Note 3 – Capitalization

 

Common Stock - During the three months ended March 31, 2019 and 2018, there were 47,649 common shares ($2.6 million) and 7,665 common shares (approximately $0.3 million), respectively, issued under the Middlesex Water Company Investment Plan (the Investment Plan). On January 2, 2019, the Company began offering shares of its common stock for purchase at a 5% discount to participants in the Investment Plan. The discount offering will continue until 200,000 shares are purchased at the discounted price or December 30, 2019, whichever event occurs first.  The discount applies to all common stock purchases made under the Investment Plan, whether by optional cash payment or by dividend reinvestment.

 

In March 2019, Middlesex filed a petition with the NJBPU seeking approval to issue and sell up to 1,500,000 shares of its common stock in one or more transactions through December 31, 2022. The sale of these additional shares of common stock is part of the Company’s comprehensive financing plan to fund its multi-year utility plant infrastructure investment program. As described below in “Long-term Debt”, the NJBPU approved the New Jersey Economic Development Authority (NJEDA) debt funding component of the financing plan. We believe the NJBPU will approve the common stock offering request, as filed, during the second quarter of 2019.

 

Long-term Debt - Subject to regulatory approval, the Company periodically issues long-term debt to fund its investments in utility plant and other assets. To the extent possible, the Company finances qualifying capital projects under State Revolving Fund (SRF) loan programs in New Jersey and Delaware. These government programs provide financing at interest rates that are typically below rates available in the broader financial markets. A portion of the borrowings under the New Jersey SRF is interest-free. Under the New Jersey SRF program, borrowers first enter into a construction loan agreement with the New Jersey Infrastructure Bank (NJIB) at a below market interest rate. The current interest rate on construction loan borrowings is zero percent (0%). When construction on the qualifying project is substantially complete, NJIB will coordinate the conversion of the construction loan into a long-term securitized loan with a portion of the principal balance having a stated interest rate of zero percent (0%) and a portion of the principal balance at a market interest rate at the time of closing using the credit rating of the State of New Jersey. The current term of the long-term loans offered through the NJIB is up to thirty years. The current portion of the principal balance having a stated interest rate of zero percent (0%) is 75% with the remaining portion of 25% having a market based interest rate. NJIB generally schedules its long-term debt financings in May and November.

 

In September 2018, the NJIB announced changes to the SRF program for project funding priority ranking, the proportions of interest free loans and market interest rate loans and overall loan limits on interest free loan balances to investor-owned water utilities. These changes affect SRF projects for which the construction loan closes after September 2018. Under the new guidelines, the principal balance having a stated interest rate of zero percent (0%) is 25% of the loan balance with the remaining portion of 75% having a market based interest rate. This is limited to the first $10.0 million of the loan. Loan amounts above $10.0 million do not participate in the 0% rate program, but do participate at the market based interest rate.

 

The only active project affected by the SRF program changes is the upgrade to the Company’s Carl J. Olsen water treatment plant (CJO Plant). In April 2018, the NJBPU approved Middlesex’s request to participate in the NJIB loan program and borrow up to $55.0 million for the CJO Plant project. Although the CJO Plant project has met all the SRF Program requirements, the NJIB has been unable to commit to funding the construction loan.

 

In order to help ensure adherence to its comprehensive financing plan, Middlesex received approval from the NJBPU in February 2019 to issue and sell up to $140 million of First Mortgage Bonds through the NJEDA in one or more transactions through December 31, 2022.

 

In May 2018, Middlesex repaid its $9.5 million RENEW 2017 interest-free construction loan by issuing to the NJIB first mortgage bonds designated as Series 2018A ($7.1 million) and Series 2018B ($2.4 million). The interest rate on the Series 2018A bond is zero and the interest rate on the Series 2018B bond ranges between 3.0% and 5.0%. Through March 31, 2019, Middlesex has drawn a total of $8.2 million and expects to draw the remaining proceeds during the second quarter of 2019. The final maturity date for both bonds is August 1, 2047, with scheduled debt service payments over the life of the loans.

 

In April 2018, the NJBPU approved Middlesex’s request to participate in the NJIB loan program to fund the construction of a large-diameter transmission pipeline from the CJO water treatment plant and interconnect with our distribution system. Middlesex closed on a $43.5 million NJIB interest-free construction loan in August 2018. Through March 31, 2019, Middlesex has drawn a total of $16.8 million and expects to draw down the remaining proceeds through the end of 2019.

 

In March 2018, the NJBPU approved Middlesex’s request to borrow up to $14.0 million under the NJIB program to fund the 2018 RENEW Program, which is an ongoing initiative to eliminate all unlined water distribution mains in the Middlesex system. Middlesex closed on an $8.7 million NJIB construction loan in September 2018. Through March 31, 2019, Middlesex has drawn a total of $6.6 million and expects to draw the remaining proceeds during the remainder of 2019. The NJIB has informed the Company that the RENEW 2018 interest-free construction loan is scheduled for the May 2019 long-term debt financing program.

 

In March 2018, the DEPSC approved Tidewater’s request to borrow up to $0.9 million under the Delaware SRF program to fund the replacement of an entire water distribution system of a small Delaware subdivision. Tidewater closed on the SRF loan in May 2018. In April 2019, Tidewater received approval from the DEPSC to increase the borrowing to $1.7 million based on revised project cost estimates. The closing on the additional $0.8 million is expected to occur in June 2019.

 

Fair Value of Financial Instruments - The following methods and assumptions were used by the Company in estimating its fair value disclosure for financial instruments for which it is practicable to estimate that value. The carrying amounts reflected in the condensed consolidated balance sheets for cash and cash equivalents, trade receivables, accounts payable and notes payable approximate their respective fair values due to the short-term maturities of these instruments. The fair value of First Mortgage and State Revolving Fund Bonds (collectively, the Bonds) issued by Middlesex is based on quoted market prices for similar issues. Under the fair value hierarchy, the fair value of cash and cash equivalents is classified as a Level 1 measurement and the fair value of notes payable and the Bonds in the table below are classified as Level 2 measurements. The carrying amount and fair value of the Bonds were as follows:

 

 

  March 31, 2019 December 31, 2018
  Carrying Fair Carrying Fair
  Amount Value Amount Value
Bonds $100,910 $103,247 $101,411 $102,789

 

For other long-term debt for which there was no quoted market price and there is not an active trading market, it was not practicable to estimate their fair value (for details, including carrying value, interest rate and due date on these series of long-term debt, please refer to those series noted as “Amortizing Secured Note”, “State Revolving Trust Note” and “Construction Loans” on the Condensed Consolidated Statements of Capital Stock and Long-Term Debt). The carrying amount of these instruments was $67.6 million and $61.5 million at March 31, 2019 and December 31, 2018, respectively. Customer advances for construction have carrying amounts of $22.6 million at both March 31, 2019 and December 31, 2018, respectively. Their relative fair values cannot be accurately estimated since future refund payments depend on several variables, including new customer connections, customer consumption levels and future rate increases.