XML 85 R17.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments, Guarantees and Contingencies
12 Months Ended
Dec. 31, 2011
Commitments, Guarantees and Contingencies [Abstract]  
Commitments, Guarantees and Contingencies
Commitments, Guarantees and Contingencies
Power Purchase Agreements. Our long-term PPAs have been evaluated under the accounting guidance for variable interest entities. We have determined that either we have no variable interest in the PPA, or where we do have variable interests, we are not the primary beneficiary; therefore, consolidation is not required. These conclusions are based on the fact that we do not have both control over activities that are most significant to the entity and an obligation to absorb losses or receive benefits from the entity’s performance. Our financial exposure relating to these PPAs is limited to our fixed capacity and energy payments.

Note 11.
Commitments, Guarantees and Contingencies (Continued)
Power Purchase Agreements (Continued)

Square Butte PPA. Minnesota Power has a PPA with Square Butte that extends through 2026 (Agreement). It provides a long-term supply of energy to customers in our electric service territory and enables Minnesota Power to meet reserve requirements. Square Butte, a North Dakota cooperative corporation, owns a 455 MW coal-fired generating unit (Unit) near Center, North Dakota. The Unit is adjacent to a generating unit owned by Minnkota Power, a North Dakota cooperative corporation whose Class A members are also members of Square Butte. Minnkota Power serves as the operator of the Unit and also purchases power from Square Butte.

Minnesota Power is obligated to pay its pro rata share of Square Butte’s costs based on Minnesota Power’s entitlement to Unit output. Our output entitlement under the Agreement is 50 percent for the remainder of the contract, subject to the provisions of the Minnkota power sales agreement described below. Minnesota Power’s payment obligation will be suspended if Square Butte fails to deliver any power, whether produced or purchased, for a period of one year. Square Butte’s costs consist primarily of debt service, operating and maintenance, depreciation and fuel expenses. As of December 31, 2011, Square Butte had total debt outstanding of $451.4 million. Annual debt service for Square Butte is expected to be approximately $44 million in each of the five years, 2012 through 2016, of which Minnesota Power's obligation is 50 percent. Fuel expenses are recoverable through our fuel adjustment clause and include the cost of coal purchased from BNI Coal, our subsidiary, under a long-term contract.

Minnesota Power’s cost of power purchased from Square Butte during 2011 was $61.2 million ($55.2 million in 2010; $53.9 million in 2009). This reflects Minnesota Power’s pro rata share of total Square Butte costs based on the 50 percent output entitlement. Included in this amount was Minnesota Power’s pro rata share of interest expense of $11.1 million in 2011 ($10.2 million in 2010; $11.0 million in 2009). Minnesota Power’s payments to Square Butte are approved as a purchased power expense for ratemaking purposes by both the MPUC and the FERC.

Minnkota Power Sales Agreement. In conjunction with the purchase of the existing 250 kV DC transmission line from Square Butte in December 2009, Minnesota Power entered into a power sales agreement with Minnkota Power. Under the power sales agreement, Minnesota Power will sell a portion of its output from Square Butte to Minnkota Power, resulting in Minnkota Power’s net entitlement increasing and Minnesota Power’s net entitlement decreasing until Minnesota Power’s share is eliminated at the end of 2025.

No power will be sold under this agreement until Minnkota Power has placed in service a new AC transmission line, which is anticipated to occur in 2013. This new AC transmission line will allow Minnkota Power to transmit its entitlement from Square Butte directly to its customers, which, in turn, will allow Minnesota Power the ability to transmit additional wind generation on the DC transmission line.

Wind PPAs. In 2006 and 2007, Minnesota Power entered into two long-term wind PPAs with an affiliate of NextEra Energy, Inc. to purchase the output from Oliver Wind I (50 MW) and Oliver Wind II (48 MW), wind facilities located near Center, North Dakota. Each agreement is for 25 years and provides for the purchase of all output from the facilities at fixed prices. There are no fixed capacity charges, and we only pay for energy as it is delivered to us.

Hydro PPAs. Minnesota Power has a PPA with Manitoba Hydro that expires in April 2015. Under this agreement, Minnesota Power is purchasing 50 MW of capacity and the energy associated with that capacity. Both the capacity price and the energy price are adjusted annually by the change in a governmental inflationary index.

