XML 66 R39.htm IDEA: XBRL DOCUMENT v3.22.4
Joint Plant Ownership (Tables)
12 Months Ended
Dec. 31, 2022
Regulated Operations [Abstract]  
Schedule of Joint Plant Ownership

The following table shows MGE's interest in utility plant in service, and the related accumulated depreciation reserves and other information related to MGE's jointly owned facilities:

 

(In thousands, except for
percentages and MW)

 

Columbia(a)

 

Elm Road(b)

 

West Campus(c)

 

Forward Wind(d)

 

Two Creeks(e)

 

Badger Hollow
I & II
(f)

Ownership interest

 

 

19

%

 

 

8.33

%

 

 

55

%

 

 

12.8

%

 

 

33

%

 

 

33

%

Share of generation (MW)

 

 

211

MW

 

 

106

MW

 

 

157

MW

 

 

18

MW

 

 

50

MW

 

 

100

MW

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

For the year ended December 31,

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operating expense - 2022

 

$

26,141

 

 

$

18,613

 

 

$

(g)

 

 

$

662

 

 

$

1,032

 

 

$

787

 

Operating expense - 2021

 

 

33,284

 

 

 

18,478

 

 

 

(g)

 

 

 

669

 

 

 

953

 

 

 

140

 

Operating expense - 2020

 

 

27,127

 

 

 

17,259

 

 

 

(g)

 

 

 

664

 

 

 

118

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

As of December 31, 2022

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility plant

 

$

 

 

$

202,118

 

 

$

115,137

 

 

$

34,117

 

 

$

67,890

 

 

$

74,941

 

Accumulated depreciation

 

 

 

 

 

(40,951)

 

 

 

(37,857)

 

 

 

(15,952)

 

 

 

(5,145)

 

 

 

(2,566)

 

Plant anticipated to be
retired early, net

 

 

147,659

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Construction work in progress

 

 

4,805

 

 

 

3,410

 

 

 

809

 

 

 

68

 

 

 

 

 

 

52,187

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

As of December 31, 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility plant

 

$

 

 

$

202,604

 

 

$

114,090

 

 

$

34,084

 

 

$

67,814

 

 

$

69,178

 

Accumulated depreciation

 

 

 

 

 

(39,279)

 

 

 

(34,907)

 

 

 

(14,945)

 

 

 

(2,932)

 

 

 

(227)

 

Plant anticipated to be
retired early, net

 

 

158,983

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Construction work in progress

 

 

2,388

 

 

 

898

 

 

 

493

 

 

 

21

 

 

 

 

 

 

19,748

 

 

(a)
MGE and the other co-owners announced plans to retire Columbia, a two unit coal-fired generation facility located in Portage, Wisconsin. The co-owners intend to retire Unit 1 and Unit 2 by June 2026. Final timing and retirement dates are subject to change depending on operational, regulatory, and other factors. As of December 31, 2022 and 2021, early retirement of Columbia was probable. See Footnote 4 for further information.
(b)
Two coal-fired generating units in Oak Creek, Wisconsin. In November 2021, MGE announced plans to end the use of coal as a primary fuel at the Elm Road Units and transition the plant to natural gas. By the end of 2030, MGE expects coal to be used only as a backup fuel at the Elm Road Units. This transition will help MGE meet its 2030 carbon reduction goals. By 2035, MGE expects that the Elm Road Units will be fully transitioned away from coal, which will eliminate coal as an internal generation source for MGE.
(c)
MGE Power West Campus and the UW jointly own the West Campus Cogeneration Facility (WCCF) located on the UW campus in Madison, Wisconsin. The UW owns a controlling interest in the chilled-water and steam plants, which are used to meet the
needs for air-conditioning and steam-heat capacity for the UW campus. MGE Power West Campus owns a controlling interest in the electric generation plant, which is leased and operated by MGE.
(d)
The Forward Wind Energy Center (Forward Wind) consists of 86 wind turbines located near Brownsville, Wisconsin.
(e)
The Two Creeks solar generation array is located in the Town of Two Creeks and the City of Two Rivers in Manitowoc and Kewaunee Counties, Wisconsin. Date of commercial operation of the solar array was November 2020.
(f)
The Badger Hollow I and II solar farm is located in southwestern Wisconsin in Iowa County, near the villages of Montfort and Cobb. Date of commercial operation of Badger Hollow I was November 2021. Construction of Badger Hollow II is expected to be completed in the second half of 2023.
(g)
Operating charges are allocated to the UW based on formulas contained in the operating agreement. Under the provisions of this arrangement, the UW is required to reimburse MGE for their allocated portion of fuel and operating expenses. For the years ended December 31, 2022, 2021, and 2020, the UW's allocated share of fuel and operating costs was $8.7 million, $6.2 million, and $5.2 million, respectively.