XML 44 R16.htm IDEA: XBRL DOCUMENT v3.10.0.1
Utility Rate Regulation
6 Months Ended
Jun. 30, 2018
Regulated Operations [Abstract]  
Utility Rate Regulation
7. Utility Rate Regulation
 
(All Registrants)
 
The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.
 
PPL
 
PPL Electric
 
June 30,
2018
 
December 31,
2017
 
June 30,
2018
 
December 31,
2017
Current Regulatory Assets:
 
 
 
 
 
 
 
Environmental cost recovery
$

 
$
5

 
$

 
$

      Generation formula rate

 
6

 

 

Smart meter rider
15

 
15

 
15

 
15

Plant outage costs
6

 
3

 

 

Gas supply clause
5

 
4

 

 

Other
1

 
1

 
1

 
1

Total current regulatory assets (a)
$
27

 
$
34

 
$
16

 
$
16

 
 
 
 
 
 
 
 
Noncurrent Regulatory Assets:
 
 
 
 
 
 
 
Defined benefit plans
$
857

 
$
880

 
$
491

 
$
504

Taxes recoverable through future rates
3

 
3

 
3

 
3

Storm costs (b)
47

 
33

 
21

 

Unamortized loss on debt
49

 
54

 
25

 
29

Interest rate swaps
21

 
26

 

 

Terminated interest rate swaps
89

 
92

 

 

Accumulated cost of removal of utility plant
182

 
173

 
182

 
173

AROs
260

 
234

 

 

 Act 129 compliance rider
15

 

 
15

 

Other
7

 
9

 

 

Total noncurrent regulatory assets
$
1,530

 
$
1,504

 
$
737

 
$
709

 
PPL
 
PPL Electric
 
June 30,
2018
 
December 31,
2017
 
June 30,
2018
 
December 31,
2017
Current Regulatory Liabilities:
 
 
 
 
 
 
 
Generation supply charge
$
30

 
$
34

 
$
30

 
$
34

Transmission service charge
4

 
9

 
4

 
9

Environmental cost recovery
25

 
1

 

 

Universal service rider
20

 
26

 
20

 
26

Transmission formula rate
11

 
9

 
11

 
9

Fuel adjustment clause
5

 
3

 

 

TCJA customer refund (c)
33

 

 

 

Storm damage expense rider
1

 
8

 
1

 
8

Other
8

 
5

 

 

Total current regulatory liabilities
$
137

 
$
95

 
$
66

 
$
86

 
 
 
 
 
 
 
 
Noncurrent Regulatory Liabilities:
 
 
 
 
 
 
 
Accumulated cost of removal of utility plant
$
678

 
$
677

 
$

 
$

Power purchase agreement - OVEC (d)
64

 
68

 

 

Net deferred taxes (e)
1,858

 
1,853

 
652

 
668

Defined benefit plans
31

 
27

 

 

Terminated interest rate swaps
72

 
74

 

 

TCJA customer refund (f)
37

 

 
37

 

Other
7

 
5

 
3

 

Total noncurrent regulatory liabilities
$
2,747

 
$
2,704

 
$
692

 
$
668

 
LKE
 
LG&E
 
KU
 
June 30,
2018
 
December 31,
2017
 
June 30,
2018
 
December 31,
2017
 
June 30,
2018
 
December 31,
2017
Current Regulatory Assets:
 
 
 
 
 
 
 
 
 
 
 
Environmental cost recovery
$

 
$
5

 
$

 
$
5

 
$

 
$

      Generation formula rate

 
6

 

 

 

 
6

Plant outage costs
6

 
3

 
6

 
3

 

 

Gas supply clause
5

 
4

 
5

 
4

 

 

Total current regulatory assets
$
11

 
$
18

 
$
11

 
$
12

 
$

 
$
6

 
 
 
 
 
 
 
 
 
 
 
 
Noncurrent Regulatory Assets:
 
 
 
 
 
 
 
 
 
 
 
Defined benefit plans
$
366

 
$
376

 
$
231

 
$
234

 
$
135

 
$
142

Storm costs
26

 
33

 
14

 
18

 
12

 
15

Unamortized loss on debt
24

 
25

 
15

 
16

 
9

 
9

Interest rate swaps
21

 
26

 
21

 
26

 

 

Terminated interest rate swaps
89

 
92

 
52

 
54

 
37

 
38

AROs
260

 
234

 
71

 
61

 
189

 
173

Other
7

 
9

 
2

 
2

 
5

 
7

Total noncurrent regulatory assets
$
793

 
$
795

 
$
406

 
$
411

 
$
387

 
$
384

 
LKE
 
LG&E
 
KU
 
June 30,
2018
 
December 31,
2017
 
June 30,
2018
 
December 31,
2017
 
June 30,
2018
 
December 31,
2017
Current Regulatory Liabilities:
 
