XML 83 R54.htm IDEA: XBRL DOCUMENT v3.5.0.2
Acquisitions, Development and Divestitures - Development (Details) - Northeast Pocono Reliability Project [Member]
$ in Millions
9 Months Ended
Sep. 30, 2016
USD ($)
kV
Substation
mi
Development Projects [Line Items]  
Total length of the expansion project (in miles) | mi 58
Capacity of a transmission line (in kilovolts) | kV 230
Substations included in request | Substation 3
Adder to the return on equity incentive denied in ratemaking request (in basis points) 100
Project costs capitalized | $ $ 350
PPL Electric Utilities Corp [Member]  
Development Projects [Line Items]  
Total length of the expansion project (in miles) | mi 58
Capacity of a transmission line (in kilovolts) | kV 230
Substations included in request | Substation 3
Adder to the return on equity incentive denied in ratemaking request (in basis points) 100
Project costs capitalized | $ $ 350