XML 95 R15.htm IDEA: XBRL DOCUMENT v2.4.0.6
Utility Rate Regulation
3 Months Ended
Mar. 31, 2013
Utility Rate Regulation [Line Items]  
Utility Rate Regulation

6. Utility Rate Regulation

 

(PPL, PPL Electric, LKE, LG&E and KU)

 

The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.

   PPL PPL Electric
   March 31, December 31, March 31, December 31,
   2013 2012 2013 2012
              
Current Regulatory Assets:            
 Transmission formula rate $ 5    $ 5   
 Gas supply clause   12 $ 11      
 Fuel adjustment clause   14   6      
 Other    6   2      
Total current regulatory assets $ 37 $ 19 $ 5   
              
Noncurrent Regulatory Assets:            
 Defined benefit plans $ 714 $ 730 $ 356 $ 362
 Taxes recoverable through future rates   295   293   295   293
 Storm costs   163   168   58   59
 Unamortized loss on debt   94   96   63   65
 Interest rate swaps   62   67      
 Accumulated cost of removal of utility plant    85   71   85   71
 AROs   30   26      
 Other    21   32   3   3
Total noncurrent regulatory assets $ 1,464 $ 1,483 $ 860 $ 853

Current Regulatory Liabilities:            
 Generation supply charge  $ 28 $ 27 $ 28 $ 27
 ECR      4      
 Gas supply clause   1   4      
 Transmission service charge   12   6   12   6
 Universal service rider   15   17   15   17
 Other    5   3   2   2
Total current regulatory liabilities $ 61 $ 61 $ 57 $ 52
              
Noncurrent Regulatory Liabilities:            
 Accumulated cost of removal of utility plant $ 687 $ 679      
 Coal contracts (a)   130   141      
 Power purchase agreement - OVEC (a)   107   108      
 Net deferred tax assets   33   34      
 Act 129 compliance rider   13   8 $ 13 $ 8
 Defined benefit plans   17   17      
 Interest rate swaps   24   14      
 Other    5   9      
Total noncurrent regulatory liabilities $ 1,016 $ 1,010 $ 13 $ 8

   LKE LG&E KU
   March 31, December 31, March 31, December 31, March 31, December 31,
   2013 2012 2013 2012 2013 2012
                    
Current Regulatory Assets:                  
 Gas supply clause $ 12 $ 11 $ 12 $ 11      
 Fuel adjustment clause   14   6   7   6 $ 7   
 Other    6   2   2   2   4   
Total current regulatory assets $ 32 $ 19 $ 21 $ 19 $ 11   
                    
Noncurrent Regulatory Assets:                  
 Defined benefit plans $ 358 $ 368 $ 225 $ 232 $ 133 $ 136
 Storm costs   105   109   57   59   48   50
 Unamortized loss on debt    31   31   20   20   11   11
 Interest rate swaps   62   67   62   67      
 AROs   30   26   17   15   13   11
 Other    18   29   7   7   11   22
Total noncurrent regulatory assets $ 604 $ 630 $ 388 $ 400 $ 216 $ 230

Current Regulatory Liabilities:                  
  ECR    $ 4          $ 4
  DSM $ 1          $ 1   
  Gas supply clause   1   4 $ 1 $ 4      
  Gas line tracker   2      2         
  Other       1            1
Total current regulatory liabilities $ 4 $ 9 $ 3 $ 4 $ 1 $ 5
                     
Noncurrent Regulatory Liabilities:                  
 Accumulated cost of removal                  
  of utility plant $ 687 $ 679 $ 299 $ 297 $ 388 $ 382
 Coal contracts (a)   130   141   57   61   73   80
 Power purchase agreement - OVEC (a)   107   108   74   75   33   33
 Net deferred tax assets   33   34   27   28   6   6
 Defined benefit plans   17   17         17   17
 Interest rate swaps   24   14   12   7   12   7
 Other    5   9   2   3   3   6
Total noncurrent regulatory liabilities $ 1,003 $ 1,002 $ 471 $ 471 $ 532 $ 531

(a)       Recorded as offsets to certain intangible assets that were recorded at fair value upon the acquisition of LKE.

Regulatory Matters

 

Kentucky Activities (PPL, LKE, LG&E and KU)

 

Rate Case Proceedings

 

In December 2012, the KPSC approved a rate case settlement agreement providing for increases in annual base electricity rates of $34 million for LG&E and $51 million for KU and an increase in annual base gas rates of $15 million for LG&E using a 10.25% return on equity. The approved rates became effective January 1, 2013.

Pennsylvania Activities (PPL and PPL Electric)

 

Rate Case Proceeding

 

In December 2012, the PUC approved a total distribution revenue increase of about $71 million, using a 10.4% return on equity. The approved rates became effective January 1, 2013.

 

Storm Damage Expense Rider

 

In its December 28, 2012 final rate case proceeding order, the PUC directed PPL Electric to file a proposed Storm Damage Expense Rider within 90 days following the order. PPL Electric filed its proposed Storm Damage Expense Rider with the PUC on March 28, 2013, including requested recovery of the 2012 qualifying storm costs related to Hurricane Sandy which were previously approved by the PUC for deferral. PPL Electric proposed that the Storm Damage Expense Rider become effective on January 1, 2013 for storm costs incurred in 2013, with those costs and the 2012 Hurricane Sandy costs included in rates effective on January 1, 2014. Several parties have filed comments opposing the Storm Damage Expense Rider. PPL Electric will file reply comments by May 6, 2013.

 

ACT 129

 

Act 129 requires Pennsylvania Electric Distribution Companies (EDCs) to meet specified goals for reduction in customer electricity usage and peak demand by specified dates. EDCs not meeting the requirements of Act 129 are exposed to significant penalties.

 

Under Act 129, EDCs must file an energy efficiency and conservation plan (EE&C Plan) with the PUC and contract with conservation service providers to implement all or a portion of the EE&C Plan. Act 129 requires EDCs to reduce overall electricity consumption by 1.0% by May 2011 and, by May 2013, reduce overall electricity consumption by 3.0% and reduce peak demand by 4.5%. Although PPL Electric believes it has met the May 2011 requirement, the PUC is not expected formally to determine compliance for any EDC before the first quarter of 2014. The peak demand reduction must occur for the 100 hours of highest demand, which is determined by actual demand reduction during the June 2012 through September 2012 period. EDCs are able to recover the costs (capped at 2.0% of the EDC's 2006 revenue) of implementing their EE&C Plans. In October 2009, the PUC approved PPL Electric's EE&C Plan. PPL Electric will determine if it met the peak demand reduction target and the May 2013 energy reduction target after it completes the final program evaluation in the fourth quarter of 2013.

Act 129 requires the PUC to evaluate the costs and benefits of the EE&C program by November 30, 2013 and adopt additional reductions if the benefits of the program exceed the costs. In August 2012, after receiving input from stakeholders, the PUC issued a Final Implementation Order establishing a three-year Phase II program, ending May 31, 2016, with individual consumption reduction targets for each EDC. PPL Electric's Phase II reduction target is 2.1% of the total energy consumption forecasted by the PUC for the June 1, 2009 through May 31, 2010 baseline year. The PUC did not establish demand reduction targets for the Phase II program. PPL Electric filed its Phase II EE&C Plan with the PUC on November 15, 2012 and the PUC issued its decision in March 2013, approving PPL Electric's Phase II program with minor modifications to a related tariff provision.

 

Act 129 also requires the Default Service Provider (DSP) to provide electric generation supply service to customers pursuant to a PUC-approved default service procurement plan through auctions, requests for proposal and bilateral contracts at the sole discretion of the DSP. Act 129 requires a mix of spot market purchases, short-term contracts and long-term contracts (4 to 20 years), with long-term contracts limited to 25% of load unless otherwise approved by the PUC. The DSP will be able to recover the costs associated with a competitive procurement plan.

 

The PUC has approved PPL Electric's procurement plan for the period January 1, 2011 through May 31, 2013, and PPL Electric concluded all competitive solicitations to procure power for its PLR obligations under that plan.

 

The PUC has directed all EDCs to file default service procurement plans for the period June 1, 2013 through May 31, 2015. PPL Electric filed its plan in May 2012. In that plan, PPL Electric proposed a process to obtain supply for its default service customers and a number of initiatives designed to encourage more customers to purchase electricity from the competitive retail market. In its January 24, 2013 final order, the PUC approved PPL Electric's plan with modifications and directed PPL Electric to establish collaborative processes to address several retail competition issues. In February 2013, PPL Electric filed a revised Default Service Supply Master Agreement and a revised Request for Proposals Process and Rules which the PUC approved. PPL Electric has filed revised retail competition initiatives and a revised plan consistent with the PUC's January order. These filings remain pending before the PUC. See Note 10 for additional information.

 

Smart Meter Rider

 

Act 129 also requires installation of smart meters for new construction, upon the request of consumers and at their cost, or on a depreciation schedule not exceeding 15 years. Under Act 129, EDCs are able to recover the costs of providing smart metering technology. All of PPL Electric's metered customers currently have advanced meters installed at their service locations capable of many of the functions required under Act 129. PPL Electric continues to conduct pilot projects to determine if its current advanced metering technology satisfies the requirements of Act 129. PPL Electric recovers the cost of its pilot projects through a cost recovery mechanism, the Smart Meter Rider (SMR). In August 2012, PPL Electric filed with the PUC an annual report describing the actions it was taking under its Smart Meter Plan in 2012 and its planned actions for 2013. PPL Electric also submitted revised SMR charges which became effective January 1, 2013. PPL Electric will submit its final Smart Meter Plan by June 30, 2014.

