XML 33 R13.htm IDEA: XBRL DOCUMENT v3.3.1.900
Regulatory Matters
12 Months Ended
Dec. 31, 2015
Regulated Operations [Abstract]  
Regulatory Matters [Text Block]
REGULATORY MATTERS

Electric Rates. Entities within our Regulated Operations segment file for periodic rate revisions with the MPUC, the FERC or the PSCW.

2010 Minnesota Rate Case. Minnesota Power’s current retail rates are based on a 2011 MPUC retail rate order, effective June 1, 2011, that allows for a 10.38 percent return on common equity and a 54.29 percent equity ratio. Subsequent to this last order, and as authorized by the MPUC, Minnesota Power has increased revenue under cost recovery riders for environmental, renewable and transmission investments. (See Transmission Cost Recovery Rider, Renewable Cost Recovery Rider and Boswell Mercury Emissions Reduction Plan.) Revenue from cost recovery riders was $86.0 million in 2015 ($69.9 million in 2014 and $40.5 million in 2013).

Energy-Intensive Trade-Exposed (EITE) Customer Rates. The Minnesota Legislature enacted EITE customer ratemaking legislation in June 2015. The legislation establishes that it is the energy policy of the state to have competitive rates for certain industries such as mining and forest products. On November 13, 2015, Minnesota Power filed a rate schedule for EITE customers and a corresponding rider for EITE cost recovery with the MPUC. The rate proposal is revenue, and cash flow, neutral. On February 11, 2016, the MPUC dismissed the petition without prejudice, offering Minnesota Power the option to refile the petition with additional information or initiate a new petition. Minnesota Power is evaluating the MPUC’s decision.

FERC-Approved Wholesale Rates. Minnesota Power has 16 non-affiliated municipal customers in Minnesota. SWL&P is a Wisconsin utility and a wholesale customer of Minnesota Power.

On April 21, 2015, Minnesota Power amended its formula-based wholesale electric sales contract with the Nashwauk Public Utilities Commission, extending the term through June 30, 2028. The electric service agreements with SWL&P and one other municipal customer are effective through June 30, 2019. The rates included in these contracts are set each July 1 based on a cost-based formula methodology, using estimated costs and a rate of return that is equal to Minnesota Power’s authorized rate of return for Minnesota retail customers (currently 10.38 percent). The formula-based rate methodology also provides for a yearly true-up calculation for actual costs incurred.

In September 2015, Minnesota Power amended its wholesale electric contracts with 14 municipal customers, extending the contract terms through December 31, 2024. These contracts include fixed capacity charges through 2018; beginning in 2019, the capacity charge will not increase by more than two percent or decrease by more than one percent from the previous year’s capacity charge and will be determined using a cost-based formula methodology. The base energy charge for each year of the contract term will be set each January 1, subject to monthly adjustment, and is also determined using a cost-based formula methodology.

NOTE 5. REGULATORY MATTERS (Continued)

All of the wholesale contracts include a termination clause requiring a three-year notice to terminate. In January 2016, one of Minnesota Power’s municipal customers provided notice of its intent to terminate its contract effective June 30, 2019. Minnesota Power currently provides approximately 29 MW of average monthly demand to this customer. Under the Nashwauk Public Utilities Commission agreement, no termination notice may be given prior to June 30, 2025. Under the agreement with SWL&P, no termination notice may be given prior to June 30, 2016. The remaining 14 municipal customers may not give termination notices prior to December 31, 2021.

2012 Wisconsin Rate Case. SWL&P’s current retail rates are based on a 2012 PSCW retail rate order, effective January 1, 2013, that allows for a 10.9 percent return on common equity.

Transmission Cost Recovery Rider. Minnesota Power has an approved cost recovery rider in place for certain transmission investments and expenditures. In an order dated February 3, 2016, the MPUC approved Minnesota Power’s updated billing factor which allows Minnesota Power to charge retail customers on a current basis for the costs of constructing certain transmission facilities plus a return on the capital invested. As a result of the MPUC approval of the certificate of need for the GNTL on June 30, 2015, the project is eligible for cost recovery under the existing transmission cost recovery rider. Minnesota Power anticipates including its portion of the investments and expenditures for the GNTL in future transmission factor filings to include updated billing rates on customer bills.

