XML 53 R11.htm IDEA: XBRL DOCUMENT v3.7.0.1
Rate And Regulatory Matters
6 Months Ended
Jun. 30, 2017
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.
Entergy Arkansas [Member]  
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.
Entergy Louisiana [Member]  
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.
Entergy Mississippi [Member]  
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.
Entergy New Orleans [Member]  
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.
Entergy Texas [Member]  
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.
System Energy [Member]  
Public Utilities Disclosure [Text Block]
RATE AND REGULATORY MATTERS (Entergy Corporation, Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)
  
Regulatory Assets and Regulatory Liabilities

See Note 2 to the financial statements in the Form 10-K for information regarding regulatory assets and regulatory liabilities in the Utility business presented on the balance sheets of Entergy and the Registrant Subsidiaries.  The following are updates to that discussion.

Fuel and purchased power cost recovery

Entergy Arkansas

Energy Cost Recovery Rider

In March 2017, Entergy Arkansas filed its annual redetermination of its energy cost rate pursuant to the energy cost recovery rider, which reflected an increase in the rate from $0.01164 per kWh to $0.01547 per kWh. The APSC staff filed testimony in March 2017 recommending that the redetermined rate should be implemented with the first billing cycle of April 2017 under the normal operation of the tariff. Accordingly, the redetermined rate went into effect on March 31, 2017 pursuant to the tariff. In July 2017 the Arkansas Attorney General requested additional information to support certain of the costs included in Entergy Arkansas’s 2017 energy cost rate redetermination.

Entergy Louisiana

As discussed in the Form 10-K, in June 2016 the LPSC staff provided notice of audits of Entergy Louisiana’s fuel adjustment clause filings and purchased gas adjustment clause filings. Discovery commenced in March 2017.

Entergy Mississippi

Mississippi Attorney General Complaint

As discussed in the Form 10-K, the Mississippi attorney general filed a complaint in state court in December 2008 against Entergy Corporation, Entergy Mississippi, Entergy Services, and Entergy Power. The defendants have denied the allegations. In June 2017 the District Court issued a case management order setting a trial date in November 2018. Discovery is currently in progress.

Entergy Texas

As discussed in the Form 10-K, in July 2016, Entergy Texas filed an application to reconcile its fuel and purchased power costs for the period April 1, 2013 through March 31, 2016. In December 2016, Entergy Texas entered into a stipulation and settlement agreement resulting in a $6 million disallowance not associated with any particular issue raised and a refund of the over-recovery balance of $21 million as of November 30, 2016, to most customers beginning April 2017 through June 2017. The fuel reconciliation settlement was approved by the PUCT in March 2017 and the refunds were made.

In June 2017, Entergy Texas filed an application for a fuel refund of approximately $30.7 million for the months of December 2016 through April 2017. For most customers, the refunds will flow through bills for the months of July 2017 through September 2017. Also in June 2017, the PUCT’s administrative law judge approved the refund on an interim basis. A final decision in this matter remains pending.

Retail Rate Proceedings

See Note 2 to the financial statements in the Form 10-K for detailed information regarding retail rate proceedings involving the Utility operating companies.  The following are updates to that information.

Filings with the APSC

2016 Formula Rate Plan Filing
    
As discussed in the Form 10-K, Entergy Arkansas is required to make a supplemental filing supporting the recovery of certain nuclear costs. In April 2017, Entergy Arkansas filed a motion consented to by all parties requesting that it be permitted to submit its supplemental filing in conjunction with its 2017 formula rate plan filing, which was subsequently made in July 2017 and is discussed below. In May 2017 the APSC approved the joint motion and proposal to review Entergy Arkansas’s supplemental filing on a concurrent schedule with the 2017 formula rate plan filing. In doing so, however, the APSC noted that a determination of whether the supplemental information supporting certain nuclear expenditures will be considered in the hearing for the 2017 formula rate plan filing or a separate hearing will be made at a later time.

2017 Formula Rate Plan Filing

In July 2017, Entergy Arkansas filed with the APSC its 2017 formula rate plan filing showing Entergy Arkansas’s projected earned return on common equity for the twelve months ended December 31, 2018 test period to be below the formula rate plan bandwidth.  The filing projected a $129.7 million revenue requirement increase to achieve Entergy Arkansas’s target earned return on common equity of 9.75%.  Because the projected revenue increase exceeds the four percent annual revenue constraint for each rate class, however, Entergy Arkansas proposed a $70.9 million revenue requirement increase. Entergy Arkansas requested an order approving its proposed formula rate plan adjustment by December 13, 2017. If a final order is not issued by this date, the proposed formula rate plan adjustment will become effective January 2, 2018, subject to refund.
Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in September 2016, Entergy Arkansas filed an application seeking a finding from the APSC that Entergy Arkansas’s deployment of advanced metering infrastructure is in the public interest. In June 2017 the APSC staff and Arkansas Attorney General filed direct testimony. The APSC staff generally supported Entergy Arkansas’s AMI deployment conditioned on various recommendations. The Arkansas Attorney General’s consultant primarily recommended denial of Entergy Arkansas’s application but alternatively suggested recommendations in the event the APSC approves Entergy Arkansas’s proposal. Entergy Arkansas filed rebuttal testimony in June 2017, substantially accepting the APSC staff’s recommendations. In August 2017, Entergy Arkansas and the parties to the proceeding filed a joint motion to suspend the procedural schedule pending the filing with the APSC of an agreement in principle on all issues.

Filings with the LPSC

Retail Rates - Electric

2014 Formula Rate Plan Filing

As discussed in the Form 10-K, in September 2015, Entergy Louisiana filed its formula rate plan evaluation report for Entergy Gulf States Louisiana’s and Entergy Louisiana’s 2014 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed an unopposed joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of this proceeding with no changes to rates already implemented.

2015 Formula Rate Plan Filing

As discussed in the Form 10-K, in May 2016, Entergy Louisiana filed its formula rate plan evaluation report for its 2015 calendar year operations. In June 2017 the LPSC staff and Entergy Louisiana filed a joint report of proceedings, which was accepted by the LPSC in June 2017, finalizing the results of the May 2016 evaluation report, interim updates, and corresponding proceedings with no changes to rates already implemented.

Also, in November 2016, Entergy Louisiana filed with the LPSC a request to extend the MISO cost recovery mechanism rider provision of its formula rate plan. In March 2017 the LPSC staff submitted direct testimony generally supportive of a one-year extension of the MISO cost recovery mechanism and the intervenor in the proceeding does not oppose an extension for this period of time. In June 2017 an uncontested joint stipulation authorizing a one-year extension of the MISO cost recovery mechanism rider was filed and the LPSC approved the stipulation in July 2017.

2016 Formula Rate Plan Filing

In May 2017, Entergy Louisiana filed its formula rate plan evaluation report for its 2016 calendar year operations. The evaluation report reflects an earned return on common equity of 9.84%. As such, no adjustment to base formula rate plan revenue is required. The following adjustments, however, are required under the formula rate plan: The 2016 formula rate plan evaluation report shows a decrease in formula rate plan revenue of approximately $16.9 million, comprised of a decrease in legacy Entergy Louisiana formula rate plan revenue of $3.5 million, a decrease in legacy Entergy Gulf States Louisiana formula rate plan revenue of $9.7 million, and a decrease in incremental formula rate plan revenue of $3.6 million. Additionally, the formula rate plan evaluation report calls for a decrease in the MISO cost recovery revenue requirement of $40.5 million, from the present level of $46.8 million to $6.3 million. Rates reflecting these adjustments will be implemented with the first billing cycle of September 2017, subject to refund, pending the review proceedings. Parties have intervened in the proceedings. No procedural schedule has been established.

Waterford 3 Replacement Steam Generator Project

See Note 2 to the financial statements in the Form 10-K for discussion of the Waterford 3 replacement steam generator project prudence review proceeding. The refund to customers of approximately $71 million as a result of the settlement approved by the LPSC was made to customers in January 2017. Following a review by the parties, an unopposed joint report of proceedings was filed by the LPSC staff and Entergy Louisiana in May 2017. In May 2017 the LPSC accepted the joint report of proceedings resolving the matter.