 

PUC Investigation of Retail Electricity Market

 

In April 2011, the PUC opened an investigation of Pennsylvania's retail electricity market to be conducted in two phases. Phase one addressed the status of the existing retail market and explored potential changes. Questions issued by the PUC for phase one of the investigation focused primarily on default service issues. Phase two was initiated in July 2011 to develop specific proposals for changes to the retail market and default service model. From December 2011 through the end of 2012, the PUC issued several orders and other pronouncements related to the investigation. A final implementation order was issued on February 15, 2013. Although the final implementation order contains provisions that will require numerous modifications to PPL Electric's current default service model for retail customers, those modifications are not expected to have a material adverse effect on PPL Electric's results of operations.

 

Legislation - Regulatory Procedures and Mechanisms

 

Act 11 authorizes the PUC to approve two specific ratemaking mechanisms - the use of a fully projected future test year in base rate proceedings and, subject to certain conditions, the use of a DSIC. Such alternative ratemaking procedures and mechanisms provide opportunity for accelerated cost-recovery and, therefore, are important to PPL Electric as it begins a period of significant capital investment to maintain and enhance the reliability of its delivery system, including the replacement of aging distribution assets. In August 2012, the PUC issued a Final Implementation Order adopting procedures, guidelines and a model tariff for the implementation of Act 11. Act 11 requires utilities to file an LTIIP as a prerequisite to filing for recovery through the DSIC. The LTIIP is mandated to be a five- to ten-year plan describing projects eligible for inclusion in the DSIC. In September 2012, PPL Electric filed its LTIIP describing projects eligible for inclusion in the DSIC.

 

The PUC approved the LTIIP on January 10, 2013 and, on January 15, 2013, PPL Electric filed a petition requesting permission to establish a DSIC. Several parties have filed responses to PPL Electric's petition. The case remains pending before the PUC. PPL Electric does not expect any new rates to be effective before the third quarter of 2013.

 

Federal Matters

 

FERC Formula Rates (PPL and PPL Electric)

 

Transmission rates are regulated by the FERC. PPL Electric's transmission revenues are billed in accordance with a FERC-approved PJM open access transmission tariff that utilizes a formula-based rate recovery mechanism. The formula rate is calculated, in part, based on financial results as reported in PPL Electric's annual FERC Form No. 1, filed under FERC's Uniform System of Accounts (USOA). PPL Electric must follow FERC's USOA, which requires subsidiaries to be presented, for FERC reporting purposes, using the equity method of accounting unless a waiver has been issued. The FERC has granted waivers of this requirement to other utilities when such waiver would more accurately present the integrated operations of the utilities and their subsidiaries. In March 2013, as part of a routine FERC audit of PPL and its subsidiaries, PPL Electric determined that it never obtained a waiver of the use of the equity method of accounting for PPL Receivables Corporation (PPL Receivables). PPL Receivables is a wholly owned subsidiary of PPL Electric, formed in 2004 to purchase eligible accounts receivable and unbilled revenue of PPL Electric to collateralize commercial paper issuances to reduce borrowing costs. In March 2013, PPL Electric filed a request for waiver with FERC that, if approved, would allow it to continue to consolidate the results of PPL Receivables with the results of PPL Electric, as it has done since 2004. While PPL Electric may ultimately be successful in obtaining a waiver from FERC, FERC may require PPL Electric to re-issue one or more of its prior FERC Form No. 1 filings in either the audit proceeding or the waiver proceeding. If re-issuance of FERC Form No. 1 filings were required by FERC, PPL Electric's revenue requirement calculated under the formula rate could be negatively impacted. The impact, if any, is not known at this time but could range between $0 and $40 million, pre-tax. PPL Electric cannot predict the outcome of the waiver or audit proceedings, which remain pending before the FERC.

 

PPL Electric has initiated its formula rate 2012, 2011 and 2010 Annual Updates. Each update has been subsequently challenged by a group of municipal customers, which challenges have been opposed by PPL Electric. In August 2011, the FERC issued an order substantially rejecting the 2010 formal challenge and the municipal customers filed a request for rehearing of that order. In September 2012, the FERC issued an order setting for evidentiary hearings and settlement judge procedures a number of issues raised in the 2010 and 2011 formal challenges. Settlement conferences were held in late 2012 and early 2013. In February 2013, the FERC set for evidentiary hearings and settlement judge procedures a number of issues in the 2012 formal challenge and consolidated that challenge with the 2010 and 2011 challenges. PPL Electric filed a request for rehearing of the February Order which remains pending before the FERC. PPL Electric anticipates that there will be additional settlement conferences held in 2013. Several of the municipal customers have filed Notice of Withdrawal of Intervention. PPL and PPL Electric cannot predict the outcome of the foregoing proceedings, which remain pending before the FERC.

U.K. Activities (PPL)

 

Ofgem Review of Line Loss Calculation

 

Ofgem is currently consulting on the methodology to be used by all network operators to calculate the final line loss incentive/penalty for the DPCR4. In April 2013, Ofgem stated that their current expectation was to issue a decision in the second half of 2013. PPL cannot predict when this matter will be resolved. WPD had an $89 million liability recorded at March 31, 2013 compared with $94 million at December 31, 2012, related to the close-out of line losses for the DPCR4, with the change due to foreign exchange movements.

PPL Electric Utilities Corp [Member]
 
Utility Rate Regulation [Line Items]  
Utility Rate Regulation

6. Utility Rate Regulation

 

(PPL, PPL Electric, LKE, LG&E and KU)

 

The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.

   PPL PPL Electric
   March 31, December 31, March 31, December 31,
   2013 2012 2013 2012
              
Current Regulatory Assets:            
 Transmission formula rate $ 5    $ 5   
 Gas supply clause   12 $ 11      
 Fuel adjustment clause   14   6      
 Other    6   2      
Total current regulatory assets $ 37 $ 19 $ 5   
              
Noncurrent Regulatory Assets:            
 Defined benefit plans $ 714 $ 730 $ 356 $ 362
 Taxes recoverable through future rates   295   293   295   293
 Storm costs   163   168   58   59
 Unamortized loss on debt   94   96   63   65
 Interest rate swaps   62   67      
 Accumulated cost of removal of utility plant    85   71   85   71
 AROs   30   26      
 Other    21   32   3   3
Total noncurrent regulatory assets $ 1,464 $ 1,483 $ 860 $ 853

Current Regulatory Liabilities:            
 Generation supply charge  $ 28 $ 27 $ 28 $ 27
 ECR      4      
 Gas supply clause   1   4      
 Transmission service charge   12   6   12   6
 Universal service rider   15   17   15   17
 Other    5   3   2   2
Total current regulatory liabilities $ 61 $ 61 $ 57 $ 52
              
Noncurrent Regulatory Liabilities:            
 Accumulated cost of removal of utility plant $ 687 $ 679      
 Coal contracts (a)   130   141      
 Power purchase agreement - OVEC (a)   107   108      
 Net deferred tax assets   33   34      
 Act 129 compliance rider   13   8 $ 13 $ 8
 Defined benefit plans   17   17      
 Interest rate swaps   24   14      
 Other    5   9      
Total noncurrent regulatory liabilities $ 1,016 $ 1,010 $ 13 $ 8

   LKE LG&E KU
   March 31, December 31, March 31, December 31, March 31, December 31,
   2013 2012 2013 2012 2013 2012
                    
Current Regulatory Assets:                  
 Gas supply clause $ 12 $ 11 $ 12 $ 11      
 Fuel adjustment clause   14   6   7   6 $ 7   
 Other    6   2   2   2   4   
Total current regulatory assets $ 32 $ 19 $ 21 $ 19 $ 11   
                    
Noncurrent Regulatory Assets:                  
 Defined benefit plans $ 358 $ 368 $ 225 $ 232 $ 133 $ 136
 Storm costs   105   109   57   59   48   50
 Unamortized loss on debt    31   31   20   20   11   11
 Interest rate swaps   62   67   62   67      
 AROs   30   26   17   15   13   11
 Other    18   29   7   7   11   22
Total noncurrent regulatory assets $ 604 $ 630 $ 388 $ 400 $ 216 $ 230

Current Regulatory Liabilities:                  
  ECR    $ 4          $ 4
  DSM $ 1          $ 1   
  Gas supply clause   1   4 $ 1 $ 4      
  Gas line tracker   2      2         
  Other       1            1
Total current regulatory liabilities $ 4 $ 9 $ 3 $ 4 $ 1 $ 5
                     
Noncurrent Regulatory Liabilities:                  
 Accumulated cost of removal                  
  of utility plant $ 687 $ 679 $ 299 $ 297 $ 388 $ 382
 Coal contracts (a)   130   141   57   61   73   80
 Power purchase agreement - OVEC (a)   107   108   74   75   33   33
 Net deferred tax assets   33   34   27   28   6   6
 Defined benefit plans   17   17         17   17
 Interest rate swaps   24   14   12   7   12   7
 Other    5   9   2   3   3   6
Total noncurrent regulatory liabilities $ 1,003 $ 1,002 $ 471 $ 471 $ 532 $ 531

(a)       Recorded as offsets to certain intangible assets that were recorded at fair value upon the acquisition of LKE.

