XML 111 R32.htm IDEA: XBRL DOCUMENT v2.4.0.8
Rate And Regulatory Matters (Narrative) (Details) (USD $)
1 Months Ended 0 Months Ended 1 Months Ended 0 Months Ended 1 Months Ended 3 Months Ended 4 Months Ended 1 Months Ended
Apr. 30, 2013
Entergy Louisiana [Member]
Mar. 31, 2013
Entergy Louisiana [Member]
Jan. 31, 2013
Entergy Louisiana [Member]
Dec. 31, 2012
Entergy Louisiana [Member]
Aug. 31, 2012
Entergy Louisiana [Member]
May 31, 2012
Entergy Louisiana [Member]
Jul. 01, 2013
Entergy Mississippi [Member]
Jun. 06, 2013
Entergy Mississippi [Member]
Mar. 31, 2013
Entergy Mississippi [Member]
Dec. 31, 2012
Entergy Mississippi [Member]
May 31, 2013
Entergy Gulf States Louisiana [Member]
Apr. 30, 2013
Entergy Gulf States Louisiana [Member]
Jan. 31, 2013
Entergy Gulf States Louisiana [Member]
Dec. 31, 2012
Entergy Gulf States Louisiana [Member]
Aug. 31, 2012
Entergy Gulf States Louisiana [Member]
May 31, 2012
Entergy Gulf States Louisiana [Member]
Aug. 01, 2013
Entergy New Orleans
Dec. 31, 2012
Entergy New Orleans
Jun. 30, 2013
Entergy New Orleans
Dec. 31, 2013
Entergy New Orleans
Apr. 30, 2013
Entergy Arkansas [Member]
Mar. 31, 2013
Entergy Arkansas [Member]
Dec. 31, 2012
Entergy Arkansas [Member]
Commitments and Contingencies [Abstract]                                              
Additional Provision Recorded For Refund To Customers                                     $ 1,100,000        
Refund To Customers                                       6,000,000      
Potential cost for Entergy Arkansas for years 2003, 2004, and 2006 based on intra-system bills                                             12,000,000
Increase In Potential Costs For Entergy Arkansas For Years 2003, 2004, and 2006 Based On Intra-System Bill                                         2,300,000    
Amount Entegy Arkansas Shareholders Should Pay Customers                                             34,000,000
Per LPSC, the amount of damages to be paid by Entergy Arkansas to the Utility Operating Companies       7,000,000           23,000,000       42,000,000       4,000,000          
Requested replenishment of storm escrow accounts - Hurricane Isaac 200,000,000                     90,000,000                      
Requested recovery of system restoration costs - Hurricane Isaac 247,700,000                     73,800,000                      
Storm restoration costs incurred - Hurricane Isaac             32,000,000                                
Storm restoration costs incurred that are recoverable through the formula rate plan - Hurricane Isaac             700,000                                
Storm reserve accrual - Hurricane Isaac             750,000                                
Increase for first year retail revenue requirement associated with W3 replacement steam generator project       88,000,000                                      
Reduction For First Year Capacity Charges For Purchase By Entergy Gulf States Louisiana From Entergy Louisiana for One Third Of Acadia Unit 2 Capacity And Energy       17,000,000                                      
Expected retail jurisdictional cost                           16,900,000                  
APSC filing requested return on common equity                                           10.40%  
APSC filing requested rate increase proposed spin merge of transmission business                                           218,000,000  
APSC filing requested revenue transfer from collection in riders to base rates MISO scenario                                           49,000,000  
APSC filing requested rate increase transition to MISO scenario                                           174,000,000  
Realignment of the recovery from Entergy Louisiana's fuel adjustment clause to base rates per LPSC January 2013 audit report     1,000,000                                        
Refund to customers per LPSC Staff January 2013 audit report     1,900,000                                        
Public Utilities Recommended Midpoint Return On Common Equity           9.63%         9.95%                        
Public Utilities Earned Return On Common Equity   10.40%     10.38%     10.59% 10.55%       11.18%   11.86% 11.94%              
Rate reduction                         43,000                    
Rate Increase   13,000,000                                          
Cost Of Service Rate Decrease                             5,700,000 6,500,000              
Rate Decrease for Incremental Capacity Costs                             20,300,000 22,900,000              
Rate Increase for Incremental Capacity Costs         15,900,000 18,100,000           7,300,000                      
Electric Base Revenue Increase               22,300,000 36,300,000                            
Electric Base Revenue Decrease                                 1,625,000            
Increase in Annual Funding for Storm Reserve             1,750,000                                
Withdrawal From Funded Storm Reserve     $ 187,000,000                   $ 65,000,000