NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.
Entergy Arkansas [Member]  
Asset Retirement Obligations
NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.
Entergy Louisiana [Member]  
Asset Retirement Obligations
NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.
Entergy Mississippi [Member]  
Asset Retirement Obligations
NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.
Entergy New Orleans [Member]  
Asset Retirement Obligations
NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.
Entergy Texas [Member]  
Asset Retirement Obligations
NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.
System Energy [Member]  
Asset Retirement Obligations
NOTE 9. ASSET RETIREMENT OBLIGATIONS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

Accounting standards require companies to record liabilities for all legal obligations associated with the retirement of long-lived assets that result from the normal operation of the assets.  For Entergy, substantially all of its asset retirement obligations consist of its liability for decommissioning its nuclear power plants.  In addition, an insignificant amount of removal costs associated with non-nuclear power plants is also included in the decommissioning and asset retirement costs line item on the balance sheets.

These liabilities are recorded at their fair values (which are the present values of the estimated future cash outflows) in the period in which they are incurred, with an accompanying addition to the recorded cost of the long-lived asset.  The asset retirement obligation is accreted each year through a charge to expense, to reflect the time value of money for this present value obligation.  The accretion will continue through the completion of the asset retirement activity.  The amounts added to the carrying amounts of the long-lived assets will be depreciated over the useful lives of the assets.  The application of accounting standards related to asset retirement obligations is earnings neutral to the rate-regulated business of the Registrant Subsidiaries.

In accordance with ratemaking treatment and as required by regulatory accounting standards, the depreciation provisions for the Registrant Subsidiaries include a component for removal costs that are not asset retirement obligations under accounting standards.  In accordance with regulatory accounting principles, the Registrant Subsidiaries have recorded regulatory assets (liabilities) in the following amounts to reflect their estimates of the difference between estimated incurred removal costs and estimated removal costs expected to be recovered in rates:
 December 31,
 20202019
 (In Millions)
Entergy Arkansas$212.6$168.9
Entergy Louisiana$302.5($2.4)
Entergy Mississippi$107.3$80.8
Entergy New Orleans$63.2$52.9
Entergy Texas$115.3$42.5
System Energy$92.9$75.9

As of December 31, 2020 the regulatory asset for removal costs for the Utility operating companies includes amounts related to Hurricane Laura, Hurricane Delta, and Hurricane Zeta restoration costs.
The cumulative decommissioning and retirement cost liabilities and expenses recorded in 2020 and 2019 by Entergy were as follows:
 Liabilities as
of December 31,
2019
 
 
Accretion
 
 
Spending
Liabilities as
of December 31,
2020
 (In Millions)
Entergy$6,159.2 $394.6 ($84.3)$6,469.5 
Utility    
Entergy Arkansas1,242.6 73.3 (1.7)1,314.2 
Entergy Louisiana1,497.3 76.0 — 1,573.3 
Entergy Mississippi9.7 0.6 (0.5)9.8 
Entergy New Orleans3.5 0.3 — 3.8 
Entergy Texas7.6 0.5 — 8.1 
System Energy931.7 37.2 — 968.9 
Entergy Wholesale Commodities
Big Rock Point40.3 3.3 (2.5)41.1 
Indian Point 1238.6 20.4 (12.4)246.6 
Indian Point 2829.0 69.4 (58.6)839.8 
Indian Point 3808.4 67.4 (6.4)869.4 
Palisades549.8 46.4 (2.1)594.1 
Other (a)0.5 — — 0.5 
 Liabilities as
of December 31,
2018
 
 
Accretion
Change in
Cash Flow
Estimate
 
 
Spending
DispositionsLiabilities as
of December 31,
2019
 (In Millions)
Entergy$6,923.4 $414.0 $273.7 ($45.6)($1,406.3)$6,159.2 
Utility     
Entergy Arkansas1,048.4 68.0 126.2 — — 1,242.6 
Entergy Louisiana1,280.3 69.5 147.5 — — 1,497.3 
Entergy Mississippi9.2 0.5 — — — 9.7 
Entergy New Orleans3.3 0.2 — — — 3.5 
Entergy Texas7.2 0.4 — — — 7.6 
System Energy896.0 35.7 — — — 931.7 
Entergy Wholesale Commodities
Big Rock Point39.7 3.2 — (2.6)— 40.3 
Indian Point 1227.9 19.5 — (8.8)— 238.6 
Indian Point 2768.0 65.5 — (4.5)— 829.0 
Indian Point 3750.6 62.5 — (4.7)— 808.4 
Palisades508.0 42.9 — (1.1)— 549.8 
Pilgrim816.5 44.1 — (23.9)(836.7)(b)— 
Vermont Yankee567.9 1.7 — — (569.6)(b)— 
Other (a)0.4 0.1 — — — 0.5 

(a)    See “Coal Combustion Residuals” below for additional discussion regarding the asset retirement obligations related to coal combustion residuals management.
(b)    See Note 14 to the financial statements for discussion of the sale of the Pilgrim plant to Holtec International in August 2019 and the sale of the Vermont Yankee plant to NorthStar in January 2019.