Regulatory Matters

 

Kentucky Activities (PPL, LKE, LG&E and KU)

 

Rate Case Proceedings

 

In December 2012, the KPSC approved a rate case settlement agreement providing for increases in annual base electricity rates of $34 million for LG&E and $51 million for KU and an increase in annual base gas rates of $15 million for LG&E using a 10.25% return on equity. The approved rates became effective January 1, 2013.

Pennsylvania Activities (PPL and PPL Electric)

 

Rate Case Proceeding

 

In December 2012, the PUC approved a total distribution revenue increase of about $71 million, using a 10.4% return on equity. The approved rates became effective January 1, 2013.

 

Storm Damage Expense Rider

 

In its December 28, 2012 final rate case proceeding order, the PUC directed PPL Electric to file a proposed Storm Damage Expense Rider within 90 days following the order. PPL Electric filed its proposed Storm Damage Expense Rider with the PUC on March 28, 2013, including requested recovery of the 2012 qualifying storm costs related to Hurricane Sandy which were previously approved by the PUC for deferral. PPL Electric proposed that the Storm Damage Expense Rider become effective on January 1, 2013 for storm costs incurred in 2013, with those costs and the 2012 Hurricane Sandy costs included in rates effective on January 1, 2014. Several parties have filed comments opposing the Storm Damage Expense Rider. PPL Electric will file reply comments by May 6, 2013.

 

ACT 129

 

Act 129 requires Pennsylvania Electric Distribution Companies (EDCs) to meet specified goals for reduction in customer electricity usage and peak demand by specified dates. EDCs not meeting the requirements of Act 129 are exposed to significant penalties.

 

Under Act 129, EDCs must file an energy efficiency and conservation plan (EE&C Plan) with the PUC and contract with conservation service providers to implement all or a portion of the EE&C Plan. Act 129 requires EDCs to reduce overall electricity consumption by 1.0% by May 2011 and, by May 2013, reduce overall electricity consumption by 3.0% and reduce peak demand by 4.5%. Although PPL Electric believes it has met the May 2011 requirement, the PUC is not expected formally to determine compliance for any EDC before the first quarter of 2014. The peak demand reduction must occur for the 100 hours of highest demand, which is determined by actual demand reduction during the June 2012 through September 2012 period. EDCs are able to recover the costs (capped at 2.0% of the EDC's 2006 revenue) of implementing their EE&C Plans. In October 2009, the PUC approved PPL Electric's EE&C Plan. PPL Electric will determine if it met the peak demand reduction target and the May 2013 energy reduction target after it completes the final program evaluation in the fourth quarter of 2013.

Act 129 requires the PUC to evaluate the costs and benefits of the EE&C program by November 30, 2013 and adopt additional reductions if the benefits of the program exceed the costs. In August 2012, after receiving input from stakeholders, the PUC issued a Final Implementation Order establishing a three-year Phase II program, ending May 31, 2016, with individual consumption reduction targets for each EDC. PPL Electric's Phase II reduction target is 2.1% of the total energy consumption forecasted by the PUC for the June 1, 2009 through May 31, 2010 baseline year. The PUC did not establish demand reduction targets for the Phase II program. PPL Electric filed its Phase II EE&C Plan with the PUC on November 15, 2012 and the PUC issued its decision in March 2013, approving PPL Electric's Phase II program with minor modifications to a related tariff provision.

 

Act 129 also requires the Default Service Provider (DSP) to provide electric generation supply service to customers pursuant to a PUC-approved default service procurement plan through auctions, requests for proposal and bilateral contracts at the sole discretion of the DSP. Act 129 requires a mix of spot market purchases, short-term contracts and long-term contracts (4 to 20 years), with long-term contracts limited to 25% of load unless otherwise approved by the PUC. The DSP will be able to recover the costs associated with a competitive procurement plan.

 

The PUC has approved PPL Electric's procurement plan for the period January 1, 2011 through May 31, 2013, and PPL Electric concluded all competitive solicitations to procure power for its PLR obligations under that plan.

 

The PUC has directed all EDCs to file default service procurement plans for the period June 1, 2013 through May 31, 2015. PPL Electric filed its plan in May 2012. In that plan, PPL Electric proposed a process to obtain supply for its default service customers and a number of initiatives designed to encourage more customers to purchase electricity from the competitive retail market. In its January 24, 2013 final order, the PUC approved PPL Electric's plan with modifications and directed PPL Electric to establish collaborative processes to address several retail competition issues. In February 2013, PPL Electric filed a revised Default Service Supply Master Agreement and a revised Request for Proposals Process and Rules which the PUC approved. PPL Electric has filed revised retail competition initiatives and a revised plan consistent with the PUC's January order. These filings remain pending before the PUC. See Note 10 for additional information.

 

Smart Meter Rider

 

Act 129 also requires installation of smart meters for new construction, upon the request of consumers and at their cost, or on a depreciation schedule not exceeding 15 years. Under Act 129, EDCs are able to recover the costs of providing smart metering technology. All of PPL Electric's metered customers currently have advanced meters installed at their service locations capable of many of the functions required under Act 129. PPL Electric continues to conduct pilot projects to determine if its current advanced metering technology satisfies the requirements of Act 129. PPL Electric recovers the cost of its pilot projects through a cost recovery mechanism, the Smart Meter Rider (SMR). In August 2012, PPL Electric filed with the PUC an annual report describing the actions it was taking under its Smart Meter Plan in 2012 and its planned actions for 2013. PPL Electric also submitted revised SMR charges which became effective January 1, 2013. PPL Electric will submit its final Smart Meter Plan by June 30, 2014.

 

PUC Investigation of Retail Electricity Market

 

In April 2011, the PUC opened an investigation of Pennsylvania's retail electricity market to be conducted in two phases. Phase one addressed the status of the existing retail market and explored potential changes. Questions issued by the PUC for phase one of the investigation focused primarily on default service issues. Phase two was initiated in July 2011 to develop specific proposals for changes to the retail market and default service model. From December 2011 through the end of 2012, the PUC issued several orders and other pronouncements related to the investigation. A final implementation order was issued on February 15, 2013. Although the final implementation order contains provisions that will require numerous modifications to PPL Electric's current default service model for retail customers, those modifications are not expected to have a material adverse effect on PPL Electric's results of operations.

 

Legislation - Regulatory Procedures and Mechanisms

 

Act 11 authorizes the PUC to approve two specific ratemaking mechanisms - the use of a fully projected future test year in base rate proceedings and, subject to certain conditions, the use of a DSIC. Such alternative ratemaking procedures and mechanisms provide opportunity for accelerated cost-recovery and, therefore, are important to PPL Electric as it begins a period of significant capital investment to maintain and enhance the reliability of its delivery system, including the replacement of aging distribution assets. In August 2012, the PUC issued a Final Implementation Order adopting procedures, guidelines and a model tariff for the implementation of Act 11. Act 11 requires utilities to file an LTIIP as a prerequisite to filing for recovery through the DSIC. The LTIIP is mandated to be a five- to ten-year plan describing projects eligible for inclusion in the DSIC. In September 2012, PPL Electric filed its LTIIP describing projects eligible for inclusion in the DSIC.

 

The PUC approved the LTIIP on January 10, 2013 and, on January 15, 2013, PPL Electric filed a petition requesting permission to establish a DSIC. Several parties have filed responses to PPL Electric's petition. The case remains pending before the PUC. PPL Electric does not expect any new rates to be effective before the third quarter of 2013.

 

Federal Matters

 

FERC Formula Rates (PPL and PPL Electric)

 

Transmission rates are regulated by the FERC. PPL Electric's transmission revenues are billed in accordance with a FERC-approved PJM open access transmission tariff that utilizes a formula-based rate recovery mechanism. The formula rate is calculated, in part, based on financial results as reported in PPL Electric's annual FERC Form No. 1, filed under FERC's Uniform System of Accounts (USOA). PPL Electric must follow FERC's USOA, which requires subsidiaries to be presented, for FERC reporting purposes, using the equity method of accounting unless a waiver has been issued. The FERC has granted waivers of this requirement to other utilities when such waiver would more accurately present the integrated operations of the utilities and their subsidiaries. In March 2013, as part of a routine FERC audit of PPL and its subsidiaries, PPL Electric determined that it never obtained a waiver of the use of the equity method of accounting for PPL Receivables Corporation (PPL Receivables). PPL Receivables is a wholly owned subsidiary of PPL Electric, formed in 2004 to purchase eligible accounts receivable and unbilled revenue of PPL Electric to collateralize commercial paper issuances to reduce borrowing costs. In March 2013, PPL Electric filed a request for waiver with FERC that, if approved, would allow it to continue to consolidate the results of PPL Receivables with the results of PPL Electric, as it has done since 2004. While PPL Electric may ultimately be successful in obtaining a waiver from FERC, FERC may require PPL Electric to re-issue one or more of its prior FERC Form No. 1 filings in either the audit proceeding or the waiver proceeding. If re-issuance of FERC Form No. 1 filings were required by FERC, PPL Electric's revenue requirement calculated under the formula rate could be negatively impacted. The impact, if any, is not known at this time but could range between $0 and $40 million, pre-tax. PPL Electric cannot predict the outcome of the waiver or audit proceedings, which remain pending before the FERC.