Minnesota Power has a separate PPA with Manitoba Hydro to purchase surplus energy from May 2011 through April 2022. This energy-only transaction primarily consists of surplus hydro energy on Manitoba Hydro’s system that is delivered to Minnesota Power on a non-firm basis. The pricing is based on forward market prices. Under this agreement, Minnesota Power will purchase at least one million MWh of energy over the contract term. On March 31, 2011, the MPUC approved this PPA with Manitoba Hydro.

On May 19, 2011, Minnesota Power and Manitoba Hydro signed a long-term PPA. The PPA calls for Manitoba Hydro to sell 250 MW of capacity and energy to Minnesota Power for 15 years beginning in 2020 and requires construction of additional transmission capacity between Manitoba and the U.S. The capacity price is adjusted annually until 2020 by a change in a governmental inflationary index. The energy price is based on a formula that includes an annual fixed price component adjusted for a change in a governmental inflationary index and a natural gas index, as well as market prices. On January 26, 2012, the MPUC approved this PPA with Manitoba Hydro.
North Dakota Wind Development. Minnesota Power uses the 465-mile, 250 kV DC transmission line that runs from Center, North Dakota, to Duluth, Minnesota to transport increasing amounts of wind energy from North Dakota while gradually phasing out coal-based electricity delivered to our system over this transmission line from Square Butte’s lignite coal-fired generating unit.

Bison 1 is an 82 MW wind project in North Dakota. All permitting has been received, the first phase was completed in 2010, and the second phase was completed in January 2012. Phase one included construction of a 22-mile, 230 kV transmission line and the installation of sixteen 2.3 MW wind turbines. Phase two consisted of the installation of fifteen 3.0 MW wind turbines. Bison 1 is expected to have a total project cost of $177 million, of which $171.5 million was spent through December 31, 2011. In 2009, the MPUC approved Minnesota Power’s petition seeking current cost recovery for investments and expenditures related to Bison 1, and in July 2010, the MPUC approved our petition establishing rates effective August 1, 2010. On November 3, 2011, the MPUC issued an order approving our petition to update the rates for additional investments and expenditures related to Bison 1.

Bison 2 and Bison 3 are both 105 MW wind projects in North Dakota which are expected to be completed by the end of 2012. Site preparation is currently underway for both projects and the total project costs for Bison 2 and Bison 3 are estimated to be approximately $160 million each, of which $37.0 million and $14.7 million, respectively, was spent through December 31, 2011. On September 8, 2011, and November 2, 2011, the MPUC approved Minnesota Power's petition seeking current cost recovery for investments and expenditures related to Bison 2 and Bison 3, respectively. On August 10, 2011, and October 12, 2011, the NDPSC issued a Certificate of Site Compatibility for Bison 2 and Bison 3, respectively, which authorized site construction to commence. We anticipate filing petitions with the MPUC in the first half of 2012 to establish customer billing rates for the approved cost recovery.
Leasing Agreements. BNI Coal is obligated to make lease payments for a dragline totaling $2.8 million annually for the lease term which expires in 2027. BNI Coal has the option at the end of the lease term to renew the lease at fair market value, to purchase the dragline at fair market value, or to surrender the dragline and pay a $3 million termination fee. We lease other properties and equipment under operating lease agreements with terms expiring through 2016. The aggregate amount of minimum lease payments for all operating leases is $10.9 million in 2012, $11.1 million in 2013, $11.4 million in 2014, $11.2 million in 2015, $9.2 million in 2016 and $43.0 million thereafter. Total rent and lease expense was $9.4 million in 2011 ($9.4 million in 2010; $9.3 million in 2009).
Coal, Rail and Shipping Contracts. We have coal supply agreements providing for the purchase of a significant portion of our coal requirements which expire in 2012 and 2013. We also have coal transportation agreements in place for the delivery of a significant portion of our coal requirements with expiration dates through 2015. Our minimum annual payment obligation under these supply and transportation agreements for 2012 is $55.4 million, and 2013 is $27.0 million. Our minimum annual payment obligations will increase when annual nominations are made for coal deliveries in future years. The delivered costs of fuel for Minnesota Power’s generation are recoverable from Minnesota Power’s utility customers through the fuel adjustment clause.
Transmission. We are making investments in Upper Midwest transmission opportunities that strengthen or enhance the regional transmission grid. This includes the CapX2020 initiative, investments in our own transmission assets, investments in other regional transmission assets (by ourselves or in combination with others), and our investment in ATC.

