The Company is subject to legal proceedings, claims, investigations and inquiries that arise in the ordinary course of business such as, but not limited to, actions with respect to commercial, intellectual property, employment, personal injury and environmental matters. While the outcome of any matter is inherently uncertain and the Company cannot be sure that it will prevail in any of the cases, subject to the matter referenced below, the Company is not aware of any matters pending that are expected to be material with respect to the Company’s business, financial position, results of operations or cash flows.
Environmental Obligations

In the fourth quarter of 2016, as part of a groundwater discharging permitting process, water samples collected from wells and process water basins at the Company’s Rochester, New Hampshire manufacturing facility, within the Performance Materials segment, showed concentrations of Perfluorinated Compounds (“PFCs”) in excess of state ambient groundwater quality standards. In January 2017, the Company received a notification from the State of New Hampshire Department of Environmental Services (“NHDES”) naming Lydall Performance Materials, Inc. a responsible party with respect to the discharge of regulated contaminants and, as such, required the Company to take action to investigate and remediate the impacts in accordance with standards established by the NHDES. The Company conducted a site investigation, the scope of which was reviewed by the NHDES, in order to assess the extent of potential soil and groundwater contamination and develop a remedial action. Based on input received from NHDES in 2017 with regard to the scope of the site investigation, the Company recorded $0.2 million of expense. In 2018, the Company received a response from the NHDES to the site investigation report outlining proposed remedial actions. The Company recorded an additional $0.1 million of expense in 2018 associated with the expected costs to remediate the impacts of the discharge of regulated contaminants in accordance with standards established by the NHDES. During 2018, the environmental liability was fully reduced reflecting payments made to vendors, resulting in no balance at December 31, 2018. Additionally, the Company incurred $0.2 million of capital expenditures in 2018, in relation to the lining of the Company's fresh water waste lagoons. In the third quarter of 2019, the Company reviewed interim remedial actions with the NHDES. The Company has not yet received further direction from the NHDES. The site investigation is ongoing. The Company cannot be sure that costs will not exceed the current estimates until this matter
is closed with the NHDES, nor that any future corrective action at this location would not have a material effect on the Company’s financial condition, results of operations or cash flows.

In December 2018, the New York State Department of Environmental Conservation (“NYDEC”) informed the Company that the newly acquired Interface site located at Hoosick Falls, NY will be the subject of an investigation in to the possibility of it being an inactive hazardous disposable waste site.  The letter specifically references perflourinated compounds or per- and polyfluoroalkyl substances (“PFAS”) that have been detected in a nearby water supply, soil and/or surface water.  Notably, the PFAS contamination has been identified in the Hoosick Falls area for some time and other large manufacturers in the area have previously been identified as a source.  The NYDEC approved a site characterization plan in December 2019. The Company recorded expense of $0.3 million in the fourth quarter of 2019 as a result of the site characterization plan preparation and site characterization activities, which will continue into the first quarter of 2020. The Company does not know the scope or extent of its future obligations, if any, that may arise from the site investigation and therefore is unable to estimate the cost of any corrective action. Accordingly, the Company cannot assure that the costs of any future corrective at this location would not have a material effect on the Company's financial condition, results of operations or cash flows.

Provisions for such matters are charged to expense when it is probable that a liability has been incurred and reasonable estimates of the liability can be made. Estimates of environmental liabilities are based on a variety of matters, including, but not limited to, the stage of investigation, the stage of the remedial design, evaluation of existing remediation technologies, and presently enacted laws and regulations. In future periods, a number of factors could significantly impact any estimates of environmental remediation costs.