 

PPL Electric has initiated its formula rate 2012, 2011 and 2010 Annual Updates. Each update has been subsequently challenged by a group of municipal customers, which challenges have been opposed by PPL Electric. In August 2011, the FERC issued an order substantially rejecting the 2010 formal challenge and the municipal customers filed a request for rehearing of that order. In September 2012, the FERC issued an order setting for evidentiary hearings and settlement judge procedures a number of issues raised in the 2010 and 2011 formal challenges. Settlement conferences were held in late 2012 and early 2013. In February 2013, the FERC set for evidentiary hearings and settlement judge procedures a number of issues in the 2012 formal challenge and consolidated that challenge with the 2010 and 2011 challenges. PPL Electric filed a request for rehearing of the February Order which remains pending before the FERC. PPL Electric anticipates that there will be additional settlement conferences held in 2013. Several of the municipal customers have filed Notice of Withdrawal of Intervention. PPL and PPL Electric cannot predict the outcome of the foregoing proceedings, which remain pending before the FERC.

U.K. Activities (PPL)

 

Ofgem Review of Line Loss Calculation

 

Ofgem is currently consulting on the methodology to be used by all network operators to calculate the final line loss incentive/penalty for the DPCR4. In April 2013, Ofgem stated that their current expectation was to issue a decision in the second half of 2013. PPL cannot predict when this matter will be resolved. WPD had an $89 million liability recorded at March 31, 2013 compared with $94 million at December 31, 2012, related to the close-out of line losses for the DPCR4, with the change due to foreign exchange movements.

LG And E And KU Energy LLC [Member]
 
Utility Rate Regulation [Line Items]  
Utility Rate Regulation

6. Utility Rate Regulation

 

(PPL, PPL Electric, LKE, LG&E and KU)

 

The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.

   PPL PPL Electric
   March 31, December 31, March 31, December 31,
   2013 2012 2013 2012
              
Current Regulatory Assets:            
 Transmission formula rate $ 5    $ 5   
 Gas supply clause   12 $ 11      
 Fuel adjustment clause   14   6      
 Other    6   2      
Total current regulatory assets $ 37 $ 19 $ 5   
              
Noncurrent Regulatory Assets:            
 Defined benefit plans $ 714 $ 730 $ 356 $ 362
 Taxes recoverable through future rates   295   293   295   293
 Storm costs   163   168   58   59
 Unamortized loss on debt   94   96   63   65
 Interest rate swaps   62   67      
 Accumulated cost of removal of utility plant    85   71   85   71
 AROs   30   26      
 Other    21   32   3   3
Total noncurrent regulatory assets $ 1,464 $ 1,483 $ 860 $ 853

Current Regulatory Liabilities:            
 Generation supply charge  $ 28 $ 27 $ 28 $ 27
 ECR      4      
 Gas supply clause   1   4      
 Transmission service charge   12   6   12   6
 Universal service rider   15   17   15   17
 Other    5   3   2   2
Total current regulatory liabilities $ 61 $ 61 $ 57 $ 52
              
Noncurrent Regulatory Liabilities:            
 Accumulated cost of removal of utility plant $ 687 $ 679      
 Coal contracts (a)   130   141      
 Power purchase agreement - OVEC (a)   107   108      
 Net deferred tax assets   33   34      
 Act 129 compliance rider   13   8 $ 13 $ 8
 Defined benefit plans   17   17      
 Interest rate swaps   24   14      
 Other    5   9      
Total noncurrent regulatory liabilities $ 1,016 $ 1,010 $ 13 $ 8

   LKE LG&E KU
   March 31, December 31, March 31, December 31, March 31, December 31,
   2013 2012 2013 2012 2013 2012
                    
Current Regulatory Assets:                  
 Gas supply clause $ 12 $ 11 $ 12 $ 11      
 Fuel adjustment clause   14   6   7   6 $ 7   
 Other    6   2   2   2   4   
Total current regulatory assets $ 32 $ 19 $ 21 $ 19 $ 11   
                    
Noncurrent Regulatory Assets:                  
 Defined benefit plans $ 358 $ 368 $ 225 $ 232 $ 133 $ 136
 Storm costs   105   109   57   59   48   50
 Unamortized loss on debt    31   31   20   20   11   11
 Interest rate swaps   62   67   62   67      
 AROs   30   26   17   15   13   11
 Other    18   29   7   7   11   22
Total noncurrent regulatory assets $ 604 $ 630 $ 388 $ 400 $ 216 $ 230

Current Regulatory Liabilities:                  
  ECR    $ 4          $ 4
  DSM $ 1          $ 1   
  Gas supply clause   1   4 $ 1 $ 4      
  Gas line tracker   2      2         
  Other       1            1
Total current regulatory liabilities $ 4 $ 9 $ 3 $ 4 $ 1 $ 5
                     
Noncurrent Regulatory Liabilities:                  
 Accumulated cost of removal                  
  of utility plant $ 687 $ 679 $ 299 $ 297 $ 388 $ 382
 Coal contracts (a)   130   141   57   61   73   80
 Power purchase agreement - OVEC (a)   107   108   74   75   33   33
 Net deferred tax assets   33   34   27   28   6   6
 Defined benefit plans   17   17         17   17
 Interest rate swaps   24   14   12   7   12   7
 Other    5   9   2   3   3   6
Total noncurrent regulatory liabilities $ 1,003 $ 1,002 $ 471 $ 471 $ 532 $ 531

(a)       Recorded as offsets to certain intangible assets that were recorded at fair value upon the acquisition of LKE.

Regulatory Matters

 

Kentucky Activities (PPL, LKE, LG&E and KU)

 

Rate Case Proceedings

 

In December 2012, the KPSC approved a rate case settlement agreement providing for increases in annual base electricity rates of $34 million for LG&E and $51 million for KU and an increase in annual base gas rates of $15 million for LG&E using a 10.25% return on equity. The approved rates became effective January 1, 2013.

Pennsylvania Activities (PPL and PPL Electric)

 

Rate Case Proceeding

 

In December 2012, the PUC approved a total distribution revenue increase of about $71 million, using a 10.4% return on equity. The approved rates became effective January 1, 2013.

 

Storm Damage Expense Rider

 

In its December 28, 2012 final rate case proceeding order, the PUC directed PPL Electric to file a proposed Storm Damage Expense Rider within 90 days following the order. PPL Electric filed its proposed Storm Damage Expense Rider with the PUC on March 28, 2013, including requested recovery of the 2012 qualifying storm costs related to Hurricane Sandy which were previously approved by the PUC for deferral. PPL Electric proposed that the Storm Damage Expense Rider become effective on January 1, 2013 for storm costs incurred in 2013, with those costs and the 2012 Hurricane Sandy costs included in rates effective on January 1, 2014. Several parties have filed comments opposing the Storm Damage Expense Rider. PPL Electric will file reply comments by May 6, 2013.

 

ACT 129

 

Act 129 requires Pennsylvania Electric Distribution Companies (EDCs) to meet specified goals for reduction in customer electricity usage and peak demand by specified dates. EDCs not meeting the requirements of Act 129 are exposed to significant penalties.

 

Under Act 129, EDCs must file an energy efficiency and conservation plan (EE&C Plan) with the PUC and contract with conservation service providers to implement all or a portion of the EE&C Plan. Act 129 requires EDCs to reduce overall electricity consumption by 1.0% by May 2011 and, by May 2013, reduce overall electricity consumption by 3.0% and reduce peak demand by 4.5%. Although PPL Electric believes it has met the May 2011 requirement, the PUC is not expected formally to determine compliance for any EDC before the first quarter of 2014. The peak demand reduction must occur for the 100 hours of highest demand, which is determined by actual demand reduction during the June 2012 through September 2012 period. EDCs are able to recover the costs (capped at 2.0% of the EDC's 2006 revenue) of implementing their EE&C Plans. In October 2009, the PUC approved PPL Electric's EE&C Plan. PPL Electric will determine if it met the peak demand reduction target and the May 2013 energy reduction target after it completes the final program evaluation in the fourth quarter of 2013.

Act 129 requires the PUC to evaluate the costs and benefits of the EE&C program by November 30, 2013 and adopt additional reductions if the benefits of the program exceed the costs. In August 2012, after receiving input from stakeholders, the PUC issued a Final Implementation Order establishing a three-year Phase II program, ending May 31, 2016, with individual consumption reduction targets for each EDC. PPL Electric's Phase II reduction target is 2.1% of the total energy consumption forecasted by the PUC for the June 1, 2009 through May 31, 2010 baseline year. The PUC did not establish demand reduction targets for the Phase II program. PPL Electric filed its Phase II EE&C Plan with the PUC on November 15, 2012 and the PUC issued its decision in March 2013, approving PPL Electric's Phase II program with minor modifications to a related tariff provision.