Transmission Investments. We have an approved cost recovery rider in place for certain transmission expenditures and the continued use of our 2009 billing factor was approved by the MPUC in May 2011. The billing factor allows us to charge our retail customers on a current basis for the costs of constructing certain transmission facilities plus a return on the capital invested. On June 29, 2011, we filed an updated billing factor that includes additional transmission projects and expenses, which we expect to be approved in 2012.

CapX2020. Minnesota Power is a participant in the CapX2020 initiative which represents an effort to ensure electric transmission and distribution reliability in Minnesota and the surrounding region for the future. CapX2020, which consists of electric cooperatives, municipals and investor-owned utilities, including Minnesota’s largest transmission owners, has assessed the transmission system and projected growth in customer demand for electricity through 2020. Studies show that the region's transmission system will require major upgrades and expansion to accommodate increased electricity demand as well as support renewable energy expansion through 2020.

Note 11.        Commitments, Guarantees and Contingencies (Continued)
Transmission (Continued)

Minnesota Power is currently participating in three CapX2020 projects: the Fargo, North Dakota to St. Cloud, Minnesota project, the Monticello, Minnesota to St. Cloud, Minnesota project, which together total a 238-mile, 345 kV line from Fargo, North Dakota to Monticello, Minnesota, and the 70-mile, 230 kV line between Bemidji, Minnesota and Minnesota Power’s Boswell Energy Center near Grand Rapids, Minnesota. Based on projected costs of the three transmission lines and the percentage agreements among participating utilities, Minnesota Power plans to invest between $100 million and $125 million in the CapX2020 initiative through 2015, of which $27.8 million was spent through December 31, 2011. As future CapX2020 projects are identified, Minnesota Power may elect to participate on a project-by-project basis.

In July 2010, the MPUC granted a route permit for the 28-mile 345 kV line between Monticello and St. Cloud. The project was completed and placed into service in December 2011. On June 10, 2011, the MPUC approved the route permit for the Minnesota portion of the Fargo to St. Cloud project. The North Dakota permitting process is underway. The entire 238-mile, 345 kV line from St. Cloud to Fargo is expected to be in service by 2015.

In November 2010, the MPUC approved a route permit for the Bemidji to Grand Rapids, Minnesota line and construction for the 230 kV line project commenced in January 2011. The Leech Lake Band of Ojibwe (LLBO) subsequently requested the MPUC suspend or revoke the route permit and also served the CapX2020 owners with a complaint filed in Leech Lake Tribal Court asserting adjudicatory and regulatory authority over the project. The CapX2020 owners filed a request for declaratory judgment in the United States District Court for the District of Minnesota (District Court) that the project does not require LLBO consent to cross non-tribal land within the reservation. On June 22, 2011, the federal judge issued a preliminary injunction directing the LLBO to cease and desist its claims of tribal court jurisdiction or from taking other actions to interfere with regulatory review, approval or project construction. The LLBO abandoned its motion to dismiss the declaratory action because the District Court’s injunction order had already dismissed the basis for the motion, namely, that the District Court did not have jurisdiction to hear the CapX2020 owners’ action. The parties are now proceeding with discovery and the CapX2020 owners do not anticipate any actions by the District Court until after the completion of discovery closes on May 31, 2012. The MPUC has taken no action in the matter in light of ongoing litigation in federal and tribal courts. The CapX2020 utilities are vigorously defending against the LLBO actions.
Environmental Matters

Our businesses are subject to regulation of environmental matters by various federal, state and local authorities. Currently, a number of regulatory changes to the Clean Air Act, the Clean Water Act and various waste management requirements are under consideration by both Congress and the EPA. Minnesota Power's fossil fuel facilities will likely be subject to regulation under these proposals. Our intention is to reduce our exposure to these requirements by reshaping our generation portfolio over time to reduce our reliance on coal.

We consider our businesses to be in substantial compliance with currently applicable environmental regulations and believe all necessary permits to conduct such operations have been obtained. Due to future restrictive environmental requirements through legislation and/or rulemaking, we anticipate that potential expenditures for environmental matters will be material and will require significant capital investments.

