The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.

PPLPPL Electric
September 30,December 31,September 30,December 31,
2015201420152014
Current Regulatory Assets:
Environmental cost recovery$19$5
Gas supply clause115
Transmission service charge76$7$6
Other 101136
Total current regulatory assets (a)$37$37$10$12
Noncurrent Regulatory Assets:
Defined benefit plans (b)$734$720$411$372
Taxes recoverable through future rates323316323316
Storm costs1011243446
Unamortized loss on debt 70774449
Interest rate swaps (c)146122
Accumulated cost of removal of utility plant 130114130114
AROs10979
Other 1410
Total noncurrent regulatory assets$1,627$1,562$942$897

Current Regulatory Liabilities:
Generation supply charge $41$28$41$28
Demand side management122
Gas supply clause96
Transmission formula rate61426142
Storm damage expense133133
Other 151053
Total current regulatory liabilities$151$91$120$76
Noncurrent Regulatory Liabilities:
Accumulated cost of removal of utility plant$695$693
Coal contracts (d)2859
Power purchase agreement - OVEC (d)8692
Net deferred tax assets2326
Act 129 compliance rider2518$25$18
Defined benefit plans2216
Interest rate swaps8284
Other 14
Total noncurrent regulatory liabilities$962$992$25$18

LKELG&EKU
September 30,December 31,September 30,December 31,September 30,December 31,
201520142015201420152014
Current Regulatory Assets:
Environmental cost recovery$19$5$10$4$9$1
Gas supply clause115115
Fuel adjustment clause422
Other 7171
Total current regulatory assets$27$25$11$21$16$4
Noncurrent Regulatory Assets:
Defined benefit plans (b)$323$348$200$215$123$133
Storm costs677837433035
Unamortized loss on debt 26281718910
Interest rate swaps (c)146122102894433
AROs1097938287151
Plant retirement costs (e)66
Other 8102466
Total noncurrent regulatory assets$685$665$396$397$289$268

Current Regulatory Liabilities:
Demand side management$12$2$6$1$6$1
Gas supply clause9696
Fuel adjustment clause88
Gas line tracker33
Other 2424
Total current regulatory liabilities$31$15$15$10$16$5
Noncurrent Regulatory Liabilities:
Accumulated cost of removal
of utility plant$695$693$304$302$391$391
Coal contracts (d)285912251634
Power purchase agreement - OVEC (d)869259632729
Net deferred tax assets232623242
Defined benefit plans22162216
Interest rate swaps828441424142
Other 14212
Total noncurrent regulatory liabilities$937$974$439$458$498$516

(a) For PPL, these amounts are included in "Other current assets" on the Balance Sheets.

(b) Included in 2015 is $4 million for PPL and LKE, $3 million for LG&E and $1 million for KU related to the deferred recovery of the difference between the pension cost calculated in accordance with LG&E and KU's pension accounting policy and pension cost using a 15 year amortization period for actuarial gains and losses as provided in the June 30, 2015 rate case settlement. See Note 9 and “Kentucky Activities - Rate Case Proceedings” below for additional information.

(c) Amounts include net settlements related to forward-starting interest rate swaps that were terminated in September 2015 and are included in "Cash Flows from Operating Activities" on the Statements of Cash Flows. See Note 14 for additional information.

(d) These liabilities were recorded as offsets to certain intangible assets that were recorded at fair value upon the acquisition of LKE by PPL.

(e) The June 30, 2015 rate case settlement provided for deferred recovery of costs associated with Green River's coal-fired generating unit retirements. These costs include inventory write-downs and separation benefits and will be amortized over three years.

Regulatory Matters

U.K. Activities (PPL)

RIIO-ED1

On April 1, 2015, the RIIO-ED1 eight-year price control period commenced for WPD's four DNOs. See "Item 1. Business - Segment Information - U. K. Regulated Segment" of PPL's 2014 Form 10-K for additional information on RIIO-ED1.

Ofgem Review of Line Loss Calculation

In March 2014, Ofgem issued its final decision on the DPCR4 line loss incentives and penalties mechanism. As a result, during the first quarter of 2014 WPD increased its liability by $65 million for over-recovery of line losses with a reduction to "Operating Revenues" on the Statement of Income. WPD began refunding the liability to customers on April 1, 2015 and will continue through March 31, 2019. The liability at September 30, 2015 was $75 million.

