Commitments, Guarantees and Contingencies - Transmission (Details) (USD $)
In Millions, unless otherwise specified
Dec. 31, 2013
Dec. 31, 2012
CapX2020 [Member]
   
Transmission [Line Items]    
Number of Projects 3  
Capital Cost Spent to Date $ 80.5 $ 48.2
CapX2020 [Member] | Minimum [Member]
   
Transmission [Line Items]    
Estimated Capital Expenditures 100  
CapX2020 [Member] | Maximum [Member]
   
Transmission [Line Items]    
Estimated Capital Expenditures 110  
CapX2020 Fargo to Monticello Project [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 238  
Transmission Line Capacity (kV) 345  
Capital Cost Spent to Date 69.6 37.3
CapX2020 Monticello to St. Cloud Project [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 28  
Transmission Line Capacity (kV) 345  
CapX2020 Bemidji to Grand Rapids Project [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 70  
Transmission Line Capacity (kV) 230  
Capital Cost Spent to Date 10.9 10.9
Great Northern Transmission Line [Member]
   
Transmission [Line Items]    
Transmission Line Length (Miles) 240  
Transmission Line Capacity (kV) 500  
Estimated Capital Expenditures $ 300  
Great Northern Transmission Line [Member] | Minnesota Power [Member]
   
Transmission [Line Items]    
Portion of Capital Expenditures GNTL 51.00%