We review environmental matters on a quarterly basis. Accruals for environmental matters are recorded when it is probable that a liability has been incurred and the amount of the liability can be reasonably estimated, based on current law and existing technologies. Accruals are adjusted as assessment and remediation efforts progress or as additional technical or legal information become available. Accruals for environmental liabilities are included in the consolidated balance sheet at undiscounted amounts and exclude claims for recoveries from insurance or other third parties. Costs related to environmental contamination treatment and cleanup are charged to expense unless recoverable in rates from customers.

Air. The electric utility industry is heavily regulated both at the federal and state level to address air emissions. Minnesota Power's generating facilities mainly burn low-sulfur western sub-bituminous coal. Square Butte, located in North Dakota, burns lignite coal. All of Minnesota Power's coal-fired generating facilities are equipped with pollution control equipment such as scrubbers, bag houses and low NOX technologies. At this time, under currently applicable environmental regulations, these facilities are substantially compliant with applicable emission requirements.

New Source Review (NSR). In August 2008, Minnesota Power received a Notice of Violation (NOV) from the EPA asserting violations of the NSR requirements of the Clean Air Act at Boswell Units 1, 2, 3 and 4 and Laskin Unit 2. The NOV asserts that seven projects undertaken at these coal-fired plants between the years 1981 and 2000 should have been reviewed under the NSR requirements and that the Boswell Unit 4 Title V permit was violated. In April 2011, Minnesota Power received a NOV alleging that two projects undertaken at Rapids Energy Center in 2004 and 2005 should have been reviewed under the NSR requirements and that the Rapids Energy Center's Title V permit was violated. Minnesota Power believes the projects specified in the NOVs were in full compliance with the Clean Air Act, NSR requirements and applicable permits. We are engaged in discussions with the EPA regarding resolution of these matters, but we are unable to predict the outcome of these discussions.

The resolution could result in civil penalties and the installation of control technology, some of which is already planned or completed for other regulatory requirements. Any costs of installing pollution control technology would likely be eligible for recovery in rates over time subject to MPUC and FERC approval in a rate proceeding.

Cross-State Air Pollution Rule (CSAPR). On July 6, 2011, the EPA issued the CSAPR, which went into effect on October 7, 2011. The final rule replaced the EPA's 2005 Clean Air Interstate Rule (CAIR). However, on December 30, 2011, the United States Court of Appeals for the District of Columbia Circuit issued a ruling staying implementation of the CSAPR, pending judicial review, and ordered that the CAIR remain in place while the CSAPR is stayed.

If the CSAPR is reinstated after judicial review, it will require states in the CSAPR region to significantly improve air quality by reducing power plant emissions that contribute to ozone and/or fine particle pollution in other states. These regulations do not directly require the installation of controls. Instead, they require facilities to have sufficient emission allowances to cover their emissions on an annual basis. These allowances would be allocated to facilities annually by the EPA and will also be able to be bought and sold.

The CAIR regulations similarly require certain states to improve air quality by reducing power plant emissions that contribute to ozone and/or fine particle pollution in other states. Minnesota participation in the CAIR was stayed by EPA administrative action while the EPA completed a review of air quality modeling issues in conjunction with the development of a final replacement rule. In its final determination, the EPA listed Minnesota as a CSAPR-affected state based on new 24-hour fine particulate NAAQS analysis. While the CAIR remains in effect, Minnesota participation in the CAIR will continue to be stayed. It is uncertain if the CSAPR-related emission restrictions will become effective for Minnesota utilities.

Since 2006, we have significantly reduced emissions at our Laskin, Taconite Harbor and Boswell generating units. Our analysis, based on our expected generation rates, indicates that these recent emission reductions would satisfy Minnesota Power's SO2 and NOX emission compliance obligations with respect to the EPA-allocated CSAPR allowances for 2012. We will continue to evaluate our compliance strategy under CSAPR and if any capital investments or allowance purchases are required, we would likely seek recovery of those costs. We are unable to predict any additional CSAPR compliance costs we might incur at this time if CSAPR is reinstated.

Minnesota Regional Haze. The federal regional haze rule requires states to submit state implementation plans (SIPs) to the EPA to address regional haze visibility impairment in 156 federally-protected parks and wilderness areas. Under the regional haze rule, certain large stationary sources, put in place between 1962 and 1977, with emissions contributing to visibility impairment, are required to install emission controls, known as Best Available Retrofit Technology (BART). We have two steam units, Boswell Unit 3 and Taconite Harbor Unit 3, which are subject to BART requirements.

