COMMITMENTS AND CONTINGENCIES

AH-1Z Program

The Company is currently engaged in discussions with its customer to resolve the technical and design issues experienced on the AH-1Z attack helicopter program that caused production and delivery delays. Engineering design changes were made after the contract date, resulting in excess costs associated with design modification and rework of parts. As a result of these technical issues and schedule delays, the Company has incurred additional costs outside the scope of work for its original contract and, under the provisions of the contract, has filed claims with its customer requesting additional consideration for work performed. Costs associated with these claims is included in inventory as of July 3, 2015. See Note 8, Inventories, for amounts capitalized into inventory associated with unanticipated contract costs.
 
On April 23, 2015, the Company received a $24.0 million warranty claim from its customer for costs incurred due to rework performed on delivered cabins. The Company is in the process of evaluating this claim; however, based on the Company's preliminary understanding it does not believe there is a legitimate basis for the claim. The Company has signed an agreement with the customer to enter into non-binding mediation in order to attempt to resolve all pending claims and disputes associated with this program. If a mutually acceptable resolution cannot be agreed upon, the Company intends to vigorously defend itself in this matter. As of July 3, 2015, no amounts have been accrued for this matter. If the Company is unsuccessful in settling the claims it has against the customer and/or settling the customer's claims against the Company, this could have a material impact on the Company's financial results and cash flows.

The Company is also in discussions with its customer regarding the acceleration of the delivery of aircraft to the U.S. Marines, which is likely to result in a scope change to the current contract. The Company has submitted a change in scope proposal to the customer and the parties are currently in negotiations. Dependent upon the outcome of these discussions and the disposition of the matters described above, the Company may be required to accrue amounts associated with its customer's claim or write-off a portion of the amounts currently recorded in inventory; however, the resolution of these matters cannot be determined at this time. There is no gross margin being recorded on sales associated with this program. Total program inventory is $44.1 million as of July 3, 2015, and there are currently sales orders of $7.0 million in backlog associated with this program.

New Hartford Property

In connection with the sale of the Company’s Music segment in 2007, the Company assumed responsibility for meeting certain requirements of the Connecticut Transfer Act (the “Transfer Act”) that applied to the transfer of the New Hartford, Connecticut, facility leased by that segment for guitar manufacturing purposes (“Ovation”). Under the Transfer Act, those responsibilities essentially consist of assessing the site's environmental conditions and remediating environmental impairments, if any, caused by Ovation's operations prior to the sale. The site is a multi-tenant industrial park, in which Ovation and other unrelated entities lease space. The environmental assessment process, which began in 2008, has been completed.

The Company's estimate of its portion of the cost to assess the environmental conditions and remediate this site is $2.4 million, all of which has been accrued. The total amount paid to date in connection with these environmental remediation activities is $0.5 million. A portion ($0.9 million) of the accrual related to this property is included in other accruals and payables and the balance is included in other long-term liabilities. The remaining balance of the accrual reflects the total anticipated cost of completing these environmental remediation activities. Although it is reasonably possible that additional costs will be paid in connection with the resolution of this matter, the Company is unable to estimate the amount of such additional costs, if any, at this time.

12. COMMITMENTS AND CONTINGENCIES (CONTINUED)

Bloomfield Property

In connection with the Company’s 2008 purchase of the portion of the Bloomfield campus that a Company subsidiary had leased from the Naval Air Systems Command (NAVAIR), the Company assumed responsibility for environmental remediation at the facility as may be required under the Transfer Act and continues the effort to define the scope of the remediation that will be required by the Connecticut Department of Energy & Environmental Protection. The assumed environmental liability of $10.3 million, all of which has been accrued, was determined by taking the undiscounted estimated remediation liability of $20.8 million and discounting it at a rate of 8%. This remediation process will take many years to complete. The total amount paid to date in connection with these environmental remediation activities is $10.0 million. At July 3, 2015, the Company has $4.6 million accrued for this environmental matter. A portion ($1.2 million) of the accrual related to this property is included in other accruals and payables, and the balance ($3.4 million) is included in other long-term liabilities. Although it is reasonably possible that additional costs will be paid in connection with the resolution of this matter, the Company is unable to estimate the amount of such additional costs, if any, at this time.

Other Environmental Matters

The Company has been notified by the Environmental Protection Agency that it is a potentially responsible party ("PRP") at a Superfund Site. At July 3, 2015, the Company had no amount accrued for this matter, as it is unable to estimate the amount of costs, if any, that might be incurred in connection with the remediation of this site. In making this determination, the Company considered all available information related to the site; specifically, the continued identification of PRPs and the inability to determine the proportion of total responsibility attributable to each PRP at this time. As more information is received, the Company will reassess its ability to estimate its portion of the cost for remediation, taking into consideration the financial resources of other PRPs involved in the site, their proportionate share of the total responsibility for waste at the site, the existence of insurance and the financial viability of the insurer.