Utility Rate Regulation (Regulatory Matters) (Details)
$ in Millions
1 Months Ended 3 Months Ended 12 Months Ended
Nov. 06, 2023
MW
Sep. 27, 2023
USD ($)
Mar. 29, 2023
USD ($)
Mar. 21, 2023
USD ($)
Feb. 03, 2023
USD ($)
Jan. 27, 2023
USD ($)
Oct. 16, 2018
Aug. 24, 2018
Dec. 31, 2023
USD ($)
Mar. 31, 2015
Dec. 31, 2023
USD ($)
Nov. 21, 2023
USD ($)
Dec. 31, 2022
USD ($)
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 $ 1,874   $ 1,874   $ 1,819
Mill Creek Unit 1                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Public Utilities, Property, Plant and Equipment, Generation or Processing                 95   95    
Public Utilities, Property, Plant and Equipment, Generation, Expected Remaining Book Value at Retirement                 83   83    
Mill Creek Unit 2                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Public Utilities, Property, Plant and Equipment, Generation or Processing                 244   244    
Public Utilities, Property, Plant and Equipment, Generation, Expected Remaining Book Value at Retirement                 160   160    
March 2023 Kentucky Wind Storms                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Amount of Regulatory Costs Not yet Approved                 74   74    
Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 97   97   118
Other [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 79   $ 79   69
PPL Electric [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Act 129 Recovery Period Under Phase IV Plan                     5 years    
PPL Electric [Member] | Pennsylvania Public Utility Commission [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Civil Penalty To Be Paid                       $ 1  
LGE [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
CPCN NGCC Combustion Turbine Facilities, Power | MW 640                        
CPCN Solar Photovoltaic Facility to be constructed, Power | MW 120                        
CPCN Solar Photovoltaic Facility to be Acquired, Power | MW 120                        
CPCN 4-Hour Battery Energy Storage Facility to be Constructed, Power | MW 125                        
Mill Creek 1 Unit, Generation Capacity, Power | MW 300                        
Mill Creek 2 Unit, Generation Capacity, Power | MW 297                        
LGE [Member] | March 2023 Kentucky Wind Storms                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Amount of Regulatory Costs Not yet Approved                 33   $ 33    
LGE [Member] | Kentucky Public Service Commission [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Return on equity                     9.35%    
LGE [Member] | Kentucky Public Service Commission [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 $ 8   $ 8    
LGE [Member] | Kentucky Public Service Commission [Member] | Environmental Cost Recovery [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Amortization period for the deferred recovery of a regulatory asset                 12 months   12 months    
KU [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
CPCN NGCC Combustion Turbine Facilities, Power | MW 621                        
CPCN Solar Photovoltaic Facility to be constructed, Power | MW 120                        
CPCN Solar Photovoltaic Facility to be Acquired, Power | MW 120                        
E. W. Brown 3 Unit, Generating Capacity, Power | MW 412                        
Ghent 2 Unit, Generation Capacity, Power | MW 486                        
KU [Member] | March 2023 Kentucky Wind Storms                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Amount of Regulatory Costs Not yet Approved                 $ 41   $ 41    
KU [Member] | Kentucky Public Service Commission [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Return on equity                     9.35%    
KU [Member] | Kentucky Public Service Commission [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 $ 11   $ 11    
KU [Member] | Kentucky Public Service Commission [Member] | Environmental Cost Recovery [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Amortization period for the deferred recovery of a regulatory asset                 12 months   12 months    
Rhode Island Energy | Federal Energy Regulatory Commission                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Initial minimum base ROE to be reset by the FERC                   11.14%      
Minimum base ROE reset by FERC                   10.57%      
New ROE proposed by NETO and approved by FERC             10.41%            
Maximum Base ROE reset by FERC                   11.74%      
Rhode Island Energy | Federal Energy Regulatory Commission | Maximum ROE authorized                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
FERC Granted ROE                     11.74%    
Rhode Island Energy | Rhode Island Public Uitilty Commsion                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Return on equity               9.275%          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Supplemental Capital Investment to spend on the FY 2024 Gas ISR Plan           $ 187              
Supplemental Capital Investment to spend on the FY 2024 Electrical ISR Plan           176              
RIPUC Approved FY 2024 Gas ISR Plan for capital investment spend     $ 163                    
2nd Supplemental Capital Investment to spend on the FY 2024 Electrical ISR Plan       $ 166                  
RIPUC approved FY 2024 Electric ISR Plan for capital investment spend     112                    
Recovery Cap on Capital Investment Related to AMF Program   $ 153                      
Supplemental Capital Investment Spend amount agreed to between RIE and RIPUC         $ 171                
Capital Investment Spend on FY 2025 Gas ISR Plan                 $ 185        
Contingency Plan Spend on FY 2025 Gas ISR Plan                 11        
Capital Investment Spend on FY 2025 Electric ISR Plan                 141        