 

Act 129 also requires the Default Service Provider (DSP) to provide electric generation supply service to customers pursuant to a PUC-approved default service procurement plan through auctions, requests for proposal and bilateral contracts at the sole discretion of the DSP. Act 129 requires a mix of spot market purchases, short-term contracts and long-term contracts (4 to 20 years), with long-term contracts limited to 25% of load unless otherwise approved by the PUC. The DSP will be able to recover the costs associated with a competitive procurement plan.

 

The PUC has approved PPL Electric's procurement plan for the period January 1, 2011 through May 31, 2013, and PPL Electric concluded all competitive solicitations to procure power for its PLR obligations under that plan.

 

The PUC has directed all EDCs to file default service procurement plans for the period June 1, 2013 through May 31, 2015. PPL Electric filed its plan in May 2012. In that plan, PPL Electric proposed a process to obtain supply for its default service customers and a number of initiatives designed to encourage more customers to purchase electricity from the competitive retail market. In its January 24, 2013 final order, the PUC approved PPL Electric's plan with modifications and directed PPL Electric to establish collaborative processes to address several retail competition issues. In February 2013, PPL Electric filed a revised Default Service Supply Master Agreement and a revised Request for Proposals Process and Rules which the PUC approved. PPL Electric has filed revised retail competition initiatives and a revised plan consistent with the PUC's January order. These filings remain pending before the PUC. See Note 10 for additional information.

 

Smart Meter Rider

 

Act 129 also requires installation of smart meters for new construction, upon the request of consumers and at their cost, or on a depreciation schedule not exceeding 15 years. Under Act 129, EDCs are able to recover the costs of providing smart metering technology. All of PPL Electric's metered customers currently have advanced meters installed at their service locations capable of many of the functions required under Act 129. PPL Electric continues to conduct pilot projects to determine if its current advanced metering technology satisfies the requirements of Act 129. PPL Electric recovers the cost of its pilot projects through a cost recovery mechanism, the Smart Meter Rider (SMR). In August 2012, PPL Electric filed with the PUC an annual report describing the actions it was taking under its Smart Meter Plan in 2012 and its planned actions for 2013. PPL Electric also submitted revised SMR charges which became effective January 1, 2013. PPL Electric will submit its final Smart Meter Plan by June 30, 2014.

 

PUC Investigation of Retail Electricity Market

 

In April 2011, the PUC opened an investigation of Pennsylvania's retail electricity market to be conducted in two phases. Phase one addressed the status of the existing retail market and explored potential changes. Questions issued by the PUC for phase one of the investigation focused primarily on default service issues. Phase two was initiated in July 2011 to develop specific proposals for changes to the retail market and default service model. From December 2011 through the end of 2012, the PUC issued several orders and other pronouncements related to the investigation. A final implementation order was issued on February 15, 2013. Although the final implementation order contains provisions that will require numerous modifications to PPL Electric's current default service model for retail customers, those modifications are not expected to have a material adverse effect on PPL Electric's results of operations.

 

Legislation - Regulatory Procedures and Mechanisms

 

Act 11 authorizes the PUC to approve two specific ratemaking mechanisms - the use of a fully projected future test year in base rate proceedings and, subject to certain conditions, the use of a DSIC. Such alternative ratemaking procedures and mechanisms provide opportunity for accelerated cost-recovery and, therefore, are important to PPL Electric as it begins a period of significant capital investment to maintain and enhance the reliability of its delivery system, including the replacement of aging distribution assets. In August 2012, the PUC issued a Final Implementation Order adopting procedures, guidelines and a model tariff for the implementation of Act 11. Act 11 requires utilities to file an LTIIP as a prerequisite to filing for recovery through the DSIC. The LTIIP is mandated to be a five- to ten-year plan describing projects eligible for inclusion in the DSIC. In September 2012, PPL Electric filed its LTIIP describing projects eligible for inclusion in the DSIC.

 

The PUC approved the LTIIP on January 10, 2013 and, on January 15, 2013, PPL Electric filed a petition requesting permission to establish a DSIC. Several parties have filed responses to PPL Electric's petition. The case remains pending before the PUC. PPL Electric does not expect any new rates to be effective before the third quarter of 2013.

 

Federal Matters

 

FERC Formula Rates (PPL and PPL Electric)

 

Transmission rates are regulated by the FERC. PPL Electric's transmission revenues are billed in accordance with a FERC-approved PJM open access transmission tariff that utilizes a formula-based rate recovery mechanism. The formula rate is calculated, in part, based on financial results as reported in PPL Electric's annual FERC Form No. 1, filed under FERC's Uniform System of Accounts (USOA). PPL Electric must follow FERC's USOA, which requires subsidiaries to be presented, for FERC reporting purposes, using the equity method of accounting unless a waiver has been issued. The FERC has granted waivers of this requirement to other utilities when such waiver would more accurately present the integrated operations of the utilities and their subsidiaries. In March 2013, as part of a routine FERC audit of PPL and its subsidiaries, PPL Electric determined that it never obtained a waiver of the use of the equity method of accounting for PPL Receivables Corporation (PPL Receivables). PPL Receivables is a wholly owned subsidiary of PPL Electric, formed in 2004 to purchase eligible accounts receivable and unbilled revenue of PPL Electric to collateralize commercial paper issuances to reduce borrowing costs. In March 2013, PPL Electric filed a request for waiver with FERC that, if approved, would allow it to continue to consolidate the results of PPL Receivables with the results of PPL Electric, as it has done since 2004. While PPL Electric may ultimately be successful in obtaining a waiver from FERC, FERC may require PPL Electric to re-issue one or more of its prior FERC Form No. 1 filings in either the audit proceeding or the waiver proceeding. If re-issuance of FERC Form No. 1 filings were required by FERC, PPL Electric's revenue requirement calculated under the formula rate could be negatively impacted. The impact, if any, is not known at this time but could range between $0 and $40 million, pre-tax. PPL Electric cannot predict the outcome of the waiver or audit proceedings, which remain pending before the FERC.

 

PPL Electric has initiated its formula rate 2012, 2011 and 2010 Annual Updates. Each update has been subsequently challenged by a group of municipal customers, which challenges have been opposed by PPL Electric. In August 2011, the FERC issued an order substantially rejecting the 2010 formal challenge and the municipal customers filed a request for rehearing of that order. In September 2012, the FERC issued an order setting for evidentiary hearings and settlement judge procedures a number of issues raised in the 2010 and 2011 formal challenges. Settlement conferences were held in late 2012 and early 2013. In February 2013, the FERC set for evidentiary hearings and settlement judge procedures a number of issues in the 2012 formal challenge and consolidated that challenge with the 2010 and 2011 challenges. PPL Electric filed a request for rehearing of the February Order which remains pending before the FERC. PPL Electric anticipates that there will be additional settlement conferences held in 2013. Several of the municipal customers have filed Notice of Withdrawal of Intervention. PPL and PPL Electric cannot predict the outcome of the foregoing proceedings, which remain pending before the FERC.

U.K. Activities (PPL)

 

Ofgem Review of Line Loss Calculation

 

Ofgem is currently consulting on the methodology to be used by all network operators to calculate the final line loss incentive/penalty for the DPCR4. In April 2013, Ofgem stated that their current expectation was to issue a decision in the second half of 2013. PPL cannot predict when this matter will be resolved. WPD had an $89 million liability recorded at March 31, 2013 compared with $94 million at December 31, 2012, related to the close-out of line losses for the DPCR4, with the change due to foreign exchange movements.

Louisville Gas And Electric Co [Member]
 
Utility Rate Regulation [Line Items]  
Utility Rate Regulation

6. Utility Rate Regulation

 

(PPL, PPL Electric, LKE, LG&E and KU)

 

The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.

   PPL PPL Electric
   March 31, December 31, March 31, December 31,
   2013 2012 2013 2012
              
Current Regulatory Assets:            
 Transmission formula rate $ 5    $ 5   
 Gas supply clause   12 $ 11      
 Fuel adjustment clause   14   6      
 Other    6   2      
Total current regulatory assets $ 37 $ 19 $ 5   
              
Noncurrent Regulatory Assets:            
 Defined benefit plans $ 714 $ 730 $ 356 $ 362
 Taxes recoverable through future rates   295   293   295   293
 Storm costs   163   168   58   59
 Unamortized loss on debt   94   96   63   65
 Interest rate swaps   62   67      
 Accumulated cost of removal of utility plant    85   71   85   71
 AROs   30   26      
 Other    21   32   3   3
Total noncurrent regulatory assets $ 1,464 $ 1,483 $ 860 $ 853

Current Regulatory Liabilities:            
 Generation supply charge  $ 28 $ 27 $ 28 $ 27
 ECR      4      
 Gas supply clause   1   4      
 Transmission service charge   12   6   12   6
 Universal service rider   15   17   15   17
 Other    5   3   2   2
Total current regulatory liabilities $ 61 $ 61 $ 57 $ 52
              
Noncurrent Regulatory Liabilities:            
 Accumulated cost of removal of utility plant $ 687 $ 679      
 Coal contracts (a)   130   141      
 Power purchase agreement - OVEC (a)   107   108      
 Net deferred tax assets   33   34      
 Act 129 compliance rider   13   8 $ 13 $ 8
 Defined benefit plans   17   17      
 Interest rate swaps   24   14      
 Other    5   9      
Total noncurrent regulatory liabilities $ 1,016 $ 1,010 $ 13 $ 8

