KCC Proceedings
Evergy Kansas Central 2020 Transmission Delivery Charge (TDC)
In March 2020, the State Corporation Commission of the State of Kansas (KCC) issued an order adjusting Evergy Kansas Central's retail prices to include updated transmission costs as reflected in the Federal Energy Regulatory Commission (FERC) transmission formula rate (TFR). The new prices were effective in April 2020 and are expected to increase Evergy Kansas Central's annual retail revenues by $3.5 million.
Evergy Metro 2020 TDC
In April 2020, the KCC issued an order adjusting Evergy Metro's retail prices to include updated transmission costs as reflected in the FERC TFR. The new prices were effective in May 2020 and are expected to decrease Evergy Metro's annual retail revenues by $2.7 million.
Evergy Kansas Central and Evergy Metro Earnings Review and Sharing Plan (ERSP)
As part of their merger settlement agreement with the KCC, Evergy Kansas Central and Evergy Metro agreed to participate in an ERSP for the years 2019 through 2022. Under the ERSP, Evergy Kansas Central's and Evergy Metro's Kansas jurisdiction are required to refund to customers 50% of annual earnings in excess of their authorized return on equity of 9.3% to the extent the excess earnings exceed the amount of Evergy Kansas Central's and Evergy Metro's annual merger bill credits for the year being measured.
Evergy Kansas Central's and Evergy Metro's 2019 calculations of annual earnings did not exceed their authorized return on equity of 9.3% and therefore did not result in any customer refund obligations. These calculations were filed with the KCC in April 2020. As of March 31, 2020, Evergy Kansas Central and Evergy Metro estimate their 2020 annual earnings will not result in a refund obligation. The final refund obligations for 2019 and 2020, if any, will be decided by the KCC and could vary from the current estimates.
Evergy Kansas Central and Evergy Metro COVID-19 Accounting Authority Order (AAO) Request
In May 2020, Evergy Kansas Central and Evergy Metro filed a request for an AAO with the KCC that would allow for the extraordinary costs and financial impacts incurred by the companies as a result of the COVID-19 pandemic to be considered for future recovery from customers as part of their next rate case. A decision by the KCC regarding the AAO request is expected in the second half of 2020.
MPSC Proceedings
Evergy Missouri West Other Proceedings
In December 2018, the Office of the Public Counsel (OPC) and the Midwest Energy Consumers Group (MECG) filed a petition with the Public Service Commission of the State of Missouri (MPSC) requesting an AAO that would require Evergy Missouri West to record a regulatory liability for all revenues collected from customers for return on investment, non-fuel operations and maintenance costs, taxes including accumulated deferred income taxes, and all other costs associated with Sibley Station following the station’s retirement in November 2018.
In October 2019, the MPSC granted OPC's and MECG's request for an AAO and required Evergy Missouri West to record to a regulatory liability the revenues discussed above for consideration in Evergy Missouri West's next rate case, which is expected to be completed no later than 2022. Depending on the MPSC's decision in this next rate case, Evergy Missouri West could be required to refund to customers all or a portion of amounts collected in revenue for Sibley Station since December 2018 or, alternatively, could be required to make no refunds.
As a result of the MPSC order, Evergy has recorded a regulatory liability of $12.9 million as of March 31, 2020 for the estimated amount of revenues that Evergy Missouri West has collected from customers for Sibley Station since December 2018 that Evergy has determined is probable of refund. Evergy expects that it will continue to defer such amounts as collected from customers until new rates become effective in Evergy Missouri West's next rate case.
The accrual for this estimated amount does not include certain revenues collected related to Sibley Station that Evergy has determined to not be probable of refund in the next rate case based on the relevant facts and circumstances. While Evergy has determined these additional revenues to not be probable of refund, the ultimate resolution of this matter in Evergy Missouri West's next rate case is uncertain and could result in an estimated loss of up to approximately $12 million per year in excess of the amount accrued until Evergy Missouri West's new rates become effective. Evergy's regulatory liability for probable refunds as of March 31, 2020 and estimated loss in excess of the amount accrued represent estimates that could change significantly based on ongoing developments including as a result of an appeal of the MPSC order, decisions in other regulatory proceedings that establish precedent applicable to this matter and positions of parties on this issue in a future Evergy Missouri West rate case.
Evergy Metro and Evergy Missouri West COVID-19 AAO Request
In May 2020, Evergy Metro and Evergy Missouri West filed a request for an AAO with the MPSC that would allow for the extraordinary costs and financial impacts incurred by the companies as a result of the COVID-19 pandemic to be considered for future recovery from customers as part of their next rate case. A decision by the MPSC regarding the AAO request is expected in the second half of 2020.
FERC Proceedings
Evergy Kansas Central TFR
Evergy Kansas Central's TFR, effective in January 2020, includes projected 2020 transmission capital expenditures and operating costs and is expected to increase annual transmission revenues by $6.8 million when compared to 2019. This rate is the most material and significant component in the retail rate calculation for Evergy Kansas Central's annual request with the KCC to adjust retail prices to include updated transmission costs through the TDC.
Evergy Metro TFR
Evergy Metro's TFR, effective in January 2020, includes projected 2020 transmission capital expenditures and operating costs and is expected to decrease annual transmission revenues by $1.7 million when compared to 2019. This rate is the most material and significant component in the retail rate calculation for Evergy Metro's annual request with the KCC to adjust retail prices to include updated transmission costs through the TDC.