Commitments and Contingencies
6 Months Ended
Jun. 30, 2013
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

Entergy Arkansas [Member]
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

Entergy Gulf States Louisiana [Member]
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

Entergy Louisiana [Member]
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

Entergy Mississippi [Member]
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

Entergy New Orleans
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

Entergy Texas [Member]
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.

 

System Energy [Member]
 
Commitments And Contingencies

ENTERGY CORPORATION AND SUBSIDIARIES

 

NOTES TO FINANCIAL STATEMENTS
(Unaudited)

 

 

NOTE 1. COMMITMENTS AND CONTINGENCIES (Entergy Corporation, Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, Entergy Texas, and System Energy)

 

            Entergy and the Registrant Subsidiaries are involved in a number of legal, regulatory, and tax proceedings before various courts, regulatory commissions, and governmental agencies in the ordinary course of business.  While management is unable to predict the outcome of such proceedings, management does not believe that the ultimate resolution of these matters will have a material adverse effect on Entergy's results of operations, cash flows, or financial condition, except as otherwise discussed in the Form 10-K or in this report.  Entergy discusses regulatory proceedings in Note 2 to the financial statements in the Form 10-K and herein, discusses tax proceedings in Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein, and discusses proceedings involving Vermont Yankee in Note 1 to the financial statements in the Form 10-K and in Note 11 to the financial statements herein.

 

ANO Damage and Outage

 

            On March 31, 2013, during a scheduled refueling outage at ANO 1, a contractor-owned and operated heavy-lifting apparatus collapsed while moving the generator stator out of the turbine building.  The collapse resulted in the death of an ironworker and injuries to several other contract workers, caused ANO 2 to shut down, and damaged the ANO turbine building.  The turbine building serves both ANO 1 and 2 and is a non-radiological area of the plant.  Entergy Arkansas is in the process of repairing this damage and readying ANO 1 to return to operation.  ANO 2 reconnected to the grid on April 28, 2013.  Restoration and restart efforts with respect to ANO 1 are ongoing and are expected to be complete before September 30, 2013.  The total cost of assessment, restoration of off-site power, site restoration, debris removal, and replacement of damaged property and equipment is currently estimated to be in the range of $95 million to $120 million.   This estimate may change through the conclusion of restoration activities.  In addition, Entergy Arkansas incurred replacement power costs for ANO 2 power during its outage and is incurring incremental replacement power costs for ANO 1 power because the outage extended beyond the originally-planned duration of the refueling outage.  Each of the Utility operating companies has recovery mechanisms in place designed to recover its prudently-incurred fuel and purchased power costs.

 

            Entergy Arkansas is assessing its options for recovering damages that resulted from the stator drop, including its insurance coverage and legal action.  Entergy is a member of Nuclear Electric Insurance Limited (NEIL), a mutual insurance company that provides property damage coverage to the members' nuclear generating plants, including ANO.  NEIL has notified Entergy that it believes that a $50 million course of construction sublimit applies to any loss associated with the lifting apparatus failure and stator drop at ANO.  Entergy has responded that it disagrees with NEIL's position and is evaluating its options for enforcing its rights under the policy.  On July 12, 2013, Entergy Arkansas filed a complaint in the Circuit Court in Pope County, Arkansas against the owner of the heavy-lifting aparatus that collapsed, an engineering firm, a general contractor, and certain individuals asserting claims of breach of contract, negligence, and gross negligence in connection with their responsibility for the stator drop.

 

             In the second quarter 2013, Entergy Arkansas recorded an insurance receivable of $50 million based on the minimum amount that it expects to receive from NEIL.  This $50 million receivable completely offset the approximately $41 million of capital spending and also offset $9 million of the operation and maintenance expense incurred for the recovery through June 30, 2013.  Entergy Arkansas has incurred approximately $14 million in operation and maintenance expense in excess of its insurance receivable as of June 30, 2013.

 

Nuclear Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on nuclear liability and property insurance associated with Entergy's nuclear power plants.

 

Conventional Property Insurance

 

            See Note 8 to the financial statements in the Form 10-K for information on Entergy's non-nuclear property insurance program.

 

Employment Litigation

 

            The Registrant Subsidiaries and other Entergy subsidiaries are responding to various lawsuits in both state and federal courts and to other labor-related proceedings filed by current and former employees and third parties not selected for open positions.  These actions include, but are not limited to, allegations of wrongful employment actions; wage disputes and other claims under the Fair Labor Standards Act or its state counterparts; claims of race, gender and disability discrimination; disputes arising under collective bargaining agreements; unfair labor practice proceedings and other administrative proceedings before the National Labor Relations Board; claims of retaliation; and claims for or regarding benefits under various Entergy Corporation sponsored plans.  Entergy and the Registrant Subsidiaries are responding to these lawsuits and proceedings and deny liability to the claimants.

 

Asbestos Litigation (Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas)

 

            See Note 8 to the financial statements in the Form 10-K for information regarding asbestos litigation at Entergy Arkansas, Entergy Gulf States Louisiana, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas.