulatory Assets

$374.5

 

$384.7

 
 
 
 
Current Regulatory Liabilities (a)
 
 
 
Provision for Interim Rate Refund (b)

$32.5

 

Provision for Tax Reform Refund (c)
6.7

 

Total Current Regulatory Liabilities
39.2

 

Non-Current Regulatory Liabilities
 
 
 
Income Taxes
401.4

 

$411.2

Wholesale and Retail Contra AFUDC
60.2

 
57.9

Plant Removal Obligations
23.0

 
20.3

Cost Recovery Riders 
16.8

 
2.2

North Dakota Investment Tax Credits
14.4

 
14.1

Provision for Interim Rate Refund (b)

 
23.7

Other
0.2

 
2.6

Total Non-Current Regulatory Liabilities
516.0

 
532.0

Total Regulatory Liabilities

$555.2

 

$532.0


(a)
Current regulatory liabilities are presented within Other Current Liabilities on the Consolidated Balance Sheet.
(b)
This amount is expected to be refunded to Minnesota Power’s regulated retail customers in the first quarter of 2019 and includes $16.7 million of discounts provided to EITE customers that will be offset against interim rate refunds as of June 30, 2018 ($8.6 million as of December 31, 2017). (See 2016 Minnesota General Rate Case and Energy-Intensive Trade‑Exposed Customer Rates.)
(c)
We have recorded the impact of income tax changes for Minnesota Power and SWL&P resulting from the TCJA in 2018 as regulatory liabilities and a reduction in revenue as the benefits are deferred pending the outcome of regulatory proceedings with the MPUC and PSCW. (See Tax Cuts and Jobs Act of 2017.)