Union Power Station

As a term of the LPSC-approved settlement authorizing the purchase of Power Blocks 3 and 4 of the Union Power Station, Entergy Louisiana agreed to make a filing with the LPSC to review its decisions to deactivate Ninemile 3 and Willow Glen 2 and 4 and its decision to retire Little Gypsy 1.  In January 2016, Entergy Louisiana made its compliance filing with the LPSC. Entergy Louisiana, LPSC staff, and intervenors participated in a technical conference in March 2016 where Entergy Louisiana presented information on its deactivation/retirement decisions for these four units in addition to information on the current deactivation decisions for the ten-year planning horizon. Parties have requested further proceedings on the prudence of the decision to deactivate Willow Glen 2 and 4. No party contests the prudence of the decision to deactivate Willow Glen 2 and 4 or suggests reactivation of these units; however, issues have been raised related to Entergy Louisiana’s decision to give up its transmission service rights in MISO for Willow Glen 2 and 4 rather than placing the units into suspended status for the three year term permitted by MISO.  This matter is pending before an ALJ, with an evidentiary hearing scheduled in August 2017.

Retail Rates - Gas

2016 Rate Stabilization Plan Filing

In January 2017, Entergy Louisiana filed with the LPSC its gas rate stabilization plan for the test year ended September 30, 2016. The filing of the evaluation report for test year 2016 reflected an earned return on common equity of 6.37%. As part of the original filing, pursuant to the extraordinary cost provision of the rate stabilization plan, Entergy Louisiana sought to recover approximately $1.5 million in deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016. Entergy Louisiana requested to recover the prudently incurred August 2016 storm restoration costs over ten years, outside of the rate stabilization plan sharing provisions. As a result, Entergy Louisiana’s filing sought an annual increase in revenue of $1.4 million. Following review of the filing, except for the proposed extraordinary cost recovery, the LPSC staff confirmed Entergy Louisiana’s filing was consistent with the principles and requirements of the rate stabilization plan. The extraordinary cost recovery request associated with the 2016 flood-related deferred operation and maintenance expenses incurred for gas operations was removed from the rate stabilization plan pending LPSC consideration in a separate docket. In April 2017 the LPSC approved a joint report of proceedings and Entergy Louisiana submitted a revised evaluation report reflecting a $1.2 million annual increase in revenue with rates implemented with the first billing cycle of May 2017.

In connection with the joint report of proceedings accepted by the LPSC, in May 2017, Entergy Louisiana filed an application to initiate a separate proceeding to recover the deferred operation and maintenance expenses incurred to restore service and repair damage resulting from flooding and widespread rainfall in southeast Louisiana that occurred in August 2016 through the extraordinary cost provision of the gas rate stabilization plan. A procedural schedule has been established, with a hearing in November 2017.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Louisiana filed an application seeking a finding from the LPSC that Entergy Louisiana’s deployment of advanced electric and gas metering infrastructure is in the public interest. The parties reached an uncontested stipulation permitting implementation of Entergy Louisiana’s proposed AMI system, with modifications to the proposed customer charge. In July 2017 the LPSC approved the stipulation.

Filings with the MPSC

Formula Rate Plan

In March 2017, Entergy Mississippi submitted its formula rate plan 2017 test year filing and 2016 look-back filing showing Entergy Mississippi’s earned return for the historical 2016 calendar year and projected earned return for the 2017 calendar year to be within the formula rate plan bandwidth, resulting in no change in rates. In June 2017, Entergy Mississippi and the Mississippi Public Utilities Staff entered into a stipulation that confirmed that Entergy Mississippi’s earned returns for both the 2016 look-back filing and 2017 test year were within the respective formula rate plan bandwidths. In June 2017 the MPSC approved the stipulation, which resulted in no change in rates.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in November 2016, Entergy Mississippi filed an application seeking a finding from the MPSC that Entergy Mississippi’s deployment of advanced metering infrastructure is in the public interest. In May 2017 the Mississippi Public Utilities Staff and Entergy Mississippi entered into and filed a joint stipulation supporting Entergy Mississippi’s filing, and the MPSC issued an order approving the filing without any material changes, finding that Entergy Mississippi’s deployment of AMI is in the public interest and granting a certificate of public convenience and necessity. The MPSC order also confirmed that Entergy Mississippi shall continue to include in rate base the remaining book value of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates.

