Columbia Environmental Project Construction (Details) (USD $)
12 Months Ended
Dec. 31, 2012
Dec. 31, 2011
Dec. 31, 2012
One Year From Balance Sheet Date [Member]
Dec. 31, 2012
More Than One And Within Two Years From Balance Sheet Date [Member]
Dec. 31, 2012
Columbia Environmental Project [Member]
Dec. 31, 2012
Columbia Units [Member]
Jointly Owned Plants [Line Items]            
Jointly owned plant's share of MGE's net generating capability           29.00%
Ownership interest in jointly owned plant           22.00%
WPL ownership interest of Columbia           46.20%
WPSC ownership interest of Columbia           31.80%
Columbia Environmental Project [Line Items]            
MGE's share of total expected capital expenditures     $ 68,000,000 $ 12,000,000 $ 140,000,000  
Total incurred costs to date 98,411,000 34,055,000     59,900,000  
MGE's share of AFUDC equity         $ 1,400,000  
Carrying cost on pre-construction costs - AFUDC rate         100.00%