Entergy Services, Inc.
639 Loyola Avenue
New Orleans, LA 70113
Tel 504 576 5035
Fax 504 576 218
Amount 1@entergy.com
|
Alyson M. Mount
Senior Vice President &
Chief Accounting Officer
|
1.
|
We note that Vermont Yankee was written down to $162 million as of March 31, 2012. We also note that on August 27, 2013, you announced your plan to close and decommission Vermont Yankee, and, as a result, recognized an impairment charge of $291.5 million to write down Vermont Yankee’s $349 million carrying value to its $62 million fair value. Please explain the change in carrying value from $162 million at March 31, 2012 to $349 million in the third quarter of 2013.
|
($ in Thousands)
|
Carrying Value After Impairment in
March 2012
|
Carrying Value Prior to Impairment in August 2013
|
Net Electric Plant
|
$102,629
|
$158,595
|
Nuclear Fuel
|
$18,892
|
$57,549
|
Deferred Nuclear Refueling Outage Costs
|
$6,484
|
$33,385
|
Materials and Supplies
|
$33,999
|
$41,882
|
Asset Retirement Cost
|
$-
|
$58,095
|
Total
|
$162,004
|
$349,506
|
1.
|
After the March 2012 write-down to fair value, and until the time of the shutdown decision, Vermont Yankee continued to make capital investments to provide for the plant’s continued operation through the expiration in 2032 of its operating license that was renewed by the NRC in 2011. This resulted in the increase in the net electric plant carrying value.
|
2.
|
Vermont Yankee performed a scheduled refueling outage in March/April 2013. The purchase of fuel in preparation for the refueling is the reason for the increase in the nuclear fuel carrying value. Work performed during the outage is the reason for the increase in the deferred nuclear refueling outage costs carrying value. In accord with ASC 908-360-30, nuclear refueling outage costs are deferred during the outage and amortized over the estimated period to the next outage because these refueling outage expenses are incurred to prepare the units to operate for the next operating cycle without having to be taken off line.
|
3.
|
The change in expectation regarding the timing of decommissioning cash flows due to the decision in August 2013 to cease operations caused a $58 million increase in Vermont Yankee’s estimated decommissioning cost liability. This resulted in a corresponding increase in the asset retirement cost carrying value.
|
·
|
Entergy is responsible for the adequacy and accuracy of the disclosure in Entergy's 2013 Form 10-K;
|
·
|
Staff comments or changes to disclosure in response to staff comments do not foreclose the Securities and Exchange Commission from taking any action with respect to Entergy's 2013 Form 10-K; and
|
·
|
Entergy may not assert staff comments as a defense in any proceeding initiated by the Securities and Exchange Commission or any person under the federal securities laws of the United States.
|