Filings with the City Council

Retail Rates

As discussed in the Form 10-K, in February 2017, Entergy New Orleans filed a proposed implementation plan for the Energy Smart program from April 2017 through March 2020. As part of the proposal, Entergy New Orleans requested that the City Council identify its desired level of funding for the program during this time period and approve a cost recovery mechanism. In April 2017 the City Council approved an implementation plan for the Energy Smart program from April 2017 through December 2019. The City Council directed that the $11.8 million balance reported for Energy Smart funds be used to continue funding the program for Entergy New Orleans’s legacy customers and that the Energy Smart Algiers program continue to be funded through the Algiers fuel adjustment clause, until additional customer funding is required for the legacy customers. The City Council ordered Entergy New Orleans to submit a supplemental and amended implementation plan for program years 8 and 9 of the Energy Smart program (January 2018 through December 2019) in October 2017. Following that filing, the City Council will determine a specific cost recovery mechanism for the program for both legacy and Algiers customers. The City Council will not permit Entergy New Orleans to recover lost contribution to fixed costs for program years 7, 8, or 9 of the Energy Smart program.

Internal Restructuring
    
As discussed in the Form 10-K, in July 2016, Entergy New Orleans filed an application with the City Council seeking authorization to undertake a restructuring that would result in the transfer of substantially all of the assets and operations of Entergy New Orleans to a new entity, which would ultimately be owned by an existing Entergy subsidiary holding company. In May 2017 the City Council adopted a resolution approving the proposed internal restructuring pursuant to an agreement in principle with the City Council advisors and certain intervenors. Pursuant to the agreement in principle, Entergy New Orleans will credit retail customers $10 million in 2017, $1.4 million in the first quarter of the year after the transaction closes, and $117,500 each month in the second year after the transaction closes until such time as new base rates go into effect as a result of the anticipated 2018 base rate case. Entergy New Orleans began crediting retail customers in June 2017. Also pursuant to the agreement in principle, if FERC approval is received prior to December 31, 2018, Entergy New Orleans will provide additional credits to retail customers of $5 million in each of the years 2018, 2019, and 2020.

Advanced Metering Infrastructure (AMI) Filing

As discussed in the Form 10-K, in October 2016, Entergy New Orleans filed an application seeking a finding from the City Council that Entergy New Orleans’s deployment of advanced electric and gas metering infrastructure is in the public interest. In April 2017, Entergy New Orleans received intervenor testimony that was generally supportive of AMI deployment. The City Council’s advisors filed testimony in May 2017 recommending the adoption of AMI subject to certain modifications, including the denial of Entergy New Orleans’s proposed customer charge as a cost recovery mechanism. In June 2017 the procedural schedule was suspended to allow for settlement discussions. A settlement status conference is scheduled for August 2017.
    
Filings with the PUCT
 
Other Filings

In September 2016, Entergy Texas filed with the PUCT a request to amend its transmission cost recovery factor (TCRF) rider. The proposed amended TCRF rider is designed to collect approximately $29.5 million annually from Entergy Texas’s retail customers. This amount includes the approximately $10.5 million annually that Entergy Texas is currently authorized to collect through the TCRF rider. In September 2016 the PUCT suspended the effective date of the tariff change to March 2017. In December 2016, Entergy Texas and the PUCT reached a settlement agreeing to the amended TCRF annual revenue requirement of $29.5 million. The PUCT approved the settlement and issued a final order in March 2017. Entergy Texas implemented the amended TCRF rider beginning with bills covering usage on and after March 20, 2017.