Pursuant to the regional haze rule, Minnesota was required to develop its SIP by December 2007. As a mechanism for demonstrating progress towards meeting the long-term regional haze goal, in April 2007, the MPCA advanced a draft conceptual SIP which relied on the implementation of CAIR. However, a formal SIP was not filed at that time due to the United States Court of Appeals for the District of Columbia Circuit's remand of CAIR. Subsequently, the MPCA requested that companies with BART-eligible units complete and submit a BART emissions control retrofit study, which was completed for Taconite Harbor Unit 3 in November 2008. The retrofit work completed in 2009 at Boswell Unit 3 meets the BART requirements for that unit. In December 2009, the MPCA approved the Minnesota SIP for submittal to the EPA for its review and approval. The Minnesota SIP incorporates information from the BART emissions control retrofit studies that were completed as requested by the MPCA.

On December 30, 2011, the EPA published in the Federal Register a proposal to revise the regional haze rule. This proposal would approve the trading program in the CSAPR as an alternative to determining BART. If adopted, states in the CSAPR region could substitute participation in CSAPR for source-specific BART requirements for SO2 and NOX emissions from power plants. On January 2, 2012, the MPCA submitted to the EPA a supplemental Minnesota regional haze SIP stating that it wishes to rely on the CSAPR to satisfy BART requirements for SO2 and NOx for electric generating units.

On January 25, 2012, the EPA published in the Federal Register a proposal to approve the Minnesota SIP, including the supplemental Minnesota SIP. If the Minnesota SIP, the supplemental Minnesota SIP, and the EPA's regional haze rule revisions are finalized as currently proposed, and the CSAPR rule is reinstated, then Minnesota Power does not foresee a need to make significant additional expenditures at Taconite Harbor Unit 3 to comply with the regional haze rule.

If controls are ultimately required, Minnesota Power will have up to five years from the final promulgation deadline to bring Taconite Harbor Unit 3 into compliance with the regional haze rule requirements. It is uncertain what controls would ultimately be required at Taconite Harbor Unit 3 under this scenario, in connection with the regional haze rule.
 
Mercury and Air Toxics Standards (MATS) Rule (formerly known as the Electric Generating Unit Maximum Achievable Control Technology (MACT) Rule). Under Section 112 of the Clean Air Act, the EPA is required to set emission standards for hazardous air pollutants (HAPs) for certain source categories. The EPA released a proposed MATS rule on March 16, 2011, addressing such emissions from coal-fired utility units greater than 25 MW. The final rule was issued on December 21, 2011. There are currently 188 listed HAPs which the EPA is required to evaluate for establishment of MACT standards. In the final MATS rule, the EPA established categories of HAPs, including mercury, trace metals other than mercury, acid gases, dioxin/furans, and organics other than dioxin/furans. The EPA also established emission limits for the first three categories of HAPs, and work practice standards for the remaining categories. Affected sources would have to be in compliance with the rule three years after it is published in the Federal Register. States have the authority to grant sources a one-year extension. Compliance at our Boswell Unit 4 to address the final MATS rule is expected to result in capital expenditures between $300 million to $400 million over the next five years. Some additional controls for complying with the rule at our remaining coal-fired generating units may be required, the costs of which cannot be estimated at this time.

EPA National Emission Standards for Hazardous Air Pollutants for Major Sources: Industrial, Commercial and Institutional Boilers and Process Heaters. In March 2011, a final rule was published in the Federal Register for industrial boiler maximum achievable control technology (Industrial Boiler MACT). The rule was stayed by the EPA on May 16, 2011, to allow the EPA time to consider additional comments received. The EPA re-proposed the rule in December 2011. A final rule is expected in April 2012. On January 9, 2012, the United States District Court for the District of Columbia ruled that the EPA stay of the Industrial Boiler MACT was unlawful, effectively reinstating the March 2011 rule and associated compliance deadlines. Major sources are expected to have three years to achieve compliance with the final rule. It is not known yet whether the final rule from the December 2011 proposal, expected in April 2012, will establish new compliance deadlines. This rule may result in additional control measures being required at Rapids Energy Center and Hibbard. Costs for complying with the final rule cannot be estimated at this time.

