The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.
Entergy Arkansas [Member]  
Difference Between Estimated Incurred Removal Costs And Estimated Removal Costs Recovered In Rates In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9
Cumulative decommissioning and retirement cost liabilities and expenses
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.
Entergy Louisiana [Member]  
Difference Between Estimated Incurred Removal Costs And Estimated Removal Costs Recovered In Rates In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9
Cumulative decommissioning and retirement cost liabilities and expenses
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.
Entergy Mississippi [Member]  
Difference Between Estimated Incurred Removal Costs And Estimated Removal Costs Recovered In Rates In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9
Cumulative decommissioning and retirement cost liabilities and expenses
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.
Entergy New Orleans [Member]  
Difference Between Estimated Incurred Removal Costs And Estimated Removal Costs Recovered In Rates In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9
Cumulative decommissioning and retirement cost liabilities and expenses
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.
Entergy Texas [Member]  
Difference Between Estimated Incurred Removal Costs And Estimated Removal Costs Recovered In Rates In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9
Cumulative decommissioning and retirement cost liabilities and expenses
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.
System Energy [Member]  
Difference Between Estimated Incurred Removal Costs And Estimated Removal Costs Recovered In Rates In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9
Cumulative decommissioning and retirement cost liabilities and expenses
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.