a. Environmental.

MGE Energy and MGE are subject to frequently changing local, state, and federal regulations concerning air quality, water quality, land use, threatened and endangered species, hazardous materials handling, and solid waste disposal. These regulations affect the manner in which they conduct their operations, the costs of those operations, as well as capital and operating expenditures. Regulatory initiatives, proposed rules, and court challenges to adopted rules, have the potential to have a material effect on our capital expenditures and operating costs. These initiatives, proposed rules, and court challenges include:

The President's announced plan and directive to the EPA to regulate carbon pollution, or GHG emissions, from new and existing electric power generation, and EPA's related proposed GHG New Source Performance Standards (NSPS).

Rules to regulate NOx and SO2 emissions, including the EPA's Cross State Air Pollution Rule (CSAPR), which recently has been reinstated by the US Supreme Court (see below for recent developments with CSAPR). The Sierra Club has sought federal appellate court review of Wisconsin's implementation plan for CAVR. Both the pending reinstatement of CSAPR and the appellate court review of Wisconsin's implementation plan for Clean Air Visibility Rule (CAVR) make the nature of compliance requirements uncertain.

Rules to regulate mercury and similar emissions, including Wisconsin's adopted Mercury Rule and the EPA's adopted Mercury and Air Toxics Standards.

The EPA's proposed cooling water intake rules. The EPA issued a proposed Phase II rule and alternative compliance strategies for existing facilities in April 2011 and has announced that it intends to release the final rule in May 2014 pursuant to a consent agreement.

The EPA's proposed water effluent limitations guidelines and standards for steam electric power plants, which focus on the reduction of metals and other pollutants in wastewater from new and existing power plants from coal-burning plants such as our Columbia and Elm Road Units.

The EPA's ongoing review of several National Ambient Air Quality Standards (NAAQS), including the potential lowering of ozone NAAQS, and upcoming guidance for determining attainment for sulfur dioxide NAAQS.

The EPA is reconsidering the current emergency dispatch restrictions in the Reciprocating Internal Combustion Engines Maximum Achievable Control Technology (RICE MACT) regulation. The reconsideration could result in increased or decreased restrictions for these engines.

The matters in the bullet points above are discussed further in Footnote 18.d. in MGE Energy's and MGE's 2013 Annual Report on Form 10-K. In addition to the developments noted above, the following discussion is an update to the current status of environmental matters set forth in that Footnote.

EPA's Cross-State Air Pollution Rule (CSAPR) Upheld by the Supreme Court

On April 29, 2014, the US Supreme Court issued a decision upholding CSAPR, thereby reversing the D.C. Circuit Court's decision on CSAPR, and remanding the matter back to the D.C. Circuit for further proceedings. The EPA may amend CSAPR to modify compliance deadlines that have passed since the rule was vacated by the D.C. Circuit. It is unclear if the rule will be reinstated for 2014 emissions or later. The Clean Air Interstate Rule (CAIR) will remain in effect until CSAPR is reinstated. See MGE Energy's and MGE's 2013 Annual Report on Form 10K for additional information on the legal proceedings associated with these environmental matters.

Past evaluations of CSAPR's effect on MGE have pointed to SO2 emissions at our Columbia plant as being our primary concern in meeting emissions allocations under CSAPR. Planned new SO2 controls at Columbia are underway; Unit 2 was completed in April 2014 and Unit 1 is expected to be completed by third quarter of 2014 (see Footnote 4 for information regarding the Columbia environmental construction project). MGE expects that the costs pertaining to meeting CSAPR requirements will be fully recoverable through rates. We will continue to monitor and evaluate recoverability through the D.C. Circuit Court process and the EPA implementation phase.

Columbia

Based upon current available information, compliance with various environmental requirements and initiatives is expected to result in significant additional operating and capital expenditures at Columbia as noted below.

Columbia Environmental Project

See Footnote 4 for information regarding the Columbia environmental construction project.

Columbia Clean Air Act Litigation

In December 2009, the EPA sent a notice of violation (NOV) to MGE as one of the co-owners of Columbia. The NOV alleges that WPL, as owner-operator, and the other co-owners failed to comply with appropriate pre-construction review and permitting requirements and, as a result, violated the PSD program requirements, the Title V operating permit requirements of the CAA and the Wisconsin State Implementation Plan (SIP). In April 2013, the EPA filed a lawsuit against the co-owners of Columbia asserting similar allegations. In September 2010 and April 2013, Sierra Club filed lawsuits against WPL alleging violations of the CAA at Columbia and other WPL-operated Wisconsin facilities.

In April 2013, WPL, as owner-operator, along with the other owners of Columbia, entered into a consent decree with the EPA and the Sierra Club to resolve these claims, while admitting no liability. In June 2013, the consent decree was approved and entered by the Court. The consent decree requires installation of the following emission controls at Columbia: scrubbers and baghouses at Columbia Units 1 and 2 by December 31, 2014, and an SCR system at Columbia Unit 2 by December 31, 2018. In addition, the consent decree establishes emission rate limits for SO2, NOx, and particulate matter for Columbia Units 1 and 2. The consent decree also includes annual plant-wide emission caps for SO2 and NOx for Columbia. MGE also paid approximately $0.2 million as its share of a civil penalty and will complete approximately $0.6 million in environmental mitigation projects. MGE intends to seek recovery in rates of the costs associated with its compliance with the terms of the final consent decree and currently expects to recover any material compliance costs.

b. Chattel Paper Agreement and Other Guarantees.

MGE makes available to qualifying customers a financing program for the purchase and installation of energy-related equipment that will provide more efficient use of utility service at the customer's property. MGE is party to a chattel paper purchase agreement with a financial institution under which it can sell or finance an undivided interest with recourse, in up to $10.0 million of the financing program receivables, until July 31, 2014. At March 31, 2014, MGE had sold a $5.1 million interest in these receivables. MGE retains the servicing responsibility for these receivables. As of March 31, 2014, the servicing asset recognized by MGE is $0.3 million.

MGE accounts for servicing rights under the amortization method. Initial determination of the servicing asset fair value is based on the present value of the estimated future cash flows. The discount rate is based on the PSCW authorized weighted cost of capital.

MGE would be required to perform under its guarantee if a customer defaulted on its loan. The energy-related equipment installed at the customer sites is used to secure the customer loans. The loan balances outstanding at March 31, 2014, approximate the fair value of the energy-related equipment acting as collateral. The length of the MGE guarantee to the financial institution varies from one to ten years depending on the term of the underlying customer loan. Principal payments for the remainder of 2014 and the next four years on the loans are:

(In thousands)20142015201620172018
Chattel Paper$ 477$ 1,007$ 910$ 506$ 449

c. Legal Matters.

MGE is involved in various legal matters that are being defended and handled in the normal course of business. MGE maintains accruals for such costs that are probable of being incurred and subject to reasonable estimation. The accrued amount for these matters is not material to the financial statements.

d. Purchase Contracts.

MGE Energy and MGE have entered into various commodity supply, transportation, and storage contracts to meet their obligations to deliver electricity and natural gas to customers. As of March 31, 2014, the future commitments related to these purchase contracts were as follows:

(In thousands)20142015201620172018
Purchase power(a)$50,542$49,072$49,743$50,243$51,265

(a) MGE has several purchase power agreements to help meet future electric supply requirements. Management expects to recover these costs in future customer rates.