Renewable Cost Recovery Rider. Minnesota Power has an approved cost recovery rider in place for investments and expenditures related to the 497 MW Bison Wind Energy Center in North Dakota. Customer billing rates for the Bison Wind Energy Center were approved by the MPUC in an order dated May 22, 2015. In November 2014, Minnesota Power filed a renewable resources factor filing which includes updated costs associated with Bison. Upon approval of the filing, Minnesota Power will be authorized to include updated billing rates on customer bills.

On February 13, 2015, Minnesota Power supplemented its November 2014 renewable resources factor filing to include costs associated with the restoration and repair of Thomson. In an order dated March 5, 2015, the MPUC approved Minnesota Power’s petition seeking cost recovery for investments and expenditures related to the restoration and repair of Thomson through a renewable resources rider.

Annual Automatic Adjustment (AAA) of Charges. Minnesota Power’s AAA filings made in 2012, 2013, 2014 and 2015 are pending MPUC approval, and represent approximately $700 million in retail fuel cost recovery collected but subject to refund. These filings have historically been approved, and Minnesota Power currently expects full recovery of amounts represented by each AAA filing, although we cannot predict the outcome of the filings at the MPUC.

Integrated Resource Plan (IRP). In a November 2013 order, the MPUC approved Minnesota Power’s 2013 IRP which detailed its EnergyForward strategic plan, announced in January 2013. Significant elements of the EnergyForward plan include major wind investments in North Dakota which were completed in the fourth quarter of 2014, the installation of emissions control technology at Boswell Unit 4 completed in December 2015, planning for the proposed GNTL, the conversion of Laskin from coal to natural gas completed in June 2015 and the retirement of Taconite Harbor Unit 3 completed in May 2015. On September 1, 2015, Minnesota Power filed its 2015 IRP with the MPUC which includes an analysis of a variety of existing and future energy resource alternatives and a projection of customer cost impact by class. The 2015 IRP also contains the next steps in Minnesota Power’s EnergyForward plan including the economic idling of Taconite Harbor Units 1 and 2 in the fall of 2016, the ceasing of coal-fired operations at Taconite Harbor in 2020, and the addition of between 200 MW and 300 MW of natural gas-fired generation in the next decade.

Boswell Mercury Emissions Reduction Plan. In August 2012, Minnesota Power filed its mercury emissions reduction plan for Boswell Unit 4 with the MPUC and the MPCA in order to comply with the Minnesota Mercury Emissions Reduction Act and the Federal MATS rule. Construction on the project to implement the Boswell Unit 4 mercury emissions reduction plan was completed with project costs totaling approximately $220 million through December 31, 2015. In a November 2013 order, the MPUC approved the Boswell Unit 4 mercury emissions reduction plan and cost recovery, establishing an environmental improvement rider. Customer billing rates for the environmental improvement rider were approved by the MPUC in an order dated August 24, 2015. On September 30, 2015, Minnesota Power filed an updated environmental improvement factor filing which included updated costs associated with Boswell Unit 4. Upon approval of the filing, Minnesota Power will be authorized to include updated billing rates on customer bills.

NOTE 5. REGULATORY MATTERS (Continued)

Boswell Remaining Life Petition. On November 17, 2015, Minnesota Power filed a petition with the MPUC for approval to extend Boswell’s remaining life to 2050 for all units and utilize the existing environmental improvement rider to credit a portion of the depreciation expense savings to customers. The extension request is based on the significant multi-emissions retrofit work done at Boswell Unit 3 and Boswell Unit 4.