Nuclear Plant Decommissioning

Entergy periodically reviews and updates estimated decommissioning costs.  The actual decommissioning costs may vary from the estimates because of the timing of plant decommissioning, regulatory requirements, changes in technology, and increased costs of labor, materials, and equipment.  As described below, during 2019 and 2018, Entergy updated decommissioning cost estimates for certain nuclear power plants. Entergy did not update decommissioning cost estimates in 2020.

Utility

In the first quarter 2019, Entergy Arkansas recorded a revision to its estimated decommissioning cost liabilities for ANO 1 and ANO 2 as a result of a revised decommissioning cost study. The revised estimates resulted in a $126.2 million increase in its decommissioning cost liabilities, along with corresponding increases in the related asset retirement cost assets that will be depreciated over the remaining lives of the units.

In the second quarter 2019, Entergy Louisiana recorded a revision to its estimated decommissioning cost liability for Waterford 3 as a result of a revised decommissioning cost study. The revised estimate resulted in a $147.5 million increase in its decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset that will be depreciated over the remaining useful life of the unit.
Entergy Wholesale Commodities

Pilgrim

Entergy Nuclear Generation Company filed its Post-Shutdown Decommissioning Activities report (PSDAR) with the NRC in the fourth quarter 2018 for the Pilgrim plant in anticipation of its May 2019 shutdown. As part of the development of the PSDAR, Entergy obtained a revised decommissioning cost study in the third quarter 2018. The revised estimate resulted in a $117.5 million increase in the decommissioning cost liability and a corresponding impairment charge.

Vermont Yankee

In the fourth quarter 2018, Entergy Wholesale Commodities recorded a revision to its estimated decommissioning cost liability for Vermont Yankee. The revised estimate resulted in a $293 million increase in the decommissioning cost liability, along with a corresponding increase in the related asset retirement cost asset. The revision was prompted by the progress of the Vermont Yankee sales transaction, which is described in Note 14 to the financial statements. Entergy accordingly evaluated the Vermont Yankee asset retirement obligation in light of the terms of the sale transaction, upon determining that Vermont Yankee was in held for sale status. Based on the terms of the sales agreement, which include Entergy receiving a note receivable from the purchaser, Entergy determined that $165 million of the asset retirement cost was impaired, and it was accordingly written down in the fourth quarter 2018. The Vermont Yankee plant was sold to NorthStar in January 2019.

NRC Filings Regarding Trust Funding Levels

Plant owners are required to provide the NRC with a biennial report (annually for units that have shut down or will shut down within five years), based on values as of December 31, addressing the owners’ ability to meet the NRC minimum funding levels. Depending on the value of the trust funds, plant owners may be required to take steps, such as providing financial guarantees through letters of credit or parent company guarantees or making additional contributions to the trusts, to ensure that the trusts are adequately funded and that NRC minimum funding requirements are met.

As nuclear plants individually approach and begin decommissioning, filings will be submitted to the NRC for planned shutdown activities. These filings with the NRC also determine whether financial assurance may be required in addition to the nuclear decommissioning trust fund.

Coal Combustion Residuals

In June 2010 the EPA issued a proposed rule on coal combustion residuals (CCRs) that contained two primary regulatory options: (1) regulating CCRs destined for disposal in landfills or received (including stored) in surface impoundments as so-called “special wastes” under the hazardous waste program of Resource Conservation and Recovery Act (RCRA) Subtitle C; or (2) regulating CCRs destined for disposal in landfills or surface impoundments as non-hazardous wastes under Subtitle D of RCRA.  Under both options, CCRs that are beneficially reused in certain processes would remain excluded from hazardous waste regulation. In April 2015 the EPA published the final CCR rule with the material being regulated under the second scenario presented above - as non-hazardous wastes regulated under RCRA Subtitle D. The final regulations create new compliance requirements including modified storage, new notification and reporting practices, product disposal considerations, and CCR unit closure criteria.  Entergy believes that on-site disposal options will be available at its facilities, to the extent needed for CCR that cannot be transferred for beneficial reuse. In December 2016 the Water Infrastructure Improvements for the Nation Act (WIIN Act) was signed into law, which authorizes states to regulate coal ash rather than leaving primary enforcement to citizen suit actions. States may submit to the EPA proposals for permit programs.