   LKE LG&E KU
   March 31, December 31, March 31, December 31, March 31, December 31,
   2013 2012 2013 2012 2013 2012
                    
Current Regulatory Assets:                  
 Gas supply clause $ 12 $ 11 $ 12 $ 11      
 Fuel adjustment clause   14   6   7   6 $ 7   
 Other    6   2   2   2   4   
Total current regulatory assets $ 32 $ 19 $ 21 $ 19 $ 11   
                    
Noncurrent Regulatory Assets:                  
 Defined benefit plans $ 358 $ 368 $ 225 $ 232 $ 133 $ 136
 Storm costs   105   109   57   59   48   50
 Unamortized loss on debt    31   31   20   20   11   11
 Interest rate swaps   62   67   62   67      
 AROs   30   26   17   15   13   11
 Other    18   29   7   7   11   22
Total noncurrent regulatory assets $ 604 $ 630 $ 388 $ 400 $ 216 $ 230

Current Regulatory Liabilities:                  
  ECR    $ 4          $ 4
  DSM $ 1          $ 1   
  Gas supply clause   1   4 $ 1 $ 4      
  Gas line tracker   2      2         
  Other       1            1
Total current regulatory liabilities $ 4 $ 9 $ 3 $ 4 $ 1 $ 5
                     
Noncurrent Regulatory Liabilities:                  
 Accumulated cost of removal                  
  of utility plant $ 687 $ 679 $ 299 $ 297 $ 388 $ 382
 Coal contracts (a)   130   141   57   61   73   80
 Power purchase agreement - OVEC (a)   107   108   74   75   33   33
 Net deferred tax assets   33   34   27   28   6   6
 Defined benefit plans   17   17         17   17
 Interest rate swaps   24   14   12   7   12   7
 Other    5   9   2   3   3   6
Total noncurrent regulatory liabilities $ 1,003 $ 1,002 $ 471 $ 471 $ 532 $ 531

(a)       Recorded as offsets to certain intangible assets that were recorded at fair value upon the acquisition of LKE.

Regulatory Matters

 

Kentucky Activities (PPL, LKE, LG&E and KU)

 

Rate Case Proceedings

 

In December 2012, the KPSC approved a rate case settlement agreement providing for increases in annual base electricity rates of $34 million for LG&E and $51 million for KU and an increase in annual base gas rates of $15 million for LG&E using a 10.25% return on equity. The approved rates became effective January 1, 2013.

Pennsylvania Activities (PPL and PPL Electric)

 

Rate Case Proceeding

 

In December 2012, the PUC approved a total distribution revenue increase of about $71 million, using a 10.4% return on equity. The approved rates became effective January 1, 2013.

 

Storm Damage Expense Rider

 

In its December 28, 2012 final rate case proceeding order, the PUC directed PPL Electric to file a proposed Storm Damage Expense Rider within 90 days following the order. PPL Electric filed its proposed Storm Damage Expense Rider with the PUC on March 28, 2013, including requested recovery of the 2012 qualifying storm costs related to Hurricane Sandy which were previously approved by the PUC for deferral. PPL Electric proposed that the Storm Damage Expense Rider become effective on January 1, 2013 for storm costs incurred in 2013, with those costs and the 2012 Hurricane Sandy costs included in rates effective on January 1, 2014. Several parties have filed comments opposing the Storm Damage Expense Rider. PPL Electric will file reply comments by May 6, 2013.

 

ACT 129

 

Act 129 requires Pennsylvania Electric Distribution Companies (EDCs) to meet specified goals for reduction in customer electricity usage and peak demand by specified dates. EDCs not meeting the requirements of Act 129 are exposed to significant penalties.

 

Under Act 129, EDCs must file an energy efficiency and conservation plan (EE&C Plan) with the PUC and contract with conservation service providers to implement all or a portion of the EE&C Plan. Act 129 requires EDCs to reduce overall electricity consumption by 1.0% by May 2011 and, by May 2013, reduce overall electricity consumption by 3.0% and reduce peak demand by 4.5%. Although PPL Electric believes it has met the May 2011 requirement, the PUC is not expected formally to determine compliance for any EDC before the first quarter of 2014. The peak demand reduction must occur for the 100 hours of highest demand, which is determined by actual demand reduction during the June 2012 through September 2012 period. EDCs are able to recover the costs (capped at 2.0% of the EDC's 2006 revenue) of implementing their EE&C Plans. In October 2009, the PUC approved PPL Electric's EE&C Plan. PPL Electric will determine if it met the peak demand reduction target and the May 2013 energy reduction target after it completes the final program evaluation in the fourth quarter of 2013.

Act 129 requires the PUC to evaluate the costs and benefits of the EE&C program by November 30, 2013 and adopt additional reductions if the benefits of the program exceed the costs. In August 2012, after receiving input from stakeholders, the PUC issued a Final Implementation Order establishing a three-year Phase II program, ending May 31, 2016, with individual consumption reduction targets for each EDC. PPL Electric's Phase II reduction target is 2.1% of the total energy consumption forecasted by the PUC for the June 1, 2009 through May 31, 2010 baseline year. The PUC did not establish demand reduction targets for the Phase II program. PPL Electric filed its Phase II EE&C Plan with the PUC on November 15, 2012 and the PUC issued its decision in March 2013, approving PPL Electric's Phase II program with minor modifications to a related tariff provision.

 

Act 129 also requires the Default Service Provider (DSP) to provide electric generation supply service to customers pursuant to a PUC-approved default service procurement plan through auctions, requests for proposal and bilateral contracts at the sole discretion of the DSP. Act 129 requires a mix of spot market purchases, short-term contracts and long-term contracts (4 to 20 years), with long-term contracts limited to 25% of load unless otherwise approved by the PUC. The DSP will be able to recover the costs associated with a competitive procurement plan.

 

The PUC has approved PPL Electric's procurement plan for the period January 1, 2011 through May 31, 2013, and PPL Electric concluded all competitive solicitations to procure power for its PLR obligations under that plan.

 

The PUC has directed all EDCs to file default service procurement plans for the period June 1, 2013 through May 31, 2015. PPL Electric filed its plan in May 2012. In that plan, PPL Electric proposed a process to obtain supply for its default service customers and a number of initiatives designed to encourage more customers to purchase electricity from the competitive retail market. In its January 24, 2013 final order, the PUC approved PPL Electric's plan with modifications and directed PPL Electric to establish collaborative processes to address several retail competition issues. In February 2013, PPL Electric filed a revised Default Service Supply Master Agreement and a revised Request for Proposals Process and Rules which the PUC approved. PPL Electric has filed revised retail competition initiatives and a revised plan consistent with the PUC's January order. These filings remain pending before the PUC. See Note 10 for additional information.

 

Smart Meter Rider

 

Act 129 also requires installation of smart meters for new construction, upon the request of consumers and at their cost, or on a depreciation schedule not exceeding 15 years. Under Act 129, EDCs are able to recover the costs of providing smart metering technology. All of PPL Electric's metered customers currently have advanced meters installed at their service locations capable of many of the functions required under Act 129. PPL Electric continues to conduct pilot projects to determine if its current advanced metering technology satisfies the requirements of Act 129. PPL Electric recovers the cost of its pilot projects through a cost recovery mechanism, the Smart Meter Rider (SMR). In August 2012, PPL Electric filed with the PUC an annual report describing the actions it was taking under its Smart Meter Plan in 2012 and its planned actions for 2013. PPL Electric also submitted revised SMR charges which became effective January 1, 2013. PPL Electric will submit its final Smart Meter Plan by June 30, 2014.

 

PUC Investigation of Retail Electricity Market

 

In April 2011, the PUC opened an investigation of Pennsylvania's retail electricity market to be conducted in two phases. Phase one addressed the status of the existing retail market and explored potential changes. Questions issued by the PUC for phase one of the investigation focused primarily on default service issues. Phase two was initiated in July 2011 to develop specific proposals for changes to the retail market and default service model. From December 2011 through the end of 2012, the PUC issued several orders and other pronouncements related to the investigation. A final implementation order was issued on February 15, 2013. Although the final implementation order contains provisions that will require numerous modifications to PPL Electric's current default service model for retail customers, those modifications are not expected to have a material adverse effect on PPL Electric's results of operations.

 

Legislation - Regulatory Procedures and Mechanisms

 

Act 11 authorizes the PUC to approve two specific ratemaking mechanisms - the use of a fully projected future test year in base rate proceedings and, subject to certain conditions, the use of a DSIC. Such alternative ratemaking procedures and mechanisms provide opportunity for accelerated cost-recovery and, therefore, are important to PPL Electric as it begins a period of significant capital investment to maintain and enhance the reliability of its delivery system, including the replacement of aging distribution assets. In August 2012, the PUC issued a Final Implementation Order adopting procedures, guidelines and a model tariff for the implementation of Act 11. Act 11 requires utilities to file an LTIIP as a prerequisite to filing for recovery through the DSIC. The LTIIP is mandated to be a five- to ten-year plan describing projects eligible for inclusion in the DSIC. In September 2012, PPL Electric filed its LTIIP describing projects eligible for inclusion in the DSIC.