Great Northern Transmission Line (GNTL). Minnesota Power and Manitoba Hydro have proposed construction of the GNTL, an approximately 220-mile 500 kV transmission line, between Manitoba and Minnesota’s Iron Range. The GNTL is subject to various federal and state regulatory approvals. In October 2013, a certificate of need application was filed with the MPUC which was approved in an order dated June 30, 2015. Based on this order, Minnesota Power’s portion of the investments and expenditures for the project are eligible for cost recovery under its existing transmission cost recovery rider and are anticipated to be included in future transmission factor filings. In an order dated December 17, 2015, the FERC approved our request to recover on construction work in progress related to the GNTL from Minnesota Power’s wholesale customers. In April 2014, Minnesota Power filed a route permit application with the MPUC and a request for a presidential permit to cross the U.S.-Canadian border with the U.S. Department of Energy. In a July 2014 order, the MPUC determined the route permit application to be complete. On October 30, 2015, the Minnesota Department of Commerce and the U.S. Department of Energy released the final EIS for the GNTL. On January 4, 2016, an administrative law judge recommended approval of the route permit for the GNTL. A final decision on the route permit by the MPUC is expected in the first quarter of 2016. Manitoba Hydro must also obtain regulatory and governmental approvals related to a new transmission line in Canada. In September 2015, Manitoba Hydro submitted the final preferred route and EIS for the transmission line in Canada to the Manitoba Conservation and Water Stewardship for regulatory approval. Construction of Manitoba Hydro’s hydroelectric generation facility commenced in 2014. Upon receipt of all applicable permits and approvals, construction of the GNTL is expected to begin by 2017 and to be completed in 2020.

Conservation Improvement Program (CIP). Minnesota requires electric utilities to spend a minimum of 1.5 percent of net gross operating revenues from service provided in the state on energy CIPs each year. These investments are recovered from certain retail customers through a combination of the conservation cost recovery charge included in retail base rates and a conservation program adjustment, which is adjusted annually through the CIP consolidated filing. The MPUC allows utilities to accumulate, in a deferred account for future cost recovery, all CIP expenditures, any financial incentive earned for cost-effective program achievements, and a carrying charge on the deferred account balance. Minnesota Power refers to its conservation programs collectively as the “Power of One”. In June 2013, Minnesota Power submitted a triennial filing for 2014 through 2016, which was subsequently approved by the Minnesota Department of Commerce. Minnesota Power’s CIP investment goal was $7.1 million for 2015 ($6.9 million for 2014; $6.0 million for 2013), with actual spending of $6.6 million in 2015 ($7.2 million in 2014; $6.4 million in 2013).

Minnesota requires each utility to establish an annual energy-savings goal of 1.5 percent of annual retail energy sales. On April 1, 2015, Minnesota Power submitted its 2014 CIP filing that requested a CIP financial incentive of $6.2 million. The requested CIP financial incentive was approved by the MPUC in an order dated September 16, 2015, and was recorded as revenue and as a regulatory asset. The approved financial incentive will be recovered through customer billing rates in 2015 and 2016. In 2014 and 2013, the CIP financial incentive recognized was $8.7 million and $7.1 million, respectively. CIP financial incentives are recognized in the period in which the MPUC approves the filing. he MPUC implemented certain limitations on amounts recoverable for the utility performance incentive program for recovery years beginning in 2015.

MISO Return on Equity Complaints. In November 2013, several customer groups located within the MISO service area filed complaints with the FERC requesting, among other things, a reduction in the base return on equity used by MISO transmission owners, including ALLETE, to 9.15 percent. On February 12, 2015, an additional complaint was filed with the FERC seeking an order to further reduce the base return on equity to 8.67 percent. On December 29, 2015, a federal administrative law judge ruled that the MISO transmission users have been charged an unreasonable base return on equity and proposed a reduction to 10.32 percent, subject to approval or adjustment by the FERC. A final decision from the FERC on the administrative law judge’s recommendation is expected in 2016. As a result of these complaints filed with the FERC and the administrative law judge’s recommendation, Minnesota Power has recorded an estimated refund obligation for MISO revenue of $7.2 million and an estimated refund for MISO transmission expense of $4.5 million, resulting in a reserve of $2.7 million as of December 31, 2015; $1.5 million was attributable to prior years.