Minnesota Mercury Emission Reduction Act. Under Minnesota law, a mercury emissions reduction plan for Boswell Unit 4 is required to be submitted by July 1, 2015, with implementation no later than December 31, 2018. The statute also calls for an evaluation of a mercury control alternative which provides for environmental and public health benefits without imposing excessive costs on the utility's customers. Until Minnesota Power files its mercury emission reduction plan for Boswell Unit 4, it must file an annual report updating the MPUC and other stakeholders on the status of emission reduction planning for Boswell Unit 4. The first update was filed with the MPUC on June 30, 2011.

Mercury emission limits have also been included in the recently finalized MATS rule. We anticipate that the emission reduction plan implemented to comply with the MATS rule will satisfy the mercury emission limits under Minnesota law. Costs for the Boswell Unit 4 emission reduction plan are included in the estimated capital expenditures required for compliance with the MATS rule discussed above.

Proposed and Finalized National Ambient Air Quality Standards (NAAQS). The EPA is required to review the NAAQS every five years. If the EPA determines that a state's air quality is not in compliance with a NAAQS, the state is required to adopt plans describing how it will reduce emissions to attain the NAAQS. These state plans often include more stringent air emission limitations on sources of air pollutants than the NAAQS. Four NAAQS have either recently been revised or are currently proposed for revision, as described below.

Ozone NAAQS. The EPA has proposed to more stringently control emissions that result in ground level ozone. In January 2010, the EPA proposed to revise the 2008 eight-hour ozone standard and to adopt a secondary standard for the protection of sensitive vegetation from ozone-related damage. The EPA was scheduled to decide upon the 2008 eight-hour ozone standard in July 2011, but has announced that it is deferring revision of this standard until 2013.

Particulate Matter NAAQS. The EPA finalized the NAAQS Particulate Matter standards in September 2006. Since then, the EPA established a more stringent 24-hour average fine particulate matter (PM2.5) standard and kept the annual average fine particulate matter standard and the 24-hour coarse particulate matter standard unchanged. The United States Court of Appeals for the District of Columbia Circuit has remanded the PM2.5 standard to the EPA, requiring consideration of lower annual average standard values. The EPA expects to propose the new PM2.5 standards in June 2012 with a goal to finalize the rule by June 2013. State attainment status determination will occur after the rule is finalized. It is not known when affected sources would have to take additional control measures if modeling demonstrates non-compliance at their property boundary. The EPA has indicated that ambient air quality monitoring for 2008 through 2010 will be used as a basis for states to characterize their attainment status.

SO2 and NO2 NAAQS. During 2010, the EPA finalized new one-hour NAAQS for SO2 and NO2. Monitoring data indicates that Minnesota will likely be in compliance with these new standards; however, the one-hour SO2 NAAQS also requires the EPA to evaluate modeling data to determine attainment. The MPCA intends to complete this initial modeling effort by the end of the first quarter of 2012, using facility data from sources that emit more than 100 tons per year of SO2. Minnesota Power provided such data for all of our steam generating facilities. It is unclear what the outcome of this evaluation will be.

These NAAQS modeling efforts could result in more stringent emission limits on our coal-fired generating facilities, and possibly additional control measures on some of our units. The MPCA has informed affected sources that compliance strategies required as a result of these modeling results must be agreed to with the MPCA by February 2013. One-hour SO2 NAAQS attainment is required by 2017.

We are unable to predict the compliance costs we might incur; however, the costs could be material. We would seek recovery of any additional costs through cost recovery riders or in a general rate case.

Climate Change. The scientific community generally accepts that emissions of GHGs are linked to global climate change. Climate change creates physical and financial risk. These physical risks could include, but are not limited to: increased or decreased precipitation and water levels in lakes and rivers; increased temperatures; and the intensity and frequency of extreme weather events. These all have the potential to affect the Company's business and operations. Minnesota Power is addressing climate change by taking the following steps that also ensure reliable and environmentally compliant generation resources to meet our customers' requirements:

Expand our renewable energy supply;
Improve the efficiency of our coal-based generation facilities, as well as other process efficiencies;
Provide energy conservation initiatives for our customers and engage in other demand side efforts; and
Support research of technologies to reduce carbon emissions from generation facilities and support carbon sequestration efforts.

EPA Regulation of GHG Emissions. In May 2010, the EPA issued the final Prevention of Significant Deterioration (PSD) and Title V Greenhouse Gas Tailoring Rule (Tailoring Rule). The Tailoring Rule establishes permitting thresholds required to address GHG emissions for new facilities, at existing facilities that undergo major modifications and at other facilities characterized as major sources under the Clean Air Act's Title V program.