Rhode Island Energy | Rhode Island Public Uitilty Commsion | Vegetation Management                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Capital Investment Spend on FY 2025 Electric ISR Plan                 13        
Rhode Island Energy | Rhode Island Public Uitilty Commsion | Other O&M                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Capital Investment Spend on FY 2025 Electric ISR Plan                 1        
Rhode Island Energy | Rhode Island Public Uitilty Commsion | Vegetation Management                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Supplemental Capital Investment to spend on the FY 2024 Electrical ISR Plan           14              
2nd Supplemental Capital Investment to spend on the FY 2024 Electrical ISR Plan       14                  
RIPUC approved FY 2024 Electric ISR Plan for capital investment spend     14                    
Rhode Island Energy | Rhode Island Public Uitilty Commsion | Other O&M                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Supplemental Capital Investment to spend on the FY 2024 Electrical ISR Plan           $ 3              
2nd Supplemental Capital Investment to spend on the FY 2024 Electrical ISR Plan       $ 1                  
RIPUC approved FY 2024 Electric ISR Plan for capital investment spend     $ 1                    
Rhode Island Energy | Rhode Island Public Uitilty Commsion | Common equity percentage related to approved rate                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Percentage of common equity used on allowed ROE               51.00%          
PPL Electric Utilities Corp [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Act 129 Recovery Period Under Phase IV Plan                     5 years    
Regulatory assets                 598   $ 598   568
PPL Electric Utilities Corp [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 0   0   0
PPL Electric Utilities Corp [Member] | Other [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 0   0   0
PPL Electric Utilities Corp [Member] | Pennsylvania Public Utility Commission [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Civil Penalty To Be Paid                       $ 1  
Louisville Gas And Electric Co [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
CPCN NGCC Combustion Turbine Facilities, Power | MW 640                        
CPCN Solar Photovoltaic Facility to be constructed, Power | MW 120                        
CPCN Solar Photovoltaic Facility to be Acquired, Power | MW 120                        
CPCN 4-Hour Battery Energy Storage Facility to be Constructed, Power | MW 125                        
New NGCC LG&E Planned Ownership Percentage 0.31                        
New Solar Units LG&E Planned Ownership Percentage 0.37                        
Mill Creek 1 Unit, Generation Capacity, Power | MW 300                        
Mill Creek 2 Unit, Generation Capacity, Power | MW 297                        
Regulatory assets                 395   395   373
Louisville Gas And Electric Co [Member] | March 2023 Kentucky Wind Storms                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Amount of Regulatory Costs Not yet Approved                 33   33    
Louisville Gas And Electric Co [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 15   15   7
Louisville Gas And Electric Co [Member] | Other [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 26   $ 26   14
Louisville Gas And Electric Co [Member] | Kentucky Public Service Commission [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Return on equity                     9.35%    
Louisville Gas And Electric Co [Member] | Kentucky Public Service Commission [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 $ 8   $ 8    
Louisville Gas And Electric Co [Member] | Kentucky Public Service Commission [Member] | Environmental Cost Recovery [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Amortization period for the deferred recovery of a regulatory asset                 12 months   12 months    
Kentucky Utilities Co [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
CPCN NGCC Combustion Turbine Facilities, Power | MW 621                        
CPCN Solar Photovoltaic Facility to be constructed, Power | MW 120                        
CPCN Solar Photovoltaic Facility to be Acquired, Power | MW 120                        
CPCN 4-Hour Battery Energy Storage Facility to be Constructed, Power | MW 125                        
New Solar Units LG&E Planned Ownership Percentage 0.63                        
New NGCC KU Planned Ownership Percentage 0.69                        
E. W. Brown 3 Unit, Generating Capacity, Power | MW 412                        
Ghent 2 Unit, Generation Capacity, Power | MW 486                        
Regulatory assets                 $ 439   $ 439   442
Kentucky Utilities Co [Member] | March 2023 Kentucky Wind Storms                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Amount of Regulatory Costs Not yet Approved                 41   41    
Kentucky Utilities Co [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 14   14   3
Kentucky Utilities Co [Member] | Other [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 17   $ 17   $ 13
Kentucky Utilities Co [Member] | Kentucky Public Service Commission [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Return on equity                     9.35%    
Kentucky Utilities Co [Member] | Kentucky Public Service Commission [Member] | Storm Costs [Member]                          
Regulatory Matters Federal Matters Federal Energy Regulatory Commission Wholesale Formula Rates Numeric [Abstract]                          
Regulatory assets                 $ 11   $ 11    
Kentucky Utilities Co [Member] | Kentucky Public Service Commission [Member] | Environmental Cost Recovery [Member]                          
Regulatory Matters - Kentucky Activities - Rate Case Proceedings (Numeric) [Abstract]                          
Amortization period for the deferred recovery of a regulatory asset                 12 months   12 months