NOTE 5. REGULATORY MATTERS (Continued)

Minnesota Solar Energy Standard. In May 2013, legislation was enacted by the state of Minnesota requiring at least 1.5 percent of total retail electric sales, excluding sales to certain industrial customers, to be generated by solar energy by the end of 2020. At least 10 percent of the 1.5 percent mandate must be met by solar energy generated by or procured from solar photovoltaic devices with a nameplate capacity of 20 kilowatts or less. Minnesota Power has two solar projects under development. On August 21, 2015, Minnesota Power filed for MPUC approval of a 10 MW utility scale solar project at Camp Ripley, a Minnesota Army National Guard base and training facility near Little Falls, Minnesota. At a hearing on January 28, 2016, the MPUC approved the Camp Ripley solar project as eligible to meet the solar energy standard and for current cost recovery, subject to certain compliance requirements. On September 10, 2015, Minnesota Power filed for MPUC approval of a 1 MW community solar garden project in Saint Louis County, Minnesota. If the community solar garden project is also approved, Minnesota Power believes these projects will meet approximately one-third of the overall mandate and approximately one-fourth of the mandate related to solar photovoltaic devices with a nameplate capacity of 20 kilowatts or less. Costs associated with these projects are expected to be recovered from customers.

Regulatory Assets and Liabilities. Our regulated utility operations are subject to accounting guidance for the effect of certain types of regulation. Regulatory assets represent incurred costs that have been deferred as they are probable for recovery in customer rates. Regulatory liabilities represent obligations to make refunds to customers and amounts collected in rates for which the related costs have not yet been incurred. The Company assesses quarterly whether regulatory assets and liabilities meet the criteria for probability of future recovery or deferral. No regulatory assets or liabilities are currently earning a return. The recovery, refund or credit to rates for these regulatory assets and liabilities will occur over the periods either specified by the applicable regulatory authority or over the corresponding period related to the asset or liability.
NOTE 5. REGULATORY MATTERS (Continued)
Regulatory Assets and Liabilities
 
 
As of December 31
2015

2014

Millions
 
 
Current Regulatory Assets (a)
 
 
Deferred Fuel Adjustment Clause

$10.6


$16.3

   Total Current Regulatory Assets
10.6

16.3

Non-Current Regulatory Assets
 
 
Defined Benefit Pension and Other Postretirement Benefit Plans (b)
219.3

223.9

Income Taxes (c)
64.2

46.6

Cost Recovery Riders (d)
58.0

59.7

Asset Retirement Obligations (e)
21.6

17.8

PPACA Income Tax Deferral
5.0

5.0

Other
3.9

4.3

Total Non-Current Regulatory Assets
372.0

357.3

Total Regulatory Assets

$382.6


$373.6

 
 
 
Non-Current Regulatory Liabilities
 
 
Wholesale and Retail Contra AFUDC (f)

$58.0


$42.9

Plant Removal Obligations
22.1

22.8

Income Taxes (c)
6.1

13.4

Defined Benefit Pension and Other Postretirement Benefit Plans (b)
0.9

3.5

Other
17.9

11.6

Total Non-Current Regulatory Liabilities

$105.0


$94.2

(a)
Current regulatory assets are included in Prepayments and Other on the Consolidated Balance Sheet.
(b)
Defined benefit pension and other postretirement items included in our Regulated Operations, which are otherwise required to be recognized in accumulated other comprehensive income as actuarial gains and losses as well as prior service costs and credits, are recognized as regulatory assets or regulatory liabilities on the Consolidated Balance Sheet. The asset or liability will decrease as the deferred items are amortized and recognized as components of net periodic benefit cost. (See Note 17. Pension and Other Postretirement Benefit Plans.)
(c)
These costs represent the difference between deferred income taxes recognized for financial reporting purposes and amounts previously billed to our customers. This balance will decrease over the remaining life of the related temporary differences and flow through current income taxes.
(d)
The cost recovery rider regulatory assets are revenues not yet collected from our customers primarily due to capital expenditures related to the Bison Wind Energy Center, investment in CapX2020 projects, and the Boswell Unit 4 environmental upgrade and are recognized in accordance with the accounting standards for alternative revenue programs. The cost recovery rider regulatory assets as of December 31, 2015 will be recovered over the next two years.
(e)
Asset retirement obligations will accrete and be amortized over the lives of the related property with asset retirement obligations.
(f)
Wholesale and Retail Contra AFUDC represents amortization to offset AFUDC Equity and Debt recorded during the construction period of our cost recovery rider projects prior to placing the projects in service. The regulatory liability will decrease over the remaining depreciable life of the related asset.