For our existing facilities, the rule does not require amending our existing Title V Operating Permits to include GHG requirements. Implementation of the requirement to add GHG provisions to permits will be completed at the state level in Minnesota by the MPCA when the Title V permits are renewed. However, installation of new units or modification of existing units resulting in a significant increase in GHG emissions will require obtaining PSD permits and amending our operating permits to demonstrate that Best Available Control Technology (BACT) is being used at the facility to control GHG emissions. The EPA has defined significant emissions increase for existing sources as a GHG increase of 75,000 tons or more per year of total GHG on a CO2 equivalent basis.

In late 2010, the EPA issued guidance to permitting authorities and affected sources to facilitate incorporation of the Tailoring Rule permitting requirements into the Title V and PSD permitting programs. The guidance stated that the project-specific top-down BACT determination process used for other pollutants will also be used to determine BACT for GHG emissions. Through sector-specific white papers, the EPA also provided examples and technical summaries of GHG emission control technologies and techniques the EPA considers available or likely to be available to sources. It is possible these control technologies could be determined to be BACT on a project-by-project basis. In the near term, one option appears to be energy efficiency maximization.

Legal challenges to the EPA's regulation of GHG emissions, including the Tailoring Rule, have been filed by others and are awaiting judicial determination. Comments to the permitting guidance were also submitted by Minnesota Power and others and may be addressed by the EPA in the form of revised guidance documents.

We are unable to predict the compliance costs we might incur; however, the costs could be material. We would seek recovery of any additional costs through cost recovery riders or in a general rate case.

Water. The Clean Water Act requires NPDES permits be obtained from the EPA (or, when delegated, from individual state pollution control agencies) for any wastewater discharged into navigable waters. We have obtained all necessary NPDES permits, including NPDES storm water permits for applicable facilities, to conduct our operations. We are in substantial compliance with these permits.

Clean Water Act - Aquatic Organisms. On April 20, 2011, the EPA published in the Federal Register proposed regulations under Section 316(b) of the Clean Water Act that set standards applicable to cooling water intake structures for the protection of aquatic organisms. The proposed regulations would require existing large power plants and manufacturing facilities that withdraw greater than 25 percent of water from adjacent water bodies for cooling purposes and have a design intake flow of greater than 2 million gallons per day to limit the number of aquatic organisms that are killed when they are pinned against the facility's intake structure or that are drawn into the facility's cooling system. The Section 316(b) standards would be implemented through NPDES permits issued to the covered facilities. The Section 316(b) proposed rule comment period ended in August 2011. The EPA is obligated to finalize the rule by July 27, 2012. Minnesota Power is in the process of evaluating the potential impacts the proposed rule may have on its facilities. We are unable to predict the compliance cost we might incur; however, the costs could be material. We would seek recovery of any additional costs through cost recovery riders or in a general rate case.

EPA Steam Electric Power Generating Effluent Guidelines. In late 2009, the EPA announced that it will be reviewing and reissuing the federal effluent guidelines for steam electric stations. These are the underlying federal water discharge rules that apply to all steam electric stations. The EPA has indicated that the new rule promulgating these guidelines will be proposed in 2012 and finalized in 2014. As part of the review phase for this new rule, the EPA issued an Information Collection Request (ICR) in June 2010, to most thermal electric generating stations in the country, including all five of Minnesota Power's generating stations. The ICR was completed and submitted to the EPA in September 2010 for Boswell, Laskin, Taconite Harbor, Hibbard, and Rapids Energy Center. The ICR was designed to gather extensive information on the nature and extent of all water discharge and related wastewater handling at power plants. The information gathered through the ICR will form a basis for development of the eventual new rule, which could include more restrictive requirements on wastewater discharge, flue gas desulfurization, and wet ash handling operations. We are unable to predict the costs we might incur to comply with potential future water discharge regulations at this time.

Solid and Hazardous Waste. The Resource Conservation and Recovery Act of 1976 regulates the management and disposal of solid and hazardous wastes. We are required to notify the EPA of hazardous waste activity and, consequently, routinely submit the necessary reports to the EPA.