 

The PUC approved the LTIIP on January 10, 2013 and, on January 15, 2013, PPL Electric filed a petition requesting permission to establish a DSIC. Several parties have filed responses to PPL Electric's petition. The case remains pending before the PUC. PPL Electric does not expect any new rates to be effective before the third quarter of 2013.

 

Federal Matters

 

FERC Formula Rates (PPL and PPL Electric)

 

Transmission rates are regulated by the FERC. PPL Electric's transmission revenues are billed in accordance with a FERC-approved PJM open access transmission tariff that utilizes a formula-based rate recovery mechanism. The formula rate is calculated, in part, based on financial results as reported in PPL Electric's annual FERC Form No. 1, filed under FERC's Uniform System of Accounts (USOA). PPL Electric must follow FERC's USOA, which requires subsidiaries to be presented, for FERC reporting purposes, using the equity method of accounting unless a waiver has been issued. The FERC has granted waivers of this requirement to other utilities when such waiver would more accurately present the integrated operations of the utilities and their subsidiaries. In March 2013, as part of a routine FERC audit of PPL and its subsidiaries, PPL Electric determined that it never obtained a waiver of the use of the equity method of accounting for PPL Receivables Corporation (PPL Receivables). PPL Receivables is a wholly owned subsidiary of PPL Electric, formed in 2004 to purchase eligible accounts receivable and unbilled revenue of PPL Electric to collateralize commercial paper issuances to reduce borrowing costs. In March 2013, PPL Electric filed a request for waiver with FERC that, if approved, would allow it to continue to consolidate the results of PPL Receivables with the results of PPL Electric, as it has done since 2004. While PPL Electric may ultimately be successful in obtaining a waiver from FERC, FERC may require PPL Electric to re-issue one or more of its prior FERC Form No. 1 filings in either the audit proceeding or the waiver proceeding. If re-issuance of FERC Form No. 1 filings were required by FERC, PPL Electric's revenue requirement calculated under the formula rate could be negatively impacted. The impact, if any, is not known at this time but could range between $0 and $40 million, pre-tax. PPL Electric cannot predict the outcome of the waiver or audit proceedings, which remain pending before the FERC.

 

PPL Electric has initiated its formula rate 2012, 2011 and 2010 Annual Updates. Each update has been subsequently challenged by a group of municipal customers, which challenges have been opposed by PPL Electric. In August 2011, the FERC issued an order substantially rejecting the 2010 formal challenge and the municipal customers filed a request for rehearing of that order. In September 2012, the FERC issued an order setting for evidentiary hearings and settlement judge procedures a number of issues raised in the 2010 and 2011 formal challenges. Settlement conferences were held in late 2012 and early 2013. In February 2013, the FERC set for evidentiary hearings and settlement judge procedures a number of issues in the 2012 formal challenge and consolidated that challenge with the 2010 and 2011 challenges. PPL Electric filed a request for rehearing of the February Order which remains pending before the FERC. PPL Electric anticipates that there will be additional settlement conferences held in 2013. Several of the municipal customers have filed Notice of Withdrawal of Intervention. PPL and PPL Electric cannot predict the outcome of the foregoing proceedings, which remain pending before the FERC.

U.K. Activities (PPL)

 

Ofgem Review of Line Loss Calculation

 

Ofgem is currently consulting on the methodology to be used by all network operators to calculate the final line loss incentive/penalty for the DPCR4. In April 2013, Ofgem stated that their current expectation was to issue a decision in the second half of 2013. PPL cannot predict when this matter will be resolved. WPD had an $89 million liability recorded at March 31, 2013 compared with $94 million at December 31, 2012, related to the close-out of line losses for the DPCR4, with the change due to foreign exchange movements.

Kentucky Utilities Co [Member]
 
Utility Rate Regulation [Line Items]  
Utility Rate Regulation

6. Utility Rate Regulation

 

(PPL, PPL Electric, LKE, LG&E and KU)

 

The following table provides information about the regulatory assets and liabilities of cost-based rate-regulated utility operations.

   PPL PPL Electric
   March 31, December 31, March 31, December 31,
   2013 2012 2013 2012
              
Current Regulatory Assets:            
 Transmission formula rate $ 5    $ 5   
 Gas supply clause   12 $ 11      
 Fuel adjustment clause   14   6      
 Other    6   2      
Total current regulatory assets $ 37 $ 19 $ 5   
              
Noncurrent Regulatory Assets:            
 Defined benefit plans $ 714 $ 730 $ 356 $ 362
 Taxes recoverable through future rates   295   293   295   293
 Storm costs   163   168   58   59
 Unamortized loss on debt   94   96   63   65
 Interest rate swaps   62   67      
 Accumulated cost of removal of utility plant    85   71   85   71
 AROs   30   26      
 Other    21   32   3   3
Total noncurrent regulatory assets $ 1,464 $ 1,483 $ 860 $ 853

Current Regulatory Liabilities:            
 Generation supply charge  $ 28 $ 27 $ 28 $ 27
 ECR      4      
 Gas supply clause   1   4      
 Transmission service charge   12   6   12   6
 Universal service rider   15   17   15   17
 Other    5   3   2   2
Total current regulatory liabilities $ 61 $ 61 $ 57 $ 52
              
Noncurrent Regulatory Liabilities:            
 Accumulated cost of removal of utility plant $ 687 $ 679      
 Coal contracts (a)   130   141      
 Power purchase agreement - OVEC (a)   107   108      
 Net deferred tax assets   33   34      
 Act 129 compliance rider   13   8 $ 13 $ 8
 Defined benefit plans   17   17      
 Interest rate swaps   24   14      
 Other    5   9      
Total noncurrent regulatory liabilities $ 1,016 $ 1,010 $ 13 $ 8

   LKE LG&E KU
   March 31, December 31, March 31, December 31, March 31, December 31,
   2013 2012 2013 2012 2013 2012
                    
Current Regulatory Assets:                  
 Gas supply clause $ 12 $ 11 $ 12 $ 11      
 Fuel adjustment clause   14   6   7   6 $ 7   
 Other    6   2   2   2   4   
Total current regulatory assets $ 32 $ 19 $ 21 $ 19 $ 11   
                    
Noncurrent Regulatory Assets:                  
 Defined benefit plans $ 358 $ 368 $ 225 $ 232 $ 133 $ 136
 Storm costs   105   109   57   59   48   50
 Unamortized loss on debt    31   31   20   20   11   11
 Interest rate swaps   62   67   62   67      
 AROs   30   26   17   15   13   11
 Other    18   29   7   7   11   22
Total noncurrent regulatory assets $ 604 $ 630 $ 388 $ 400 $ 216 $ 230

Current Regulatory Liabilities:                  
  ECR    $ 4          $ 4
  DSM $ 1          $ 1   
  Gas supply clause   1   4 $ 1 $ 4      
  Gas line tracker   2      2         
  Other       1            1
Total current regulatory liabilities $ 4 $ 9 $ 3 $ 4 $ 1 $ 5
                     
Noncurrent Regulatory Liabilities:                  
 Accumulated cost of removal                  
  of utility plant $ 687 $ 679 $ 299 $ 297 $ 388 $ 382
 Coal contracts (a)   130   141   57   61   73   80
 Power purchase agreement - OVEC (a)   107   108   74   75   33   33
 Net deferred tax assets   33   34   27   28   6   6
 Defined benefit plans   17   17         17   17
 Interest rate swaps   24   14   12   7   12   7
 Other    5   9   2   3   3   6
Total noncurrent regulatory liabilities $ 1,003 $ 1,002 $ 471 $ 471 $ 532 $ 531

(a)       Recorded as offsets to certain intangible assets that were recorded at fair value upon the acquisition of LKE.

Regulatory Matters

 

Kentucky Activities (PPL, LKE, LG&E and KU)

 

Rate Case Proceedings

 

In December 2012, the KPSC approved a rate case settlement agreement providing for increases in annual base electricity rates of $34 million for LG&E and $51 million for KU and an increase in annual base gas rates of $15 million for LG&E using a 10.25% return on equity. The approved rates became effective January 1, 2013.

Pennsylvania Activities (PPL and PPL Electric)

 

Rate Case Proceeding

 

In December 2012, the PUC approved a total distribution revenue increase of about $71 million, using a 10.4% return on equity. The approved rates became effective January 1, 2013.

 

Storm Damage Expense Rider

 

In its December 28, 2012 final rate case proceeding order, the PUC directed PPL Electric to file a proposed Storm Damage Expense Rider within 90 days following the order. PPL Electric filed its proposed Storm Damage Expense Rider with the PUC on March 28, 2013, including requested recovery of the 2012 qualifying storm costs related to Hurricane Sandy which were previously approved by the PUC for deferral. PPL Electric proposed that the Storm Damage Expense Rider become effective on January 1, 2013 for storm costs incurred in 2013, with those costs and the 2012 Hurricane Sandy costs included in rates effective on January 1, 2014. Several parties have filed comments opposing the Storm Damage Expense Rider. PPL Electric will file reply comments by May 6, 2013.

 

ACT 129

 

Act 129 requires Pennsylvania Electric Distribution Companies (EDCs) to meet specified goals for reduction in customer electricity usage and peak demand by specified dates. EDCs not meeting the requirements of Act 129 are exposed to significant penalties.