Kentucky Activities (PPL, LKE, LG&E and KU)

Rate Case Proceedings

On June 30, 2015, the KPSC approved a rate case settlement agreement providing for increases in the annual revenue requirements associated with KU base electricity rates of $125 million and LG&E base gas rates of $7 million.  The annual revenue requirement associated with base electricity rates at LG&E was not changed.  Although the settlement did not establish a specific return on equity with respect to the base rates, an authorized 10% return on equity will be utilized in the ECR and GLT mechanisms.  The settlement agreement provides for deferred recovery of costs associated with Green River Units 3 and 4 through their retirement.  The new regulatory asset will be amortized over three years. The settlement also provides regulatory asset treatment for the difference between pension expense calculated in accordance with LG&E and KU’s pension accounting policy and pension expense using a 15 year amortization period for actuarial gains and losses. The new rates and all elements of the settlement became effective July 1, 2015.

KPSC Landfill Proceedings

On May 22, 2015, LG&E and KU filed an application with the KPSC for a declaratory order that the existing CPCN and ECR approvals regarding the initial phases of construction and rate recovery of the landfill for management of CCRs at the Trimble County Station remain in effect. The current design of the proposed landfill provides for construction in substantially the same location as originally proposed with approximately the same storage capacity and expected useful life. On May 20, 2015, the owner of an underground limestone mine filed a complaint with the KPSC requesting it to revoke the CPCN for the Trimble County landfill and limit recovery of costs for the Ghent Station landfill on the grounds that, as a result of cost increases, the proposed landfill no longer constitutes the least cost alternative for CCR management. The KPSC has initiated its own investigation, consolidated the proceedings, and ordered an accelerated procedural schedule. The KPSC conducted a hearing on the matter in September 2015 and LG&E and KU are awaiting a ruling. Although the companies continue to believe that the landfills at the Trimble County and Ghent stations are the least cost options and the CPCN and prior KPSC determinations provide the necessary regulatory authority to proceed with construction of the landfill and obtain cost recovery, LG&E and KU are currently unable to predict the outcome or impact of the pending proceedings.

Pennsylvania Activities (PPL and PPL Electric)

Act 11 authorizes the PUC to approve two specific ratemaking mechanisms: the use of a fully projected future test year in base rate proceedings and, subject to certain conditions, the use of a Distribution System Improvement Charge (DSIC). Such alternative ratemaking procedures and mechanisms provide opportunity for accelerated cost-recovery and, therefore, are important to PPL Electric as it is in a period of significant capital investment to maintain and enhance the reliability of its delivery system, including the replacement of aging distribution assets.

Rate Case Proceeding

On March 31, 2015, PPL Electric filed a request with the PUC for an increase in its annual distribution revenue requirement of approximately $167.5 million. The application was based on a fully projected future test year of January 1, 2016 through December 31, 2016. On September 3, 2015, PPL Electric filed with the PUC Administrative Law Judge a petition for approval of a settlement agreement under which PPL Electric would be permitted to increase its annual distribution rates by $124 million, effective January 1, 2016. On October 5, 2015, the Administrative Law Judge issued a recommended decision approving the settlement agreement. The PUC is expected to issue its final order in December 2015. PPL Electric cannot predict the outcome of this proceeding.

Distribution System Improvement Charge (DSIC)

On March 31, 2015, PPL Electric filed a petition requesting a waiver of the DSIC cap of 5% of billed revenues and approval to increase the maximum allowable DSIC from 5% to 7.5% for service rendered after January 1, 2016. PPL Electric filed the petition concurrently with its 2015 rate case and the Administrative Law Judge granted PPL Electric's request to consolidate these two proceedings. Under the terms of the settlement agreement discussed above, PPL Electric agreed to withdraw the petition without prejudice to re-file it at a later date.