 
 
 
 
 
 
 
 
 
 
Environmental cost recovery
$
25

 
$
1

 
$
14

 
$

 
$
11

 
$
1

Fuel adjustment clause
5

 
3

 
1

 

 
4

 
3

Gas line tracker
2

 
3

 
2

 
3

 

 

TCJA customer refund (c)
33

 

 
15

 

 
18

 

Other
6

 
2

 
2

 

 
4

 
2

Total current regulatory liabilities
$
71

 
$
9

 
$
34

 
$
3

 
$
37

 
$
6

 
 
 
 
 
 
 
 
 
 
 
 
Noncurrent Regulatory Liabilities:
 
 
 
 
 
 
 
 
 
 
 
Accumulated cost of removal
of utility plant
$
678

 
$
677

 
$
280

 
$
282

 
$
398

 
395

Power purchase agreement - OVEC (d)
64

 
68

 
44

 
47

 
20

 
21

Net deferred taxes (e)
1,206

 
1,185

 
561

 
552

 
645

 
633

Defined benefit plans
31

 
27

 

 

 
31

 
27

Terminated interest rate swaps
72

 
74

 
36

 
37

 
36

 
37

Other
4

 
5

 
1

 
1

 
3

 
4

Total noncurrent regulatory liabilities
$
2,055

 
$
2,036

 
$
922

 
$
919

 
$
1,133

 
$
1,117

  
(a)
For PPL, these amounts are included in "Other current assets" on the Balance Sheets.
(b)
Storm costs incurred in PPL Electric's territory from a March 2018 storm will be amortized from 2019 through 2021.
(c)
Relates to estimated amounts owed to LG&E and KU customers as a result of the reduced U.S. federal corporate income tax rate as enacted by the TCJA, effective January 1, 2018. Amounts owed will be distributed through the TCJA bill credit.
(d)
This liability was recorded as an offset to an intangible asset that was recorded at fair value upon the acquisition of LKE by PPL.
(e)
Primarily relates to excess deferred taxes recorded as a result of the TCJA, which reduced the U.S. federal corporate income tax rate effective January 1, 2018, requiring deferred tax balances and the associated regulatory liabilities to be remeasured as of December 31, 2017. LG&E and KU began distributing amounts through the TCJA bill credit effective April 1, 2018.
(f)
Relates to amounts owed to PPL Electric customers as a result of the reduced U.S. federal corporate income tax rate as enacted by the TCJA, for the period of January 1, 2018 through June 30, 2018 which is not yet reflected in customer rates. The distribution method back to customers of this liability must be proposed to the PUC at the earlier of May 2021 or PPL Electric’s next rate case.

Regulatory Matters
 
Kentucky Activities
 
(PPL, LKE, LG&E and KU)

CPCN Filing

On January 10, 2018, LG&E and KU filed an application for a CPCN with the KPSC requesting approval to implement Advanced Metering Systems across their Kentucky service territories, including gas operations for LG&E. The full deployment is expected to be completed in 2021 with estimated capital costs of $155 million and $104 million for KU and LG&E electric service and $62 million for LG&E gas service. The full Advanced Metering Systems deployment is expected to result in incremental operation and maintenance costs during the deployment phase of $17 million and $11 million for KU and LG&E electric service and $3 million for LG&E gas service. A hearing on this matter was held July 24, 2018. LG&E and KU cannot predict the outcome of this proceeding.

TCJA Impact on LG&E and KU Rates

On December 21, 2017, Kentucky Industrial Utility Customers, Inc. submitted a complaint with the KPSC against LG&E and KU, as well as other utility companies in Kentucky, alleging that their respective rates would no longer be fair, just and reasonable following the enactment of the TCJA reducing the federal corporate tax rate from 35% to 21%. The complaint requested the KPSC to issue an order requiring LG&E and KU to begin deferring, as of January 1, 2018, the revenue requirement effect of all income tax expense savings resulting from the federal corporate income tax reduction, including the amortization of excess deferred income taxes by recording those savings in a regulatory liability account and establishing a process by which the federal corporate income tax savings will be passed back to customers.

On January 29, 2018, LG&E, KU, Kentucky Industrial Utility Customers, Inc. and the Office of the Attorney General reached a settlement agreement to commence returning savings related to the TCJA to their customers through their ECR, DSM and LG&E's GLT rate mechanisms beginning in March 2018 and through a new bill credit mechanism from April 1, 2018 through April 30, 2019. The estimated impact of the rate reduction represents approximately $91 million in KU electricity revenues ($70 million through the new bill credit and $21 million through existing rate mechanisms), $69 million in LG&E electricity revenues ($49 million through the new bill credit and $20 million through existing rate mechanisms) and $17 million in LG&E gas revenues (substantially all through the new bill credit) for the period January 2018 through April 2019. Ongoing tax savings are also expected to be addressed in LG&E's and KU's next Kentucky base rate case. LG&E and KU have indicated their intent to file an application for base rate changes during 2018 to be effective during spring 2019.