In June 2017, Entergy Texas filed an application to amend its distribution cost recovery factor (DCRF) rider by increasing the total collection from $8.65 million to approximately $19 million. In July 2017, Entergy Texas, the PUCT, and the two other parties in the proceeding entered into an unopposed stipulation and settlement agreement resulting in an amended DCRF annual revenue requirement of $18.3 million, with the resulting rates effective for usage no later than October 1, 2017. PUCT action on the stipulation and settlement agreement remains pending.

Advanced Metering Infrastructure (AMI) Filing

In its most recent regular session, the Texas legislature enacted legislation that extends statutory support for AMI deployment to Entergy Texas and directs that if Entergy Texas elects to deploy AMI, it shall do so as rapidly as practicable. In July 2017, Entergy Texas filed an application seeking an order from the PUCT approving Entergy Texas’s deployment of AMI. Entergy Texas proposed to replace existing meters with advanced meters that enable two-way data communication; design and build a secure and reliable network to support such communications; and implement support systems. AMI is intended to serve as the foundation of Entergy Texas’s modernized power grid. The filing identified a number of quantified and unquantified benefits, with Entergy Texas showing that its AMI deployment is expected to produce nominal net operational cost savings to customers of $33 million. Entergy Texas also sought to continue to include in rate base the remaining book value, approximately $41 million at December 31, 2016, of existing meters that will be retired as part of the AMI deployment and also to depreciate those assets using current depreciation rates. Entergy Texas proposed a seven-year depreciable life for the new advanced meters, the three-year deployment of which is expected to begin in 2019. Entergy Texas also proposed a surcharge tariff to recover the reasonable and necessary costs it has and will incur under the deployment plan for the full deployment of advanced meters. Further, Entergy Texas is seeking approval of fees that would be charged to customers who choose to opt out of receiving service through an advanced meter and instead receive electric service with a non-standard meter. Subject to approval by the PUCT, deployment of the communications network is expected to begin in 2018. Entergy Texas expects a decision from the PUCT by December 2017.
System Agreement Cost Equalization Proceedings

See the Form 10-K for a discussion of the litigation involving the System Agreement at the FERC and in federal courts.

Entergy Arkansas Opportunity Sales Proceedings

As discussed in the Form 10-K, in June 2009 the LPSC filed a complaint requesting that the FERC determine that certain of Entergy Arkansas’s sales of electric energy to third parties: (a) violated the provisions of the System Agreement that allocated the energy generated by Entergy System resources, (b) imprudently denied the Entergy System and its ultimate consumers the benefits of low-cost Entergy System generating capacity, and (c) violated the provision of the System Agreement that prohibited sales to third parties by individual companies absent an offer of a right-of-first-refusal to other Utility operating companies.  The LPSC’s complaint challenges sales made beginning in 2002 and requests refunds.

In April 2016 the FERC issued orders addressing requests for rehearing filed in July 2012 and an ALJ’s August 2013 initial decision. The first order denies Entergy’s request for rehearing and affirms FERC’s earlier rulings that Entergy’s original methodology for allocating energy costs to the opportunity sales was incorrect and, as a result, Entergy Arkansas must make payments to the other Utility operating companies to put them in the same position that they would have been in absent the incorrect allocation. The FERC clarified that interest should be included with the payments. The second order affirmed in part, and reversed in part, the rulings in the ALJ’s August 2013 initial decision regarding the methodology that should be used to calculate the payments Entergy Arkansas is to make to the other Utility operating companies. The FERC affirmed the ALJ’s ruling that a full re-run of intra-system bills should be performed, but required that methodology be modified so that the sales have the same priority for purposes of energy allocation as joint account sales. The FERC reversed the ALJ’s decision that any payments by Entergy Arkansas should be reduced by 20%. The FERC also reversed the ALJ’s decision that adjustments to other System Agreement service schedules and excess bandwidth payments should not be taken into account when calculating the payments to be made by Entergy Arkansas. The FERC held that such adjustments and excess bandwidth payments should be taken into account, but ordered further proceedings before an ALJ to address whether a cap on any reduction due to bandwidth payments was necessary and to implement the other adjustments to the calculation methodology.