Storm Damage Expense Rider (SDER)

In its December 28, 2012 final rate case order, the PUC directed PPL Electric to file a proposed SDER. The SDER is a reconcilable automatic adjustment clause under which PPL Electric annually will compare actual storm costs to storm costs allowed in base rates and refund or recoup any differences from customers. In March 2013, PPL Electric filed its proposed SDER with the PUC and, as part of that filing, requested recovery of the 2012 qualifying storm costs related to Hurricane Sandy. PPL Electric proposed that the SDER become effective January 1, 2013 at a zero rate with qualifying storm costs incurred in 2013 and the 2012 Hurricane Sandy costs included in rates effective January 1, 2014. In April 2014, the PUC issued a final order approving the SDER with a January 1, 2015 effective date and initially including actual storm costs compared to collections for December 2013 through November 2014. As a result, PPL Electric reduced its regulatory liability by $12 million in March 2014. Also, as part of the April 2014 order, PPL Electric was authorized to recover Hurricane Sandy storm damage costs through the SDER of $29 million over a three-year period beginning January 1, 2015.

On June 20, 2014, the Office of Consumer Advocate (OCA) filed a petition with the Commonwealth Court of Pennsylvania requesting that the Court reverse and remand the April 2014 order permitting PPL Electric to establish the SDER. This matter remains pending before the Commonwealth Court. On January 15, 2015, the PUC issued a final order closing an investigation related to a separate OCA complaint concerning PPL Electric's October 2014 preliminary SDER calculation and modified the effective date of the SDER to February 1, 2015.

Smart Meter Rider (SMR)

Act 129 requires installation of smart meters for new construction, upon the request of consumers and at their cost, or on a depreciation schedule not exceeding 15 years. Under Act 129, EDCs are able to recover the costs of providing smart metering technology. All of PPL Electric's metered customers currently have advanced meters installed at their service locations capable of many of the functions required under Act 129. PPL Electric conducted pilot projects and technical evaluations of its current advanced metering technology and concluded that the current technology does not meet all of the requirements of Act 129. PPL Electric recovered the cost of its pilot programs and evaluations through a cost recovery mechanism, the Smart Meter Rider. In August 2013, PPL Electric filed with the PUC an annual report describing the actions it was taking under its Smart Meter Plan during 2013 and its planned actions for 2014. PPL Electric also submitted revised SMR charges that became effective January 1, 2014. In June 2014, PPL Electric filed its final Smart Meter Plan with the PUC. In that plan, PPL Electric proposes by the end of 2019 to replace all of its current meters with new meters that meet the Act 129 requirements. The total cost of the project is estimated to be approximately $450 million, of which approximately $328 million is expected to be capital. PPL Electric proposes to recover these costs through the SMR which the PUC previously approved for recovery of such costs. On April 30, 2015, the Administrative Law Judge assigned by the PUC to review PPL Electric's Smart Meter Plan issued a recommended decision approving the plan with minor modifications. On September 3, 2015, the PUC entered a final order approving the Smart Meter Plan with minor modifications.

Federal Matters (PPL, LKE and KU)

FERC Wholesale Formula Rates

In September 2013, KU filed an application with the FERC to adjust the formula rate under which KU provides wholesale requirements power sales to 12 municipal customers. Among other changes, the application requests an amended formula whereby KU would charge cost-based rates with a subsequent true-up to actual costs, replacing the current formula which does not include a true-up. KU's application proposed an authorized return on equity of 10.7%. Certain elements, including the new formula rate, became effective April 23, 2014, subject to refund. In April 2014, nine municipalities submitted notices of termination, under the original notice period provisions, to cease taking power under the wholesale requirements contracts. Such terminations are to be effective in 2019, except in the case of one municipality with a 2017 effective date. In addition, a tenth municipality has become a transmission-only customer as of June 2015. In July 2014, KU agreed on settlement terms with the two municipal customers that did not provide termination notices and filed the settlement proposal with the FERC for its approval. In August 2014, the FERC issued an order on the interim settlement agreement allowing the proposed rates to become effective pending a final order. If approved, the settlement agreement will resolve the rate case with respect to these two municipalities, including approval of the formula rate with a true-up provision and authorizing a return on equity of 10% or the return on equity awarded to other parties in this case, whichever is lower. In August 2015, KU filed a partial settlement agreement with the nine terminating municipalities, which, if approved by FERC, would resolve all but one open matter with one municipality, including providing for certain refunds, approving the formula rate with a true-up provision, and authorizing a 10.25% return on equity. A single remaining unresolved issue with one terminating municipality is in FERC litigation proceedings. KU cannot predict the ultimate outcome of these FERC proceedings regarding its wholesale power agreements with the municipalities, but does not currently anticipate significant remaining refunds beyond amounts already recorded.