On March 20, 2018, the KPSC issued an order approving, with certain modifications, the settlement agreement reached between LG&E, KU, Kentucky Industrial Utility Customers, Inc. and the Office of the Attorney General. The KPSC estimates that, pursuant to its modifications, electricity revenues would incorporate reductions of approximately $108 million for KU ($87 million through the new bill credit and $21 million through existing rate mechanisms) and $79 million for LG&E ($59 million through the new bill credit and $20 million through existing rate mechanisms). This represents $27 million ($17 million at KU and $10 million at LG&E) in additional reductions from the amounts proposed by the settlement. The KPSC's modifications to the settlement include certain changes in assumptions or inputs used in assessing tax reform or calculating LG&E's and KU's electricity rates. LG&E gas rate reductions were not modified significantly from the amount included in the settlement agreement.

On March 26, 2018, LG&E and KU filed a petition for reconsideration and request for hearing with the KPSC, taking exception to the KPSC's modifications and the process, and also requested certain relief from implementing the amounts represented by the additional reductions until the matter is fully resolved. On March 28, 2018, the Office of the Attorney General filed a response to the petition and gave notice of its withdrawal from the settlement agreement.

On March 28, 2018, the KPSC issued an Order granting LG&E's and KU's request for reconsideration and amending its March 20, 2018 Order by suspending the approved rates, allowing LG&E and KU, on an interim basis, to return savings related to the TCJA at the rates agreed to in the January 29, 2018 settlement. On March 30, 2018, following receipt of the Attorney General's response, the KPSC issued an Order amending its March 28, 2018 Order to allow the parties to raise any relevant issues related to the TCJA. A hearing on this matter was held May 24, 2018. Post-hearing briefs have been filed and the case is now submitted to the KPSC for a decision.

LG&E and KU cannot predict the outcome of these proceedings.

Additionally, on January 8, 2018, the VSCC ordered KU, as well as other utilities in Virginia, to accrue regulatory liabilities reflecting the Virginia jurisdictional revenue requirement impacts of the reduced federal corporate tax rate. On March 22, 2018, KU reached a settlement agreement regarding its rate case in Virginia. New rates, inclusive of TCJA impacts, were effective June 1, 2018. The settlement also stipulates that actual tax savings for the five month period prior to new rates taking effect would be addressed through KU's annual information filing for calendar year 2018. On May 8, 2018, the VSCC approved the settlement agreement. The TCJA and rate case are not expected to have a significant impact on KU's financial condition or results of operations related to Virginia.

On March 15, 2018, the FERC issued a Notice of Inquiry seeking information on whether and how it should address changes relating to accumulated deferred income taxes and bonus depreciation resulting from passage of the TCJA on FERC-jurisdictional rates. LG&E and KU have not made any submission in response to the Notice of Inquiry, but do not anticipate the impact of the TCJA related to their FERC-jurisdictional rates to be significant. 

Gas Franchise (LKE and LG&E)
 
LG&E’s gas franchise agreement for the Louisville/Jefferson County service area expired in March 2016. In August 2016, LG&E and Louisville/Jefferson County entered into a revised franchise agreement with a 5-year term (with renewal options). The franchise fee may be modified at Louisville/Jefferson County's election upon 60 days' notice. However, any franchise fee is capped at 3% of gross receipts for natural gas service within the franchise area. The agreement further provides that if the KPSC determines that the franchise fee should be recovered from LG&E's Louisville/Jefferson county customers in the franchise areas as a separate line item on their bill, the franchise fee will revert to zero. In August 2016, LG&E filed an application requesting the KPSC to review and rule upon the recoverability of the franchise fee.

On March 14, 2018, the KPSC issued an order authorizing the franchise fee to be recovered only from LG&E's Louisville/Jefferson County customers in the franchise area. As a result, the franchise fee will continue to be zero in accordance with the terms of the August 2016, 5-year gas franchise agreement.

