XML 44 R17.htm IDEA: XBRL DOCUMENT v3.4.0.3
Acquisitions, Development and Divestitures
3 Months Ended
Mar. 31, 2016
Acquisitions Development And Divestitures [Abstract]  
Acquisitions, Development and Divestitures

8. Acquisitions, Development and Divestitures

(All Registrants)

The Registrants from time to time evaluate opportunities for potential acquisitions, divestitures and development projects. Development projects are reexamined based on market conditions and other factors to determine whether to proceed with, modify or terminate the projects. Any resulting transactions may impact future financial results. See Note 8 in the Registrants' 2015 Form 10-K for additional information.

(PPL)

Discontinued Operations

Spinoff of PPL Energy Supply

In June 2015, PPL and PPL Energy Supply completed the spinoff of PPL Energy Supply which combined its competitive power generation businesses with those of Riverstone to form a new, stand-alone, publicly traded company named Talen Energy.

Following completion of the spinoff, PPL shareowners owned 65% of Talen Energy and affiliates of Riverstone owned 35%. The spinoff had no effect on the number of PPL common shares owned by PPL shareowners or the number of shares of PPL common stock outstanding. The transaction is intended to be tax-free to PPL and its shareowners for U.S. federal income tax purposes.

PPL has no continuing ownership interest in or control of Talen Energy and Talen Energy Supply (formerly PPL Energy Supply). See Note 8 in PPL's 2015 Form 10-K for additional information.

Continuing Involvement (PPL and PPL Electric)

As a result of the spinoff, PPL and PPL Energy Supply entered into a Transition Services Agreement (TSA) that terminates no later than two years after the spinoff. Pursuant to the TSA, PPL is providing Talen Energy certain information technology, financial and accounting, human resource and other specified services. For the three months ended March 31, 2016, the amounts PPL billed Talen Energy for these services were $10 million. In general, the fees for the transition services allow the provider to recover its cost of the services, including overheads, but without margin or profit.

Additionally, prior to the spinoff, through the annual competitive solicitation process, PPL EnergyPlus was awarded supply contracts for a portion of the PLR generation supply for PPL Electric, which were retained by Talen Energy Marketing as part of the spinoff. PPL Electric's supply contracts with Talen Energy Marketing extend through November 2016. Energy purchases from PPL EnergyPlus were previously included in PPL Electric's Statements of Income as "Energy purchases from affiliate" but were eliminated in PPL’s Consolidated Statements of Income.

For the three months ended March 31, 2016, PPL Electric’s energy purchases from Talen Energy Marketing were $54 million and are no longer considered affiliate transactions.

Summarized Results of Discontinued Operations (PPL)

The operations of the Supply segment prior to the spinoff on June 1, 2015 are included in “Income (Loss) from Discontinued Operations (net of income taxes)” on the Statements of Income. Following are the components of Discontinued Operations in the Statement of Income for the period ended March 31, 2015:

Operating revenues$944
Operating expenses767
Other Income (Expense) - net7
Interest expense (a)38
Income (loss) before income taxes146
Income tax expense (benefit)51
Income (Loss) from Discontinued Operations (net of income taxes)$95

(a) Includes interest associated with the Supply Segment with no additional allocation as the Supply segment was sufficiently capitalized.

Development

Regional Transmission Line Expansion Plan (PPL and PPL Electric)

Northeast/Pocono

In October 2012, the FERC issued an order in response to PPL Electric's December 2011 request for ratemaking incentives for the Northeast/Pocono Reliability project (a new 58-mile, 230 kV transmission line that includes three new substations and upgrades to adjacent facilities). The FERC granted the incentive for inclusion in rate base of all prudently incurred construction work in progress costs but denied the requested incentive for a 100 basis point adder to the return on equity.

In December 2012, PPL Electric submitted an application to the PUC requesting permission to site and construct the project. In January 2014, the PUC issued a Final Order approving the application. The line was energized in April 2016, completing the $350 million project which includes additional substation security enhancements. Costs related to the project were capitalized and are included on the Balance Sheets, primarily in "Regulated utility plant."