Coal Ash Management Facilities. Minnesota Power generates coal ash at all five of its coal-fired electric generating facilities. Two facilities store ash in onsite impoundments (ash ponds) with engineered liners and containment dikes. Another facility stores dry ash in a landfill with an engineered liner and leachate collection system. Two facilities generate a combined wood and coal ash that is either land applied as an approved beneficial use or trucked to state permitted landfills. In June 2010, the EPA proposed regulations for coal combustion residuals generated by the electric utility sector. The proposal sought comments on three general regulatory schemes for coal ash. Comments on the proposed rule were due in November 2010. It is estimated that the final rule will be published in late 2012 or early 2013. We are unable to predict the compliance cost we might incur; however, the costs could be material. We would seek recovery of any additional costs through cost recovery riders or in a general rate case.

Manufactured Gas Plant Site. We are reviewing and addressing environmental conditions at a former manufactured gas plant site in the City of Superior, Wisconsin, and formerly operated by SWL&P. We have been working with the WDNR to determine the extent of contamination and the remediation of contaminated locations. As of December 31, 2011, we have a $0.5 million liability for this site and a corresponding regulatory asset as we expect recovery of remediation costs to be allowed by the PSCW.
Other Matters

BNI Coal. As of December 31, 2011, BNI Coal had surety bonds outstanding of $29.8 million related to the reclamation liability for closing costs associated with its mine and mine facilities. Although the coal supply agreements obligate the customers to provide for the closing costs, additional assurance is required by federal and state regulations. In addition to the surety bonds, BNI Coal has secured a letter of credit with CoBANK ACB for an additional $2.6 million to provide for BNI Coal’s total reclamation liability currently estimated at $32.4 million. BNI Coal does not believe it is likely that any of these outstanding surety bonds will be drawn upon.

ALLETE Properties. As of December 31, 2011, ALLETE Properties, through its subsidiaries, had surety bonds outstanding of $10.2 million primarily related to performance and maintenance obligations to governmental entities to construct improvements in the Company's various projects. The remaining work to be completed on these improvements is estimated to be approximately $8.0 million and ALLETE Properties does not believe it is likely that any of these outstanding surety bonds will be drawn upon.

Community Development District Obligations. In March 2005, the Town Center District issued $26.4 million of tax-exempt, 6 percent capital improvement revenue bonds and in May 2006, the Palm Coast Park District issued $31.8 million of tax-exempt, 5.7 percent special assessment bonds. The capital improvement revenue bonds and the special assessment bonds are payable over 31 years (by May 1, 2036, and 2037, respectively) and secured by special assessments on the benefited land. The bond proceeds were used to pay for the construction of a portion of the major infrastructure improvements in each district and to mitigate traffic and environmental impacts. The assessments were billed to the landowners beginning in November 2006, for Town Center, and November 2007, for Palm Coast Park. To the extent that we still own land at the time of the assessment, we will incur the cost of our portion of these assessments, based upon our ownership of benefited property. At December 31, 2011, we owned 73 percent of the assessable land in the Town Center District (69 percent at December 31, 2010) and 93 percent of the assessable land in the Palm Coast Park District (93 percent at December 31, 2010). At these ownership levels, our annual assessments are $1.5 million for Town Center and $2.2 million for Palm Coast Park. As we sell property, the obligation to pay special assessments will pass to the new landowners. Under current accounting rules, these bonds are not reflected as debt on our consolidated balance sheet.

Legal Proceedings. In January 2011, the Company was named as a defendant in a lawsuit in the Sixth Judicial District for the State of Minnesota by one of our customer’s (United Taconite, LLC) property and business interruption insurers. In October 2006, United Taconite experienced a fire as a result of the failure of certain electrical protective equipment. The equipment at issue in the incident was not owned, designed, or installed by Minnesota Power, but Minnesota Power had provided testing and calibration services related to the equipment. The lawsuit alleges approximately $20 million in damages related to the fire. The Company believes that it has strong defenses to the lawsuit and intends to vigorously assert such defenses. An accrual related to any damages that may result from the lawsuit has not been recorded as of December 31, 2011, because a potential loss is not currently probable; however, the Company believes it has adequate insurance coverage for potential loss.

Other. We are involved in litigation arising in the normal course of business. Also in the normal course of business, we are involved in tax, regulatory and other governmental audits, inspections, investigations and other proceedings that involve state and federal taxes, safety, compliance with regulations, rate base and cost of service issues, among other things. While the resolution of such matters could have a material effect on earnings and cash flows in the year of resolution, none of these matters are expected to materially change our present liquidity position, or have a material adverse effect on our financial condition.