 

Under Act 129, EDCs must file an energy efficiency and conservation plan (EE&C Plan) with the PUC and contract with conservation service providers to implement all or a portion of the EE&C Plan. Act 129 requires EDCs to reduce overall electricity consumption by 1.0% by May 2011 and, by May 2013, reduce overall electricity consumption by 3.0% and reduce peak demand by 4.5%. Although PPL Electric believes it has met the May 2011 requirement, the PUC is not expected formally to determine compliance for any EDC before the first quarter of 2014. The peak demand reduction must occur for the 100 hours of highest demand, which is determined by actual demand reduction during the June 2012 through September 2012 period. EDCs are able to recover the costs (capped at 2.0% of the EDC's 2006 revenue) of implementing their EE&C Plans. In October 2009, the PUC approved PPL Electric's EE&C Plan. PPL Electric will determine if it met the peak demand reduction target and the May 2013 energy reduction target after it completes the final program evaluation in the fourth quarter of 2013.

Act 129 requires the PUC to evaluate the costs and benefits of the EE&C program by November 30, 2013 and adopt additional reductions if the benefits of the program exceed the costs. In August 2012, after receiving input from stakeholders, the PUC issued a Final Implementation Order establishing a three-year Phase II program, ending May 31, 2016, with individual consumption reduction targets for each EDC. PPL Electric's Phase II reduction target is 2.1% of the total energy consumption forecasted by the PUC for the June 1, 2009 through May 31, 2010 baseline year. The PUC did not establish demand reduction targets for the Phase II program. PPL Electric filed its Phase II EE&C Plan with the PUC on November 15, 2012 and the PUC issued its decision in March 2013, approving PPL Electric's Phase II program with minor modifications to a related tariff provision.

 

Act 129 also requires the Default Service Provider (DSP) to provide electric generation supply service to customers pursuant to a PUC-approved default service procurement plan through auctions, requests for proposal and bilateral contracts at the sole discretion of the DSP. Act 129 requires a mix of spot market purchases, short-term contracts and long-term contracts (4 to 20 years), with long-term contracts limited to 25% of load unless otherwise approved by the PUC. The DSP will be able to recover the costs associated with a competitive procurement plan.

 

The PUC has approved PPL Electric's procurement plan for the period January 1, 2011 through May 31, 2013, and PPL Electric concluded all competitive solicitations to procure power for its PLR obligations under that plan.

 

The PUC has directed all EDCs to file default service procurement plans for the period June 1, 2013 through May 31, 2015. PPL Electric filed its plan in May 2012. In that plan, PPL Electric proposed a process to obtain supply for its default service customers and a number of initiatives designed to encourage more customers to purchase electricity from the competitive retail market. In its January 24, 2013 final order, the PUC approved PPL Electric's plan with modifications and directed PPL Electric to establish collaborative processes to address several retail competition issues. In February 2013, PPL Electric filed a revised Default Service Supply Master Agreement and a revised Request for Proposals Process and Rules which the PUC approved. PPL Electric has filed revised retail competition initiatives and a revised plan consistent with the PUC's January order. These filings remain pending before the PUC. See Note 10 for additional information.

 

Smart Meter Rider

 

Act 129 also requires installation of smart meters for new construction, upon the request of consumers and at their cost, or on a depreciation schedule not exceeding 15 years. Under Act 129, EDCs are able to recover the costs of providing smart metering technology. All of PPL Electric's metered customers currently have advanced meters installed at their service locations capable of many of the functions required under Act 129. PPL Electric continues to conduct pilot projects to determine if its current advanced metering technology satisfies the requirements of Act 129. PPL Electric recovers the cost of its pilot projects through a cost recovery mechanism, the Smart Meter Rider (SMR). In August 2012, PPL Electric filed with the PUC an annual report describing the actions it was taking under its Smart Meter Plan in 2012 and its planned actions for 2013. PPL Electric also submitted revised SMR charges which became effective January 1, 2013. PPL Electric will submit its final Smart Meter Plan by June 30, 2014.

 

PUC Investigation of Retail Electricity Market

 

In April 2011, the PUC opened an investigation of Pennsylvania's retail electricity market to be conducted in two phases. Phase one addressed the status of the existing retail market and explored potential changes. Questions issued by the PUC for phase one of the investigation focused primarily on default service issues. Phase two was initiated in July 2011 to develop specific proposals for changes to the retail market and default service model. From December 2011 through the end of 2012, the PUC issued several orders and other pronouncements related to the investigation. A final implementation order was issued on February 15, 2013. Although the final implementation order contains provisions that will require numerous modifications to PPL Electric's current default service model for retail customers, those modifications are not expected to have a material adverse effect on PPL Electric's results of operations.

 

Legislation - Regulatory Procedures and Mechanisms

 

Act 11 authorizes the PUC to approve two specific ratemaking mechanisms - the use of a fully projected future test year in base rate proceedings and, subject to certain conditions, the use of a DSIC. Such alternative ratemaking procedures and mechanisms provide opportunity for accelerated cost-recovery and, therefore, are important to PPL Electric as it begins a period of significant capital investment to maintain and enhance the reliability of its delivery system, including the replacement of aging distribution assets. In August 2012, the PUC issued a Final Implementation Order adopting procedures, guidelines and a model tariff for the implementation of Act 11. Act 11 requires utilities to file an LTIIP as a prerequisite to filing for recovery through the DSIC. The LTIIP is mandated to be a five- to ten-year plan describing projects eligible for inclusion in the DSIC. In September 2012, PPL Electric filed its LTIIP describing projects eligible for inclusion in the DSIC.

 

The PUC approved the LTIIP on January 10, 2013 and, on January 15, 2013, PPL Electric filed a petition requesting permission to establish a DSIC. Several parties have filed responses to PPL Electric's petition. The case remains pending before the PUC. PPL Electric does not expect any new rates to be effective before the third quarter of 2013.

 

Federal Matters

 

FERC Formula Rates (PPL and PPL Electric)

 

Transmission rates are regulated by the FERC. PPL Electric's transmission revenues are billed in accordance with a FERC-approved PJM open access transmission tariff that utilizes a formula-based rate recovery mechanism. The formula rate is calculated, in part, based on financial results as reported in PPL Electric's annual FERC Form No. 1, filed under FERC's Uniform System of Accounts (USOA). PPL Electric must follow FERC's USOA, which requires subsidiaries to be presented, for FERC reporting purposes, using the equity method of accounting unless a waiver has been issued. The FERC has granted waivers of this requirement to other utilities when such waiver would more accurately present the integrated operations of the utilities and their subsidiaries. In March 2013, as part of a routine FERC audit of PPL and its subsidiaries, PPL Electric determined that it never obtained a waiver of the use of the equity method of accounting for PPL Receivables Corporation (PPL Receivables). PPL Receivables is a wholly owned subsidiary of PPL Electric, formed in 2004 to purchase eligible accounts receivable and unbilled revenue of PPL Electric to collateralize commercial paper issuances to reduce borrowing costs. In March 2013, PPL Electric filed a request for waiver with FERC that, if approved, would allow it to continue to consolidate the results of PPL Receivables with the results of PPL Electric, as it has done since 2004. While PPL Electric may ultimately be successful in obtaining a waiver from FERC, FERC may require PPL Electric to re-issue one or more of its prior FERC Form No. 1 filings in either the audit proceeding or the waiver proceeding. If re-issuance of FERC Form No. 1 filings were required by FERC, PPL Electric's revenue requirement calculated under the formula rate could be negatively impacted. The impact, if any, is not known at this time but could range between $0 and $40 million, pre-tax. PPL Electric cannot predict the outcome of the waiver or audit proceedings, which remain pending before the FERC.

 

PPL Electric has initiated its formula rate 2012, 2011 and 2010 Annual Updates. Each update has been subsequently challenged by a group of municipal customers, which challenges have been opposed by PPL Electric. In August 2011, the FERC issued an order substantially rejecting the 2010 formal challenge and the municipal customers filed a request for rehearing of that order. In September 2012, the FERC issued an order setting for evidentiary hearings and settlement judge procedures a number of issues raised in the 2010 and 2011 formal challenges. Settlement conferences were held in late 2012 and early 2013. In February 2013, the FERC set for evidentiary hearings and settlement judge procedures a number of issues in the 2012 formal challenge and consolidated that challenge with the 2010 and 2011 challenges. PPL Electric filed a request for rehearing of the February Order which remains pending before the FERC. PPL Electric anticipates that there will be additional settlement conferences held in 2013. Several of the municipal customers have filed Notice of Withdrawal of Intervention. PPL and PPL Electric cannot predict the outcome of the foregoing proceedings, which remain pending before the FERC.

U.K. Activities (PPL)

 

Ofgem Review of Line Loss Calculation

 

Ofgem is currently consulting on the methodology to be used by all network operators to calculate the final line loss incentive/penalty for the DPCR4. In April 2013, Ofgem stated that their current expectation was to issue a decision in the second half of 2013. PPL cannot predict when this matter will be resolved. WPD had an $89 million liability recorded at March 31, 2013 compared with $94 million at December 31, 2012, related to the close-out of line losses for the DPCR4, with the change due to foreign exchange movements.