XML 38 R53.htm IDEA: XBRL DOCUMENT v2.4.0.8
Utility Rate Regulation (Regulatory Matters) (Details) (USD $)
In Millions, unless otherwise specified
3 Months Ended 9 Months Ended
Sep. 30, 2013
Sep. 30, 2013
Integer
Y
Dec. 31, 2012
Regulatory Matters - Pennsylvania Activities - Act 129 (Numeric) [Abstract]      
Under Act 129, percentage cap on costs that can be recovered for implementation of EE and C plan   2.00%  
Under Act 129, percentage reduction in electricity consumption by 2011   1.00%  
Under Act 129, percentage reduction in electricity consumption by 2013   3.00%  
Under Act 129, percentage reduction in peak demand electricity consumption by 2013   4.50%  
Number of hours that are the benchmark for demand reductions by 2013   100  
Number of years EDCs have to comply with consumption reduction target   3  
Under Act 129, percentage reduction in electricity target for the company under the Phase II program   2.10%  
Minimum term of long term supply contract under Act 129 (in years)   4  
Maximum term of long term supply contract under Act 129 (in years)   20  
Maximum percentage of long-term contracts that can be included in the mix of PLR supply contracts under Act 129   25.00%  
Regulatory Matters - Pennsylvania Activities - Smart Meter Rider (Numeric) [Abstract]      
Maximum number of years the cost of smart meters can be depreciated   15  
Regulatory Matters - Pennsylvania Activities - Public Utility Commission Investigation of Retail Electricity Market (Numeric) [Abstract]      
Number of phases of a PUC investigation of retail electricity market   2  
Regulatory Matters - Pennsylvania Activities - Distribution System Improvement Charge (Numeric) [Abstract]      
Number of ratemaking mechanisms authorized for PUC approval   2  
Minimum term for Long Term Infrastructure Improvement Plan (in years)   5  
Maximum term for Long Term Infrastructure Improvement Plan (in years)   10  
Number of issues assigned to the Office of Administrative Law Judge   4  
Regulatory Matters - United Kingdom Activities - Ofgem Review of Line Loss Calculation (Numeric) [Abstract]      
Charge to income during period for line loss incentive/penalty liability $ 21 $ 45  
Minimum potential loss exposure regarding line loss incentive/penalty 93 93  
Maximum potential loss exposure regarding line loss incentive/penalty 226 226  
Liability at period end regarding line loss incentive/penalty 93 93 94
Reduction in liability for line loss liability, beginning April 2013, resulting refunds included in tariff   41  
PPL Electric [Member] | Distribution Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   71  
Return on equity used in approved rate case proceeding   10.40%  
LGE [Member] | Electric Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   34  
Return on equity used in approved rate case proceeding   10.25%  
LGE [Member] | Gas Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   15  
Return on equity used in approved rate case proceeding   10.25%  
KU [Member] | Electric Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   51  
Return on equity used in approved rate case proceeding   10.25%  
PPL Electric Utilities Corp [Member]
     
Regulatory Matters - Pennsylvania Activities - Act 129 (Numeric) [Abstract]      
Under Act 129, percentage cap on costs that can be recovered for implementation of EE and C plan   2.00%  
Under Act 129, percentage reduction in electricity consumption by 2011   1.00%  
Under Act 129, percentage reduction in electricity consumption by 2013   3.00%  
Under Act 129, percentage reduction in peak demand electricity consumption by 2013   4.50%  
Number of hours that are the benchmark for demand reductions by 2013   100  
Number of years EDCs have to comply with consumption reduction target   3  
Under Act 129, percentage reduction in electricity target for the company under the Phase II program   2.10%  
Minimum term of long term supply contract under Act 129 (in years)   4  
Maximum term of long term supply contract under Act 129 (in years)   20  
Maximum percentage of long-term contracts that can be included in the mix of PLR supply contracts under Act 129   25.00%  
Regulatory Matters - Pennsylvania Activities - Smart Meter Rider (Numeric) [Abstract]      
Maximum number of years the cost of smart meters can be depreciated   15  
Regulatory Matters - Pennsylvania Activities - Public Utility Commission Investigation of Retail Electricity Market (Numeric) [Abstract]      
Number of phases of a PUC investigation of retail electricity market   2  
Regulatory Matters - Pennsylvania Activities - Distribution System Improvement Charge (Numeric) [Abstract]      
Number of ratemaking mechanisms authorized for PUC approval   2  
Minimum term for Long Term Infrastructure Improvement Plan (in years)   5  
Maximum term for Long Term Infrastructure Improvement Plan (in years)   10  
Number of issues assigned to the Office of Administrative Law Judge   4  
PPL Electric Utilities Corp [Member] | Distribution Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   71  
Return on equity used in approved rate case proceeding   10.40%  
LG And E And KU Energy LLC [Member] | LGE [Member] | Electric Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   34  
Return on equity used in approved rate case proceeding   10.25%  
LG And E And KU Energy LLC [Member] | LGE [Member] | Gas Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   15  
Return on equity used in approved rate case proceeding   10.25%  
LG And E And KU Energy LLC [Member] | KU [Member] | Electric Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   51  
Return on equity used in approved rate case proceeding   10.25%  
Louisville Gas And Electric Co [Member] | Electric Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   34  
Return on equity used in approved rate case proceeding   10.25%  
Louisville Gas And Electric Co [Member] | Gas Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   15  
Return on equity used in approved rate case proceeding   10.25%  
Kentucky Utilities Co [Member] | Electric Rates [Member]
     
Regulatory Matters - Rate Case Proceeding (Numeric) [Abstract]      
Dollar amount of increase to rates   $ 51  
Return on equity used in approved rate case proceeding   10.25%