(PPL and PPL Electric)

Pennsylvania Activities

TCJA Impact on PPL Electric Rates

On February 12, 2018, the PUC issued a Secretarial Letter requesting certain information from regulated utilities and inviting comment from interested parties on potential revision to customer rates as a result of enactment of the TCJA. PPL Electric submitted its response to the Secretarial Letter on March 9, 2018. On March 15, 2018, the PUC issued a Temporary Rates Order to allow time to determine the manner in which rates could be adjusted in response to the TCJA. The PUC issued another Temporary Rates Order on May 17, 2018 to address the impact of the TCJA and indicated that utilities without a currently pending general rate proceeding would receive a utility specific order. The PUC issued an Order specific to PPL Electric on May 17, 2018 which required PPL Electric to file a tariff or tariff supplement by June 15, 2018 to establish (a) temporary rates to include a negative surcharge of 0.56%, which was based on PPL Electric's 2017 taxable income, to be effective July 1, 2018, and (b) to record a deferred regulatory liability to reflect the tax savings associated with the TCJA for the period January 1 through June 30, 2018. On June 8, 2018, PPL Electric submitted a petition to the PUC to increase the negative surcharge proposed in the May 17, 2018 Order from 0.56% to 7.05% to reflect the estimated 2018 tax savings associated with the TCJA. The PUC approved PPL Electric's petition on June 14, 2018 and PPL Electric filed a tariff on June 15, 2018 reflecting the increased negative surcharge. The estimated 2018 full year impact of the rate reduction is $72 million in PPL Electric's operating revenues of which $37 million relates to the period January 1, 2018 through June 30, 2018 and has been recorded as a noncurrent regulatory liability to be distributed to customers pursuant to a future rate adjustment. The remaining $35 million is the estimated impact for the period July 1, 2018 through December 31, 2018 and will be passed back to customers through the negative surcharge beginning July 1, 2018.

On March 15, 2018, the FERC issued a Notice of Inquiry seeking information on whether and how it should address changes to FERC-jurisdictional rates relating to accumulated deferred income taxes and bonus depreciation resulting from passage of the TCJA. On March 16, 2018, PPL Electric filed a waiver request, pursuant to Rule 207(a)(5) of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission, to accelerate incorporation of the changes to the federal corporate income tax rate in its transmission formula rate commencing on June 1, 2018 rather than allowing the TCJA tax rate reduction to be initially incorporated in PPL Electric's June 1, 2019 transmission formula rate. The waiver was approved on April 23, 2018 and PPL Electric submitted its transmission formula rate, reflecting the TCJA rate reduction, on April 27, 2018. In addition, on May 21, 2018, PPL Electric, as part of a PJM joint transmission owners filing, submitted comments in response to the FERC's March 15, 2018 Notice of Inquiry. The filing submitted by the PJM joint transmission owners requested guidance on how the reduction in accumulated deferred income taxes, resulting from the TCJA reduced federal corporate income tax rate, should be treated for ratemaking purposes. PPL Electric is currently awaiting FERC's decision on this matter. The changes, related to accumulated deferred income taxes impacting the transmission formula rate revenues, have not been significant since the new rate went into effect on June 1, 2018.

Federal Matters

(PPL, LKE, LG&E and KU)

FERC Transmission Rate Filing

On August 3, 2018, LG&E and KU submitted an application to the FERC requesting elimination of certain on-going credits to a sub-set of transmission customers relating to the 1998 merger of LG&E’s and KU’s parent entities and the 2006 withdrawal of LG&E and KU from the Midcontinent Independent System Operator, Inc. (“MISO”), a regional transmission operator and energy market. The application seeks termination of LG&E’s and KU’s commitment to provide mitigation for certain horizontal market power concerns arising out of the 1998 merger for certain transmission service between MISO and LG&E and KU. The affected transmission customers are a limited number of municipal entities in Kentucky or Tennessee. The amounts at issue are generally waivers or credits for either LG&E and KU or for MISO transmission charges depending upon the direction of transmission service incurred by the municipalities. LG&E and KU estimate that such charges may average approximately $22 million annually, depending upon actual transmission customer and market volumes, structures and prices, with such charges allocated according to LG&E and KU’s respective transmission system ownership ratio. Due to the development of robust, accessible energy markets over time, LG&E and KU believe the mitigation commitments are no longer relevant or appropriate. LG&E and KU currently receive recovery of such expenses in other rate mechanisms. LG&E and KU cannot predict the outcome of the proceeding, including any effects on their financial condition or results of operations.

Other

Purchase of Receivables Program

(PPL and PPL Electric)
 
In accordance with a PUC-approved purchase of accounts receivable program, PPL Electric purchases certain accounts receivable from alternative electricity suppliers at a discount, which reflects a provision for uncollectible accounts. The alternative electricity suppliers have no continuing involvement or interest in the purchased accounts receivable. Accounts receivable that are acquired are initially recorded at fair value on the date of acquisition. During the three and six months ended June 30, 2018, PPL Electric purchased $297 million and $673 million of accounts receivable from alternate suppliers. During the three and six months ended June 30, 2017, PPL Electric purchased $288 million and $644 million of accounts receivable from alternate suppliers.