Mergers, Acquisitions and Dispositions Disclosures [Text Block] ACQUISITIONS AND DISPOSITIONS (Entergy Corporation and Entergy Mississippi)
Acquisitions

Sunflower Solar

In November 2018, Entergy Mississippi entered into an agreement for the purchase of an approximately 100 MW solar photovoltaic facility to be sited on approximately 1,000 acres in Sunflower County, Mississippi. The project, Sunflower Solar facility, was being built by Sunflower County Solar Project, LLC, an indirect subsidiary of Recurrent Energy, LLC. In December 2018, Entergy Mississippi filed a joint petition with Sunflower County Solar Project with the MPSC for Sunflower County Solar Project to construct and for Entergy Mississippi to acquire and thereafter own, operate, improve, and maintain the solar facility. In March 2020, Entergy Mississippi filed supplemental testimony addressing questions and observations raised in August 2019 by consultants retained by the Mississippi Public Utilities Staff and proposing an alternative structure for the transaction that would reduce its cost. In April 2020 the MPSC issued an order approving certification of the Sunflower Solar facility, subject to certain conditions, including: (i) that Entergy Mississippi pursue a tax equity partnership structure through which the partnership would acquire and own the facility under the build-own-transfer agreement and (ii) that if Entergy Mississippi does not consummate the partnership structure under the terms of the order, there will be a cap of $136 million on the level of recoverable costs. In April 2022, Entergy Mississippi confirmed mechanical completion of the Sunflower Solar facility. Pursuant to the MPSC’s April 2020 order, MS Sunflower Partnership, LLC was formed for the tax equity partnership with Entergy Mississippi as its managing member. In May 2022 both Entergy Mississippi and the tax equity investor made capital contributions to the tax equity partnership that
were then used to make an initial payment of $105 million for acquisition of the facility. Substantial completion of the Sunflower Solar facility was accepted by Entergy Mississippi in September 2022. A final payment is currently expected in fourth quarter 2022. Commercial operation at the Sunflower Solar facility commenced in September 2022.

Dispositions

Palisades

In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. The NRC issued an order approving the application in December 2021. Palisades was shut down in May 2022 and defueled in June 2022. The Palisades transaction closed in June 2022 for a purchase price of $1,000 (subject to adjustment for net liabilities and other amounts). The sale included the transfer of the Palisades nuclear decommissioning trust and the asset retirement obligation for spent fuel management and plant decommissioning. The transaction resulted in a gain of $166 million ($130 million net-of-tax) in the second quarter 2022. The disposition-date fair value of the nuclear decommissioning trust fund was approximately $552 million and the disposition-date fair value of the asset retirement obligation was approximately $708 million. The transaction also included property, plant, and equipment with a net book value of zero and materials and supplies.
Entergy Mississippi [Member]  
Mergers, Acquisitions and Dispositions Disclosures [Text Block] ACQUISITIONS AND DISPOSITIONS (Entergy Corporation and Entergy Mississippi)
Acquisitions

Sunflower Solar

In November 2018, Entergy Mississippi entered into an agreement for the purchase of an approximately 100 MW solar photovoltaic facility to be sited on approximately 1,000 acres in Sunflower County, Mississippi. The project, Sunflower Solar facility, was being built by Sunflower County Solar Project, LLC, an indirect subsidiary of Recurrent Energy, LLC. In December 2018, Entergy Mississippi filed a joint petition with Sunflower County Solar Project with the MPSC for Sunflower County Solar Project to construct and for Entergy Mississippi to acquire and thereafter own, operate, improve, and maintain the solar facility. In March 2020, Entergy Mississippi filed supplemental testimony addressing questions and observations raised in August 2019 by consultants retained by the Mississippi Public Utilities Staff and proposing an alternative structure for the transaction that would reduce its cost. In April 2020 the MPSC issued an order approving certification of the Sunflower Solar facility, subject to certain conditions, including: (i) that Entergy Mississippi pursue a tax equity partnership structure through which the partnership would acquire and own the facility under the build-own-transfer agreement and (ii) that if Entergy Mississippi does not consummate the partnership structure under the terms of the order, there will be a cap of $136 million on the level of recoverable costs. In April 2022, Entergy Mississippi confirmed mechanical completion of the Sunflower Solar facility. Pursuant to the MPSC’s April 2020 order, MS Sunflower Partnership, LLC was formed for the tax equity partnership with Entergy Mississippi as its managing member. In May 2022 both Entergy Mississippi and the tax equity investor made capital contributions to the tax equity partnership that
were then used to make an initial payment of $105 million for acquisition of the facility. Substantial completion of the Sunflower Solar facility was accepted by Entergy Mississippi in September 2022. A final payment is currently expected in fourth quarter 2022. Commercial operation at the Sunflower Solar facility commenced in September 2022.

Dispositions

Palisades

In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. The NRC issued an order approving the application in December 2021. Palisades was shut down in May 2022 and defueled in June 2022. The Palisades transaction closed in June 2022 for a purchase price of $1,000 (subject to adjustment for net liabilities and other amounts). The sale included the transfer of the Palisades nuclear decommissioning trust and the asset retirement obligation for spent fuel management and plant decommissioning. The transaction resulted in a gain of $166 million ($130 million net-of-tax) in the second quarter 2022. The disposition-date fair value of the nuclear decommissioning trust fund was approximately $552 million and the disposition-date fair value of the asset retirement obligation was approximately $708 million. The transaction also included property, plant, and equipment with a net book value of zero and materials and supplies.