XML 87 R22.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
Environmental Costs
12 Months Ended
Dec. 31, 2019
Environmental Remediation Obligations [Abstract]  
Environmental Costs ENVIRONMENTAL COSTS

The following table displays the activity and balances associated with accruals related to environmental costs included in other current liabilities and other long-term liabilities:
 
 
2019
 
2018
In thousands
 
 
 
 
Balance at January 1
 
$
5,531

 
$
6,057

Additions to accrual
 
1,122

 

Payments
 
(569
)
 
(944
)
Changes in foreign currency exchange rates
 
(6
)
 
418

Balance at December 31
 
$
6,078

 
$
5,531



13. ENVIRONMENTAL COSTS (CONTINUED)

Bloomfield

In August 2008, the Company completed its purchase of the portion of the Bloomfield campus that Kaman Aerospace Corporation had leased from NAVAIR for many years. In connection with the purchase, the Company has assumed responsibility for environmental remediation at the facility as may be required under the Connecticut Transfer Act (the “Transfer Act”) and it continues the effort to define the scope of the remediation that will be required by the Connecticut Department of Environmental Protection (“CTDEP”). The transaction was recorded by taking the undiscounted estimated remediation liability of $20.8 million and discounting it at a rate of 8% to its present value. The fair value of the Navy Property asset, which at that time approximated the discounted present value of the assumed environmental liability of $10.3 million, is included in property, plant and equipment, net. This remediation process will take many years to complete.

The following represents estimated future payments for the undiscounted environmental remediation liability related to the Bloomfield campus as of December 31, 2019:
In thousands
 
2020
$
172

2021
653

2022
151

2023
184

2024
387

Thereafter
4,956

Total
$
6,503



Other

In 2014, the Company sold its former manufacturing facility in Moosup, Connecticut to TD Development, LLC ("TD"). In connection with the sale, the Company agreed to contribute $4.0 million in cash to an escrow account over a four-year period to fund a portion of TD's environmental remediation work performed on the site. The Company funded $1.6 million to the escrow account between 2014 and 2015. TD stopped work on the site in 2016 and defaulted on its obligations under the sale agreements. From 2016 to 2018, the Company funded $2.4 million to a separate environmental escrow account due to TD's work stoppage.

In December 2016, the Company filed a summons and civil complaint against TD, which was subsequently amended in April 2017. The amended complaint alleged breach of contract, default by TD and unjust enrichment, and sought damages and other equitable relief against TD, including the return to the Company of all amounts held in the environmental escrow accounts. On December 21, 2018, the court entered an order and judgment favorable to the Company, which granted its application to confirm an arbitration award. The judgment provides that TD is not entitled to any of the amounts held in the escrow accounts nor any accrued interest, and the funds held in the escrow accounts shall be released to the Company. Additionally, the court awarded the Company compensatory damages, including reasonable legal fees, costs and expenses, and interest on the amounts awarded, but unpaid. In February 2019, the Company received the remaining balance of the escrow account ($0.7 million), which was added to the Company's accrual related to this matter. As of December 31, 2019, the Company has not recorded any amounts for compensatory damages, reasonable legal fees and costs and expenses from the arbitration award. The accrual related to the Moosup facility was $3.1 million as of December 31, 2019.

The Company's environmental accrual also includes estimated environmental remediation costs that the Company expects to incur at the former Music segment’s New Hartford, CT facility and the Company’s facility in Rimpar, Germany. The Company continues to assess the work that may be required at each of these facilities, which may result in a change to this accrual. For further discussion of these matters, see Note 19, Commitments and Contingencies.