Acquisitions, Development and Divestitures (Details) (USD $)
12 Months Ended
Dec. 31, 2011
MW
Dec. 31, 2010
Development Projects [Abstract]    
Number of plants anticipated to retire based on stricter EPA regulations or new construction 3  
Combined capacity, in MW, of plants anticipated to retire based on stricter EPA regulations or new construction 797  
Number of applicants that submitted loan guarantees to the DOE 10  
Holtwood Hydroelectric Plant Expansion [Member]
   
Development Projects [Abstract]    
Expected capital cost of an expansion project $ 438,000,000  
Capital cost unspent at the end of the period 196,000,000  
Rainbow Hydroelectric Plant Expansion [Member]
   
Development Projects [Abstract]    
Planned capacity (in MW) expansion 28  
Expected capital cost of an expansion project 207,000,000  
Capital cost unspent at the end of the period 29,000,000  
Actual investments tax credits recorded 52,000,000 52,000,000
Forecasted investment tax credits 54,000,000  
Susquehanna Nuclear Plant Expansion [Member]
   
Development Projects [Abstract]    
Share of the total planned capacity (in MW) expansion when the company has a joint ownership interest 195  
Completed capacity (in MW) expansion 50  
Proposed Bell Bend Nuclear Unit [Member]
   
Development Projects [Abstract]    
Number of applicants still active in DOE nuclear guarantee program 8  
Current appropriated federal loan guarantees for nuclear projects 18,500,000,000  
Maximum number of projects the DOE is expected to finance 3  
Amount currently authorized by Board of Directors to spend on Bell Bend COLA 162,000,000  
Capitalized costs associated with licensing efforts 131,000,000 109,000,000
Susquehanna Roseland Transmission Line [Member]
   
Development Projects [Abstract]    
Expected capital cost of an expansion project 500,000,000  
Total length (in miles) of the expansion project 150  
Capacity (in kilovolts) of a transmission line 500  
Total length (in miles) of the expansion project to be routed through Pennsylvania 100  
Pending Bluegrass Plant Acquistion [Member]
   
Development Projects [Abstract]    
Capacity of purchased units (in MW) 495  
Purchase price 110,000,000  
LG&E ownership percentage 69.00%  
KU ownership percentage 31.00%  
Proposed Natural Gas Fired Combined Cycle Turbine [Member]
   
Development Projects [Abstract]    
Planned capacity (in MW) expansion 640  
Expected capital cost of an expansion project $ 580,000,000  
Number of plants anticipated to retire based on stricter EPA regulations or new construction 6