In May 2016, Entergy Services filed a request for rehearing of the FERC’s April 2016 order addressing the requests for rehearing filed in July 2012. Entergy Services also filed a request for clarification and/or rehearing of the FERC’s April 2016 order addressing the ALJ’s August 2013 initial decision. The APSC and the LPSC also filed requests for rehearing of the FERC’s April 2016 order. The rehearing and clarification requests filed in May 2016 are pending FERC action.

Pursuant to the procedural schedule established in the case, Entergy Services re-ran intra-system bills for the ten-year period 2000-2009 to quantify the effects of the FERC's ruling. In November 2016 the LPSC submitted testimony disputing certain aspects of the calculations, and Entergy Services submitted answering testimony in January 2017. In February 2017 the FERC staff filed testimony and Entergy Services filed responsive testimony. In March 2017 the LPSC filed rebuttal testimony. A hearing was held in May 2017. In July 2017, the ALJ issued an initial decision concluding that Entergy Arkansas should pay $86 million plus interest to the other Utility operating companies. The Utility operating companies have the opportunity to challenge the ALJ’s initial decision by filing a brief on exceptions with the FERC. No payments will be made or received by the Utility operating companies until the FERC issues an order reviewing the initial decision and Entergy submits a subsequent filing to comply with that order.

The effect of the FERC’s decisions thus far in the case would be that Entergy Arkansas will make payments to some or all of the other Utility operating companies.  Because further proceedings will still occur in the case, the amount and recipients of payments by Entergy Arkansas are unknown at this time.  Based on testimony previously submitted in the case and its assessment of the April 2016 FERC orders, in the first quarter 2016, Entergy Arkansas recorded a liability of $87 million, which includes interest, for its estimated increased costs and payment to the other Utility operating companies.  This estimate is subject to change depending on how the FERC resolves the issues that are still outstanding in the case, including its review of the July 2017 initial decision.  Entergy Arkansas’s increased costs will be attributed to Entergy Arkansas’s retail and wholesale businesses, and it is not probable that Entergy Arkansas will recover the wholesale portion.  Entergy Arkansas, therefore, recorded a regulatory asset in the first quarter 2016 of approximately $75 million, which represents its estimate of the retail portion of the costs.

Complaint Against System Energy

In January 2017 the APSC and MPSC filed a complaint with the FERC against System Energy. The complaint seeks a reduction in the return on equity component of the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. Entergy Arkansas also sells some of its Grand Gulf capacity and energy to Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans under separate agreements. The current return on equity under the Unit Power Sales Agreement is 10.94%. The complaint alleges that the return on equity is unjust and unreasonable because current capital market and other considerations indicate that it is excessive. The complaint requests the FERC to institute proceedings to investigate the return on equity and establish a lower return on equity, and also requests that the FERC establish January 23, 2017 as a refund effective date. The complaint includes return on equity analysis that purports to establish that the range of reasonable return on equity for System Energy is between 8.37% and 8.67%. System Energy answered the complaint in February 2017 and disputes that a return on equity of 8.37% to 8.67% is just and reasonable. The LPSC and the City Council intervened in the proceeding expressing support for the complaint. System Energy is recording a provision against revenue for the potential outcome of this proceeding. Action by the FERC is pending.

Unit Power Sales Agreement

In August 2017, System Energy submitted to the FERC proposed amendments to the Unit Power Sales Agreement pursuant to which System Energy sells its Grand Gulf capacity and energy to Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, and Entergy New Orleans. The filing proposes limited amendments to the Unit Power Sales Agreement to adopt (1) updated rates for use in calculating Grand Gulf plant depreciation and amortization expenses and (2) updated nuclear decommissioning cost annual revenue requirements, both of which are recovered through the Unit Power Sales Agreement rate formula. The proposed amendments would result in lower charges to the Utility operating companies that buy capacity and energy from System Energy under the Unit Power Sales Agreement. The proposed changes are based on updated depreciation and nuclear decommissioning studies that take into account the renewal of Grand Gulf’s operating license for a term through November 1, 2044. System Energy requested that the FERC accept the amendments effective October 1, 2017. Action by the FERC is pending.